Roadworks

Planned works

These are our larger-scale planned works that will be completed in addition to the ad-hoc repairs we carry out.

Major projects

Site nameTown or parishDurationStartFinish
Corby Station Link - Cycleway, Structure, infill and resurfacingCorby265 daysMonday 5 August 2024Summer 2025

Traffic signals

Site NameTown or parishDurationStartFinish
Croyland Road Wellingborough - Toucan crossingWellingborough49 daysTuesday 27 May 2025Tuesday 5 August 2025

Drainage

Site NameTown or parishDurationStartFinish
B670 - The Hill Middleton - New gullys and footwayMiddleton10 daysMonday 21 July 2025Wednesday 13 August 2025
Deenethorpe A43 - Culvert repairs phase 2Deenethorpe10 daysSaturday 25 October 2025Monday 10 November 2025
King's Cliffe - Culvert replacementKing's Cliffe8 daysMonday 29 September 2025Wednesday 8 October 2025
Geddington - Stamford Road - Ditch cleaningGeddington3 daysMonday 1 September 2025Friday 5 September 2025
Hargrave - Brook Street - New CulvertHargrave8 daysWednesday 8 October 2025Friday 17 October 2025

Accident and vandalism

Site nameTown or parishDurationStartFinish
Structure 3303 - Cross Way - Hands Farm - Masonary Parapet repairSouthwick2 daysMonday 4 August 2025Tuesday 5 August 2025
Structure Wakerly - Retaining WallWakerly5 daysMonday 11 August 2025Friday 15 August 2025
Struture 6433 - Hemmington House - A&V Repairs to North and South Parapet - Post & RailHemington4 daysMonday 11 August 2025Thursday 14 August 2025

Structures

Site NameTown or parishDurationStartFinish
Washbrook Ramp - Midland RoadRushden50 daysTuesday 27 May 2025Thursday 28 August 2025
5003 - Harringworth - Turtle Bridge parapet repairHarringworth20 daysMonday 28 July 2025Friday 22 August 2025

Traffic engineering / Minor improvements

Site NameTown or parishDurationStartFinish
Springfield Road - Oundle - Dropped kerbsOundleTBCTBCTBC
A6 Road Safety - Higham Road - Burton Latimer - SignalisationBurton Latimer43 daysMonday 21 July 2025Friday 3 October 2025
A5028 - Windmill Banks - Higham Ferrers - Pedestrian refuge worksHigham Ferrers10 daysMonday 25 August 2025Friday 5 September 2025

Surfacing and patching

Site nameTown or parishDurationStartFinish
A4300 Kettering - Stamford RoadKettering18 daysWednesday 6 August 2025Friday 29 August 2025
Pipewell - Desborough Road - PatchingPipewell15 daysMonday 29 September 2025Friday 17 October 2025

Last updated 04 August 2025