Planning policy monitoring

Contents

Assessment of housing land supply

Introduction

The National Planning Policy Framework (NPPF) says that local planning authorities should illustrate the expected rate of housing delivery through a housing trajectory for the plan period and set out how they will maintain delivery of a five-year supply of housing land to meet their housing target.

All local authorities are required to identify and update annually a supply of specific deliverable sites sufficient to provide a minimum five years’ worth of housing against their housing requirements set out in adopted strategic policies or against their local housing need where the strategic policies are more than five years old. The NPPF states that where planning authorities cannot demonstrate a five-year supply, the relevant policies for the supply of housing should not be considered up-to-date and the ‘presumption in favour of sustainable development’ should apply. This means granting consent unless the application of policies in the framework that protect areas or assets of particular importance provides a clear reason for refusing the development proposed or the adverse impacts of doing so would ‘significantly and demonstrably’ outweigh the benefits when assessed against the policies in the framework taken as a whole. The ability to identify a five year supply of deliverable housing is therefore significant in dealing with planning applications for housing.

Local planning authorities should also identify a supply of specific developable sites or broad locations for growth for years 6 to 10 and where possible, for years 11 to 15 of the plan.

This sets out the deliverable and developable housing land supply for North Northamptonshire up to 2031 and identifies the current five-year land supply position. The full picture for the North Northamptonshire area is provided within the Authority’s Monitoring Report (AMR).

Housing requirement

The North Northamptonshire Joint Core Strategy (JCS) was adopted in July 2016. It sets out the housing requirements for the area. Policy 28 of the JCS sets out the following housing requirements across North Northamptonshire:

Table 1: Share of objectively assessed needs in the housing market area

AreaAnnual average dwellings 2011-31

Housing requirement

(2011-31)

Corby Borough Requirement4609,200
Corby Borough Strategic Opportunity(710)(14,200)
East Northamptonshire District4208,400
Kettering Borough52010,400
Borough of Wellingborough3507,000
North Northamptonshire

1,750

(2,000)

35,000

(40,000)

The distribution of housing in the JCS is urban focused, with the four growth towns being defined as the most sustainable locations for development. The Sustainable Urban Extensions in the urban areas are the key building blocks for North Northamptonshire for the plan period and beyond. The plan also supports development to meet local needs and aspirations in the rural area.

The housing requirements set out in Policy 28 of the Joint Core Strategy (JCS) applied until July 2021, when the plan became 5 years old. National policy (NPPF, paragraph 78) states that where strategic policies are more than five years old the supply should be assessed against Local Housing Need (LHN) calculated using the Government’s standard method.

Table 2: Local housing need for North Northamptonshire from the new standard method

Type of methodTotal
Total Dwelling Stock160,328
Step 1. Annual Dwelling Stock Increase (0.8%)1,283
Affordability Ratio (2019-23)7.95
Uplift156%
Step 2. Housing Need2,002

The approach to reporting housing land supply on a North Northamptonshire-wide basis rather than staying with the former local planning authority areas (as some other new unitary councils in the UK do) was agreed at the North Northamptonshire Planning Policy Executive Advisory Panel in June 2021.

Identifying the supply of deliverable and developable sites

Existing planning consents do not represent the only source of housing land supply when identifying deliverable or developable sites. As referred to above, the local authority is required to identify five years’ worth of deliverable sites and 6 -15 years’ worth of developable sites.

The NPPF defines what is meant by deliverable in the glossary at Annex 2:

To be considered deliverable, sites for housing should be available now, offer a suitable location for development now, and be achievable with a realistic prospect that housing will be delivered on the site within five years. In particular:

a) sites which do not involve major development and have planning permission, and all sites with detailed planning permission, should be considered deliverable until permission expires, unless there is clear evidence that homes will not be delivered within five years (for example because they are no longer viable, there is no longer a demand for the type of units or sites have long term phasing plans).

b) where a site has outline planning permission for major development, has been allocated in a development plan, has a grant of permission in principle, or is identified on a brownfield register, it should only be considered deliverable where there is clear evidence that housing completions will begin on site within five years.

Sites falling within category b are listed below.

Major sites with outline consent

LocationPlanning application numberSite addressDescriptionTotal development sizeTotal included in 5 yearsJustification for inclusion in housing supply
RothwellNK/2022/0372Land to the west of Rothwell, Rothwell Central, Rothwell, KetteringResidential development of up to 220 dwellings with access only considered22080The site (RO/088a) is allocated under Policy ROT3 of the Kettering Site Specific Part 2 Local Plan. Access is provided through Rothwell North. Rothwell North Phase 1 is complete. Phase 2 (NK/2021/0904), Phase 3 (NK/2023/0108) and Phase 4 (NK/2023/0620) are all under construction. This site will form the next phase. Outline consent was granted for 220 dwellings on 29/11/2024. Reserved Matters (NK/2025/0020) for 186 dwellings was granted 06/06/2025. Start on site estimated in 2027/28. It has been assumed there will be 1 outlet delivering 30 dwellings in 2028/29 and 50 in the following year.
RushdenNE/21/00518/OUTLand Between Old Railway Line and John Clark WayOutline: For up to 39 Residential Dwellings (All Matters reserved except Access)3929Outline consent was allowed on Appeal on 25/06/2024. A Flood Risk Assessment & Drainage Strategy; Ground Investigation Report; Preliminary Contamination Risk Assessment; and Site Investigation and Great Crested Newt Working Method Statement were submitted as part of the appeal process. Accordingly, firm progress has been made with site assessment work and no significant constraints to development have been identified. Reserved Matters are anticipated to be submitted and granted within 3 years. Estimated that 9 dwellings will be delivered in 2028/9 and 20 in the following year.
Corby19/00351/OUTPriors Hall Zone 2 & 3: remaining unitsApplication for outline planning permission with all matters reserved except for means of access, for the development of a mixed use urban extension to include: residential development of up to 3,500 dwellings (C3)3500 with 2316 remaining at 1st April 2025227The outline consent was granted on 3/5/2021 and a number of Reserved Matters have been granted consent and are delivering dwellings currently. Delivery questionnaires have been received from Urban & Civic for both Zones 2 and 3 (Pages 75-80 HLS App 4). These project rates building up to 180 dwellings on Zone 2 and 100 on Zone 3. The totals of these have been combined and then the residual of the Reserved Matters applications mentioned specifically within the trajectory is included on this entry. In 2024/5 Priors Hall delivered 207 dwellings, peak delivery to date was 269 dwellings in 2017/18. The total projected for each year across zones 2 & 3 in the 5 year period are: 177, 229, 234, 270, 280. A new Reserved Matters application for Parcel 6 Zone 2 is expected to be submitted soon by Allison Homes for 161 dwellings (Developer acquires land for more homes at Corby site - BBC News). Urban and Civic are understood to be marketing a further 3 parcels next year.
Corby17/00180/OUTCorby West SUEOutline application for a sustainable urban extension comprising of 4,500 dwellings, 46,850sqm of Class B1/B2, two local centres/mixed use A1-A5, B1, C2, C3 and D1/D2, secondary schools, primary schools, public open space, drainage, access and associated infrastructure works. Demolition of existing buildings450087Phase 1 reserved matters have been submitted and are being considered by the Council (NC/24/00335/REM, NC/24/00339/REM, NC/24/00341/REM, NC/24/00382/REM, NC/24/00383/REM, NC/24/386/REM). All pre-RM application conditions are approved including a site-wide design code (NC/23/00444/CON). Delivery rate numbers are from previous 23/24 developer response. Barratt David Wilson and Taylor Wimpy are promoting the site and intend to deliver half the site. The remaining land will be sold to other developers. A PPA is in place to assist with determining applications. There is strong developer interest and reports of strong market demand.
Corby15/00138/OUTLand South of Brooke Weston - Oakley Vale phase 8 and 9New residential development comprising up to 530 dwellings, a local centre (to include uses within Use Classes C3, A1, A2, A3, A4, A5, B1 and D1), a primary school/community facility site, informal open space, multi-use games area, playing fields, revised access and car parking at Great Oakley Community Hall, together with landscaping, pedestrian/cycle and vehicular routes including access onto Lewin Road, Bennett Road, Mill Hill and Chepstow Road, diversion of Footpath UB30, and other infrastructure and associated works53075NC/23/00264/RVC106 for a modification to the planning obligation to change the school site location is pending a decision, but the relocation of the school is agreed in principle. NC/24/00400/NMA Design Code pending decision - NC/25/00107/CON Phasing plan pending decision. A delivery questionnaire was received (Page 72 HLS App 4) anticipating RMs submission at the end of 2025. All site assessment work has been completed. Discharge of conditions anticipated mid 2026 with commencement on site at the end of 2026 and first dwelling completed Q3 of 2027. Developer anticipated delivery: 25 units in 2027/28 and 50 for the next 3 years then rising to 100 dwellings at the peak. A more cautious approach has been taken pushing the anticipated delivery back 12 months in case there is any delay in determining the pending applications or discharge of conditions. Oakley Vale has previously had good rates of delivery.
RushdenNE/22/00851/OUTLand east of A6 Bypass/ Bedford RoadErection of up to 450 dwellings, a community / retail and / or health facility, improvement works to the existing A6 / Bedford Road roundabout including provision of shared pedestrian / cycle access, parking, landscaping, drainage features, open space, and associated infrastructure (All matters reserved except access from the A6 / Bedford Road)450110Outline consent was granted in January 2025. Pre-application advice has been given regarding reserved matters (NE/24/00928/QRY). A delivery questionnaire has been received (page 44 HLS App 4). Commencement on site anticipated Feb 2027, first dwelling completion in Feb 2028, and site completed June 2037. Bellway are expected to submit Reserved Matters application soon. A PPA is being prepared.

Grant of permission in principle

LocationPlanning application numberSite addressDescriptionTotal development sizeTotal included in 5 yearsJustification for inclusion in housing supply
Stoke AlbanyNK/2024/0250Stoke Farm, Ashley Road, Stoke Albany, LE16 8PZPermission in Principle for up to 5 no. serviced self/custom build plots55Small site with extant consent, anticipate details can be provided and dwellings delivered within 5 years. No known ownership, viability or infrastructure constraints.

Allocated in a development plan

LocationPlanning application numberSite addressDescriptionTotal development sizeTotal included in 5 yearsJustification for inclusion in housing supply
WellingboroughWP/15/00605 & WP/15/00481WEAST - overall anticipated delivery and residual from specific applicationsAllocation PBW Policy Site 1, JCS Policy 293650680WEAST, also known as Stanton Cross is currently delivering well. Completions in 2045/5 were 397 dwellings on 7 Parcels. The site promoter anticipates an average delivery of 300 dwellings per year. This seems reasonable having regard to last years’ completions and that 167 dwellings have already been completed within the first 6 months of 2025/26. This entry is calculated as the residual amounts from the RM applications currently listed separately in the trajectory to give a total of 300 dwellings. There are a number of parcels with approved RMs and some of those have now commenced (NW/22/00905, NW/22/00755) and started delivery in 2025/6. There also a number of pending Reserved Matters applications (NW/22/00776/REM, NW/22/00777/REM, NW/22/00908/REM, NW/23/00017/REM, NW/23/00032/FUL, NW/23/00486/FUL, NW/22/00828/REM, NW/22/00829/REM, NW/23/00060/REM, NW/22/00833/REM) which will deliver over the later years.
WellingboroughNW/24/00138/OUTWellingborough North - Phase 2Allocation PBW Policy Site 2, JCS Policy 291000400Phase 1 of WNORTH also known as Glenvale Park has been delivering well. In 2024/25 310 dwellings were completed. There are a few remaining parcels to complete. A new Outline for Phase 2 was approved in principle subject to signing the S106 on 26/06/2025. The S106 is nearing completion and is expected to be signed shortly. PPAs are in progress for Design Codes, Phasing and Landscaping and another PPA is being prepared in relation to delivery of the access road. A Delivery Questionnaire has been received from Glenvale Park LLP (page 20 HLS App 4) where they anticipate the S106 to be signed in October, the discharge of conditions to occur in December 2025 and commencement on Site in early 2026 with the first dwelling completed in February 2027. They have projected 50 completions in 2026/27. Whilst this may well be achievable, the Council has proposed a more conservative estimate and pushed back the trajectory by one year to see 50 completions 2027/8. It is understood that three Developers are already on board to deliver Phase 2 and pre apps/Reserved Matters will be submitted as soon as the Design Codes are approved.
Wellingborough Windsor RoadAllocation PBW Policy Site 36060The site is allocated in the Plan for the Borough of Wellingborough under Policy Site 3 for 60 dwellings. The site is jointly owned and promoted by Hampton Brook and Greatwell Homes (a Registered Housing Provider). Part of the site was previously owned by the Borough Council of Wellingborough, but it was transferred to Greatwell Homes to aid delivery. A delivery questionnaire has been received (page 106 HLS App 4) which proposes a pre-app in 2026 before the submission of an outline application. Reserved Matters are anticipated during 2027/28 to enable commencement on site in mid 2028. The questionnaire refers to delivery of 120 dwellings. There may well be more capacity in the site than assumed in the local plan however as this has not yet been tested the capacity has been restricted to the local plan assumptions for the purposes of the housing land supply. The proposed delivery rates have therefore been reduced from 40 dwellings per annum to 30 for the final two years of the 5 year period. The landowner has continued to put the site forward for 84 dwellings through call for sites (Call For Sites - External) for the local plan – see Site Ref 129. There are no known barriers to delivery and due to the scale of the development there will not be significant infrastructure requirements.
Wellingborough Land Between Finedon Road and Nest LaneAllocation PBW Policy Site 410050The site is allocated in the Plan for the Borough of Wellingborough under Policy Site 4 for approximately 100 dwellings. A delivery questionnaire has been received (page 41 HLS App 4). The Borough Council of Wellingborough transferred the site to Greatwell Homes (a registered housing provider) to aid delivery. Pre-app is anticipated 2026/7, an outline application 2027 with commencement on site 2028. It is noted that surveys are still to be completed although as the site is a former sports ground with a frontage onto Nest Lane there are not anticipated to be significant physical constraints. Standard biodiversity surveys will be required to demonstrate compliance with BNG and the development plan policy. The start date is considered achievable; however the delivery rate has been reduced from 64 dwellings to 50 per year as the capacity of the site has not yet been confirmed.
Wellingborough Former PO Sorting Office, Midland RoadAllocation PBW Policy TC82374The site is allocated in the Plan for the Borough of Wellingborough under Policy TC8 for approximately 23 dwellings. The plan was anticipating a mixed used development including new shops with residential above. This approach has not proved to be deliverable. The site does however remain a key redevelopment priority within the town centre. An application (NW/24/00564) has been received for Demolition of Former Wellingborough Post Office and Construction of Residential Development consisting of 74 apartments (45 x 1 bed and 29 x 2 bed). The application is pending determination, but an Extension of Time has been agreed to enable the application to go to committee for determination on either 8/10/25 or 5/11/2025. Assuming a positive outcome then it is anticipated that there is a realistic prospect that the apartments will be delivered within the 5 year period.
Wellingborough Leys Road/Highfield RoadAllocation PBW Policy Site 74040The site is allocated in the Plan for the Borough of Wellingborough under Policy Site 7 for approximately 40 dwellings. A delivery questionnaire has been received from the owner (page 59 HLS App 4) which anticipates submission of a pre-application in March 2027, a detailed application in June 2027 with commencement on site in June 2028. These delivery rates seem reasonable. It is a relatively small brownfield site and whilst some decontamination may be required it is anticipated that there will be minimal infrastructure requirements. The landowner has continued to put the site forward for 40 dwellings through call for sites (Call For Sites - External) for the local plan – see Site Ref 342.
Finedon PBW allocation Milner RoadAllocation PBW Policy Site 86015The site is allocated in the Plan for the Borough of Wellingborough under Policy Site 8 for approximately 90 dwellings. The first phase of the site has been delivered. This is the remaining section and capacity has been estimated as 60 dwellings. The landowner has continued to put the site forward for 82 dwellings through call for sites (Call For Sites - External) for the local plan – see Site Ref 053. An initial assessment continues to show no barriers to delivery. It is a relatively small site and there are not likely to be significant infrastructure requirements. It is therefore considered that there is a realistic prospect that housing will be delivered on the site within five years.
Irchester Land off Austin CloseAllocation Irchester NP Policy Site 37515The site was allocated within the Irchester Neighbourhood Plan Policy 3. The site was one of two allocated in the plan, the other site is nearing completion. This site is owned by the Parish Council who are currently in advanced negotiations regarding the sale and delivery of the site. An indicative scheme is under discussion and it is considered reasonable that the site can start to deliver dwellings within the 5 year period. It is a medium sized site with no major infrastructure requirements anticipated.
Braybrooke Top Orchard (The Old Rectory), BraybrookeAllocation KSS Policy BRA233The site was allocated in the Kettering Site Specific Plan under Policy BRA2 for a maximum of 3 dwellings. This is a small site with no known barriers to development and could therefore be reasonably deliverable within 5 years. NK/2024/0054 application received and pending determination. This application is for 5 dwellings and includes both sites allocated under BRA2 and H1.
Braybrooke Top YardAllocation Braybrooke NP Policy H122The site was allocated in the Braybrooke Neighbourhood Plan under Policy H1 for 2 dwellings. This is a small site with no known barriers to development and could therefore be reasonably deliverable within 5 years. NK/2024/0054 application received and pending determination. This application is for 5 dwellings and includes both sites allocated under BRA2 and H1.
Burton Latimer Land adjacent to the Bungalow, Higham RoadAllocation KSS Policy BLA577The site (BL/038) was allocated in the Kettering Site Specific Plan under Policy BLA5 for up to 7 dwellings. This is a small site with no known barriers to development and therefore has a realistic prospect that housing will be delivered on the site within five years.
Desborough2016/0044Desborough (land to the south of)Allocation KSS Policy DES530477KET/2016/0044 was allowed on appeal. A number of the conditions were discharged and a variation to the S106 agreed. A Non-material Amendment KET/2019/0027 was made but subsequently withdrawn and the consent lapsed. The scale of the amendment was not considered appropriate and a revised application was suggested. Discussion on the site remains ongoing and a new application is expected. A Reserved Matters Application remains pending NK/2021/0372. Bellway is the lead developer. It is estimated that a revised scheme can be approved and development commenced within 5 years. The development is acceptable in principle, a number of details have already been agreed and site assessment work was undertaken for the previous consent.
Geddington Geddington Sawmill, GeddingtonAllocation KSS Policy GED21212Pre-app received PRE/2024/0097. Delivery questionnaire received (page 84 HLS App 4). Detailed application anticipated March 2026, commencement on site 2027.
Geddington Geddington South EastAllocation KSS Policy GED32121Pre-app received PRE/2024/0098. Delivery questionnaire received (page 87 HLS App 4 ). Application due to be submitted 2025, commence on site 2026.
Kettering Yards Quarter: Soans Yard (Y2)*, KetteringAllocation
Kettering TCAAP Policy Y2
1414Allocation with Outline application pending NK/2024/0468 as at 31/03/2025 but approved 10/09/2025. Reserved Matters received 25/01310/REM.
KetteringNK/2021/0292East Kettering: Phase 2Allocation JCS Policy 293383828Phase 1 is continuing to deliver well. NK/2021/0292 for Phase 2 has a resolution to grant, completion of the S106 is expected soon. In anticipation of the planning decision the Developer is preparing pre commencement submissions. The first round of pre-commencement applications are being prepared for submission including those relating to the Design Code(s). The Education Authority / DfE are expected to submit RM applications in December for primary and secondary schools. Negotiations are currently also taking place with the Developers on the sale of individual residential parcels to House builders with a view to submitting RMs. Delivery questionnaire received (page 38 HLS App 4) suggesting 311 dws in 2025/6 and then 384dw pa. Included a more conservative estimate of 280 dws pa having regard to past delivery rates. Assumed a total of 280 across the site from 2026/7 and 6-8 outlets of 40-50dws pa.
Rushden20/01453/OUT (pending)Rushden East Urban Extension, Liberty Way (phases 1-3) High HaydonAllocation JCS Policy 33, EN LP Policy EN292200180Pending application, with a PPA in place, S106 discussions ongoing expect determination early 2026. Previous A45 junction mitigation has cause delays however mitigation now agreed in principle. Update from National Highways May 2025 confirms that the applicant is collaborating with the developers for Knights Farm application regarding the proposed mitigation works at Rushden Lakes roundabout and that good progress has been made regarding the traffic modelling evidence and operational performance. A Stage 1 Road Safety Audit is to be undertaken shortly. Once this is completed discussions will continue to agree the trigger points for the works. A Masterplan Framework Document has been prepared which can be used to guide Reserved Matters applications and Design Codes. Reserved Matters expected in 2027 with start on site in 2028. The site is being promoted by a consortium of Taylor Wimpy and Barratt David Wilson. Anticipate 4 outlets at circa 50dwpa. Expect there to be strong market demand and proximity to Rushden Lakes and Universal Studios expected to enhance the area’s appeal and drive demand. Anticipate peak delivery rates at 200dwpa and complete by 2040/41
RushdenNE/21/01124/OUT (pending)Rushden East Urban Extension, Liberty Way (phase 4 - Knight's Farm)Allocation JCS Policy 33, EN LP Policy EN29500175Pending application with a PPA in place, S106 discussions ongoing expect determination early 2026. National Highways have agreed broad mitigation in principle. SPA mitigation also has broad agreement from Natural England. A Masterplan Framework Document has been prepared which can be used to guide Reserved Matters applications and Design Codes. Reserved Matters expected in 2027 with start on site in 2028. Anticipate 2 outlets at circa 50dwpa. Expect there to be strong market demand and proximity to Rushden Lakes and Universal Studios expected to enhance the areas appeal and drive demand. Anticipate peak delivery rates at 100dwpa and complete by 2033/34
CorbyNC/23/00409/DPA pending decision Yr end 2024/25Former Co-Op Site Alexandra RoadAllocation CP2LP Policy TC3 Proposed mixed use residential-led development comprising 150 dwellings (C3 Use Class), 2,165sqft of Class E Use floor space including external soft and hard landscaping, opens space provision, car and cycle parking, renewable energy provision and ancillary infrastructure.150150Committee on 04/12/2024 agreed approval subject to conditions 19/09/2025 decision issued - Demolition and preparation of oversite has commenced under NC/22/00195/PADEM

The latest National Planning Practice Guidance (NPPG) (Paragraph: 007 Reference ID: 68-007-20190722) further advises that:

In order to demonstrate 5 years’ worth of deliverable housing sites, robust, up to date evidence needs to be available to support the preparation of strategic policies and planning decisions. Annex 2 of the National Planning Policy Framework defines a deliverable site. As well as sites which are considered to be deliverable in principle, this definition also sets out the sites which would require further evidence to be considered deliverable, namely those which:

  • have outline planning permission for major development
  • are allocated in a development plan
  • have a grant of permission in principle
  • are identified on a brownfield register

Such evidence, to demonstrate deliverability, may include:

  • current planning status – for example, on larger scale sites with outline or hybrid permission how much progress has been made towards approving reserved matters, or whether these link to a planning performance agreement that sets out the timescale for approval of reserved matters applications and discharge of conditions
  • firm progress being made towards the submission of an application - for example, a written agreement between the local planning authority and the site developer(s) which confirms the developers’ delivery intentions and anticipated start and build-out rates
  • firm progress with site assessment work
  • clear relevant information about site viability, ownership constraints or infrastructure provision, such as successful participation in bids for large-scale infrastructure funding or other similar projects

The NPPF also defines what is meant by developable:

‘To be considered developable, sites should be in a suitable location for housing development with a reasonable prospect that they will be available and could be viably developed at the point envisaged.’

The following sources of housing land supply have been examined to identify sites which are deliverable or developable:

  • Existing commitments (sites currently under construction and sites with valid planning consent)
  • Sites with a resolution to grant consent subject to S106 agreements
  • Site where pre-application discussions are well advanced
  • Sites in adopted Development Plans
  • Additional capacity within the Sustainable Urban Extensions (SUEs)
  • The North Northamptonshire Brownfield Land Register
  • Housing for older people, including residential institutions in Use Class C2
  • Communal accommodation
  • Housing delivered through permitted development rights or prior notification such as flats above shops or office conversions
  • Windfall sites (see below)

Windfall allowance

The NPPF defines windfall sites as those which have not specifically been identified in the development plan. They normally comprise previously developed sites that become unexpectedly available. Local planning authorities can make a windfall allowance in the five year supply if they have compelling evidence that such sites have consistently become available and will continue to provide a reliable source of supply.

Evidence of past windfall delivery is provided in Appendix 1. The data has been collected slightly differently across the previous authority areas. It does however clearly demonstrate that these have made a significant contribution to the supply of housing in the area. The total amount of windfall completions has been gradually falling over recent years as completions on sites allocated within the local plan continue to rise. The contribution of small sites is however fairly consistent. It is therefore reasonable to assume this source of supply will continue at a similar rate. An allowance of the average of these years on sites below 10 dwellings can be applied to the anticipated housing supply. A separate windfall allowance is applied for each of the previous areas as this takes account of the slight differences in the nature of these areas, for example the Corby area has traditionally had less windfall as it is a largely reliant on large new allocations and has fewer settlements. In addition, separating the windfall total provides greater clarity for infrastructure providers of the location of anticipated supply e.g. for transport modelling. In order to avoid double counting of smaller sites with an extant planning permission, this element of supply is only included from year 3 onwards in the 5-year assessment period.

Lapse rate

It is reasonable to assume that not all planning permissions granted will be implemented, particularly on the small sites. In order to ensure a robust approach, there is a need to make an allowance for non-implementation (or lapse rate) of a proportion of the permissions. An assessment of the actual lapses in the area has been undertaken. The results are shown in Appendix 2.

Based on the local evidence it is reasonable to apply a 9% lapse rate to sites with permission for less than 10 dwellings within the Kettering and Wellingborough areas, an 8% lapse rate in Corby and a 4% rate within the East Northants area. Not all of the sites with more than 10 dwellings will all be completed within the plan period; this particularly applies to the SUEs and other strategic sites. Delivery rates on these sites are however dealt with in the trajectory, rather than through application of a lapse rate.

Communal accommodation

It is reasonable to include communal accommodation as part of the supply where this could be considered as part of the dwelling stock. This includes student accommodation, houses in multiple occupation and housing for older people including residential institutions in Use Class C2. Total net change for communal accommodation is as reported in the Housing Flows Return and as used for the Housing Delivery Test. Calculated as number of bedrooms adjusted by the communal net change national ratio of 1.9. The ratios for both net student and net other communal accommodation are found in the Housing Delivery Test measurement rule book.

Housing trajectory

Those sites from the sources listed above which have been considered as deliverable or developable are in Appendix 3. For each site an assessment has been made as to when the site can commence and the likely build out rates, this takes account of information from the site’s developers where this is available. On the smaller sites (sites of less than 10 dwellings) it has been assumed that they will be delivered before the consent expires (unless there is evidence to the contrary) then a lapse rate has been applied to the total. Dwellings under construction as at 31 March 2025 are assumed to be completed by 31 March 2026 unless there is specific local knowledge that this is not likely to be the case. For other sites, evidence from site promoters has been taken into account where available alongside information on past delivery rates. Delivery questionnaires were sent to site promoters of all major sites and site allocations.

A significant amount of literature is published exploring the delivery of major residential development. Inevitably, each example is unique and specific to the local circumstances. For this reason delivery information from the site promoters, as they know the specific details of the site, is taken into account together with evidence of past delivery. Certain trends can however be identified. Whilst there will be many influences on a forecast housing trajectory from a strategic site, it will essentially be dictated by the rate of sales that the site’s developers want and are able to achieve in light of site conditions, business strategies and wider market demand. A large site would typically involve multiple developers who would be active at any one time. The precise number of active sales outlets at any one time could vary, but would typically start with a few (especially when creating a new ‘place’) and increase over time to a steady state. How many active outlets exist on one site will vary depending on the specific circumstances. For well-established sites in strong areas this could get as high as 10 to 15 outlets. Some of the larger national builders can even operate more than one outlet off a single site, and run these as entirely separate construction and sales outlets under different brands or aimed at different market segments. As the number of separate sales outlets grow, the overall build rate will increase. Evidence suggests that completions from a single outlet can range from around 30 to 50 units per annum.

The purpose of the housing land supply report is not to predict what will be built, but to identify land supply that is deliverable. The council can influence land supply, but it can have limited impact on the wider economic and financial climate that may affect house building and sales.

Five year supply of deliverable sites

Appropriate buffer

When identifying a five year supply, the NPPF requires the addition of a 5% buffer to the housing requirement to add choice and competition in the market. This rises to a 20% buffer where there has been significant under delivery over the previous three years. There is also an option for a 10% buffer on production of an annual position statement agreed by the Secretary of State.

The NPPF (paragraph 78) says that significant under delivery will be measured against the Housing Delivery Test and will be defined as delivery below 85% of the housing requirement.

The 2023 Housing Delivery Test published in December 2024 remains the most up-to-date published version and covers the period 2020/21, 2021/22 and 2022/23.

Housing Delivery Test (%) = Total net homes delivered over three year period / Total number of homes required over three year period

Details of how the homes required is calculated is provided in a technical note. It is based on projections of household growth and affordability. In order to reflect the national disruption caused to housing delivery by the pandemic to starts and completions, construction, and monitoring of completions, the period for measuring the homes required in 2020 and 2021 year has been reduced by 4 months.

The homes delivered figure is based on the net additional dwellings calculated by local authorities with an adjustment for communal accommodation. The following table sets out the results for North Northamptonshire.

Table 3: Housing delivery test - 2023 Measurement

Homes2020/212021/222022/23Total
North Northamptonshire Homes Required1,1641,7691,8734,806
North Northamptonshire Homes Delivered1,7881,5882,0615,438
HDT   113%

It can be seen that delivery does not constitute significant under delivery as defined in the NPPF. It is therefore appropriate to continue to use a 5% buffer.

Treatment of past under-provision

When measuring five year supply against development plan targets the Planning Practice Guidance states that ‘The level of deficit or shortfall will need to be calculated from the base date of the adopted plan and should be added to the plan requirements for the next 5 year period (the Sedgefield approach) then the appropriate buffer should be applied. If a strategic policy-making authority wishes to deal with past under delivery over a longer period, then a case may be made as part of the plan-making and examination process rather than on a case by case basis on appeal’ (Paragraph: 031 Reference ID: 68-031-20190722).

Where the standard method for assessing local housing need is used as the starting point in forming the planned requirement for housing, the Planning Practice Guidance states that ‘Step 2 of the standard method factors in past under-delivery as part of the affordability ratio, so there is no requirement to specifically address under-delivery separately when establishing the minimum annual local housing need figure’ (Paragraph: 031 Reference ID: 68-031-20190722).

As the JCS is over five years old, the JCS requirements are now superseded by local housing need using the standard methodology. On the basis of the above guidance there is no longer a need to take account of any shortfall against the JCS when calculating the 5 year housing land supply.

Five year supply requirement

The five year supply requirement is calculated below based on local housing need and the application of the 5% buffer.

Table 4: Five year supply requirement

Housing needTotal
Local housing need annual requirement2,002
5 year requirement10,010
5% buffer500.5
Total 5 year housing requirement10,511

Deliverable sites

Appendix 3 sets out the summary of the source of supply of deliverable and developable sites. It also takes account of the lapse rate and includes the windfall allowance. The schedule of sites provides a total supply of 11,017 dwellings within the five year period. The source of supply is summarised below.

Table 5: Source of housing supply 2025/26 - 2029/30

SourceDwellings
Sites with full* planning permission7,229
Sites with outline planning permission516
Sites with Permission in Principle5
Sites allocated in adopted plans2,913
Sites on a brownfield land register0
Lapse Rate-45
Windfall Allowance398
Total11,016

* Includes prior approval, certificate of lawful use and reserved matters.

Five year supply assessment measured against local housing need

The five year supply assessment for the area based on the information above is as set out below.

Table 6: Five Year Supply of Deliverable Housing Land

LevelSupplyTotal
AFive Year Requirement10,010
BPlus 5% Buffer10,511
CSupply of Deliverable Sites11,016
E5 Year Supply (C/B x 5)5.24

 

Appendix 1: Windfall

Wellingborough and Kettering

Year

Wellingborough

Total completions

Wellingborough

Windfall completions

Wellingborough

Windfall completions on sites of less than 10 dws

Kettering

Total completions

Kettering Windfall completions

Kettering

Windfall completions on sites of less than 10 dws

2011/121221224931324881
2012/13116636335132163
2013/142552357354052177
2014/153843237828226135
2015/163802658954750959
2016/172471707270669677
2017/182741659349549545
2018/1933913768644640130
2019/203541127935035063
2020/21347715344244256
2021/22327683441740957
2022/23562714075957636
2023/2473384444095050
2024/2593924115868728
Total537919108466841 857
Average38413660487 61

Corby and East Northamptonshire

YearCorby Total completionsCorby Windfall on sites of more than 10 dwsCorby Windfall completions on sites of less than 10 dwsEast Northamptonshire Total completionsEast Northamptonshire Total WindfallEast Northamptonshire windfall on sites of less than 10dws
2011/1248219616   
2012/134832099   
2013/143426018   
2014/1539014217   
2015/163693910   
2016/17349365   
2017/1859712436   
2018/1963214220   
2019/203714018   
2020/214188619   
2021/22420353044619072
2022/23380292127112038
2023/24366111122414548
2024/2533662032015282
Total559911492501261607240
Average436.194.517.931515260

Notes:

Windfall completions for Kettering 2011/2 - 2022/3 include large sites including Hanwood Park SUE

Appendix 2: Lapse Rates

Wellingborough Lapse Rates:

YearCommitments 10 and overLapses 10 and overLapse rate 10 and overCommitments less than 10Lapse less than 10Lapse rate less than 10
2011/127,051380.5%1913618.8%
2012/136,64400%18294.9%
2013/146,88200%201199.5%
2014/157,14200%2053014.6%
2015/166,90300%249187.2%
2016/177,679140.2%235229.4%
2017/187,7861201.5%229114.8%
2018/197,153100.1%210188.6%
2019/207,423700.9%1822312.6%
2020/217,51800.0%16821.2%
2021/227,225120.2%1852211.9%
2022/232,8744081142.0%12897.0%
2023/243,0391635.4%157117.0%
2024/252,95700.0%233135.6%
Average6,30532210.7%197178.8%

Notes:

The 120 dwellings that lapsed in 2017/18 were from a single planning application.

The 4081 dwellings that lapsed in 2022/23 were from 3 applications from the SUEs, there are a number of pending Reserved Matters Applications relating to these.

The 163 that lapsed in 2023/4 were from two applications.

Kettering Lapse Rates:

2011/2012 to 2017/2018

Year2011/122012/132013/142014/152015/162016/172017/18
Commitments on sites of 10 dws and more7,8078,4998,7619,0198,5178,3628,726
Lapses on sites of 10 dws and more53390001030
Lapse rate - sites of 10 dws and more0.68%0.46%0.00%0.00%0.00%0.12%0.34%
Commitments on sites of less than 10 dws242305258290390362389
Lapses on sites of less than 10 dws5737225191242
Lapse rate - sites of less than 10 dws23.55%12.13%8.53%1.72%4.87%3.31%10.80%

2018/2019 to 2024/2025

Year2018/192019/202020/212021/222022/232024/25Average
Commitments on sites of 10 dws and more9,0929,0049,2779,1728,3812,6858,254
Lapses on sites of 10 dws and more310361404019.46
Lapse rate - sites of 10 dws and more0.34%0.00%0.39%0.15%0.00%1.49%0.21%
Commitments on sites of less than 10 dws323341283245313205303.54
Lapses on sites of less than 10 dws3403826372422.46
Lapse rate - sites of less than 10 dws10.53%0.00%13.43%10.61%11.82%11.71%9.46%

Notes:

Figures not available for 2023/24 due to a change in monitoring systems.

East Northants Lapse rates:

Year2020/212021/222022/232023/42024/5Average
Commitments 10 and over1,2971,0371,0351,5851,6331,317.4
Lapses 10 and over0001002
Lapse rate - sites of 10 dws and over0.00%0.00%0.00%0.63%0.00%0.13%
Commitments less than 10304272298311258288.6
Lapse less than 1011141541111
Lapse rate - sites of less than 10 dws3.62%5.15%5.03%1.29%4.26%3.87%

Corby Lapse Rates:

2013/2014 to 2018/2019

Year2013/142014/152015/162016/172017/182018/19
Commitments at large sites (>10 dwellings) excluding the Sustainable Urban Extensions4,6574,8505,0604,9534,8655,365
Number of permitted dwellings lapsed79009500
Lapse Rate1.60%0%0%1.90%0%0%

2019/2020 to 2024/2025

Year2019/202020/212021/222022/232023/242024/25
Commitments at large sites (>10 dwellings) excluding the Sustainable Urban Extensions     4,584
Number of permitted dwellings lapsed2300000
Lapse Rate 0% 0% 0% 0% 0%0.00%

2011/2012 to 2017/2018

Year2011/122012/132013/142014/152015/162016/172017/18
Commitments remaining at small sites (<10 dwellings)43596186756663
Number of permitted dwellings lapsed20031741
Lapse Rate4.60%0%0%3.40%22%6%1.50%

2018/2019 to 2024/2025

Year2018/192019/202020/212021/222022/232023/242024/25Average
Commitments remaining at small sites (<10 dwellings)8393878588754772
Number of permitted dwellings lapsed0200611215
Lapse Rate0%1.80%0%0%6.82%14.67%44.68%7.53%

Appendix 3: Housing trajectory

The housing trajectory for the 5 year period.

Last updated 27 October 2025