2022
Application number |
NN/21/00059/WASVOC |
---|---|
Location |
Storefield Plant, Gretton Brook Road, Earlstrees Industrial Estate, Corby, NN17 4BA |
Proposal | Variation of Condition 32 of planning permission ref: 20/00022/WASVOC to increase the stack height from 25m (currently permitted) to 35m |
Decision | Approved by the NNC Strategic Planning Committee on 11th April 2022 |
Decision date | 27 April 2022 |
Relevant documents |
Supporting InformationPlans |
Application number |
NN/21/00058/WASVOC |
---|---|
Location |
Storefield Plant, Gretton Brook Road, Earlstrees Industrial Estate, Corby, NN17 4BA |
Proposal | Variation of Condition 32 of planning permission ref: 20/00022/WASVOC to increase the stack height from 25m (currently permitted) to 35m |
Decision | Approved by the NNC Strategic Planning Committee on 11th April 2022 |
Decision date | 27 April 2022 |
Relevant documents |
Supporting InformationPlans |
2021
Application number |
NCC - 20/00047/WASFUL |
---|---|
Location |
Land East of Shelton Road, Willowbrook East Industrial Estate, Corby, NN17 5XH |
Proposal | Formation of temporary construction compound with associated vehicular access points in connection with the construction of permitted Energy Recovery Facility |
Decision | Approved by Delegation |
Decision date | 29 January 2021 |
Relevant documents |
Supporting Information
Plan |
2020
Application number |
NCC - 20/00023/WASVOC |
---|---|
Location | Storefield Plant, Gretton Brook Road, Earlstrees Industrial Estate, Corby, NN17 4AB |
Proposal | Variation of conditions 2 and 3 of Planning Permission 14/00094/WASVOC to amend building elevations and annual throughput of waste |
Decision | Approved by Committee on 4 August 2020 |
Decision date | 05 August 2020 |
Relevant documents |
Supporting InformationPlans |
Application number |
NCC - 20/00022/WASVOC |
---|---|
Location | Storefield Plant, Gretton Brook Road, Earlstrees Industrial Estate, Corby, NN17 4AB |
Proposal | Variation of conditions 2 and 3 of Planning Permission 14/00093/WASVOC to amend building elevations and annual throughput of waste |
Decision | Approved by Committee on 4 August 2020 |
Decision date | 05 August 2020 |
Relevant documents |
Supporting InformationPlans |
Application number |
NCC - 19/00066/WASVOC |
---|---|
Location | Crown House, Gretton Brook Road, Earlstrees Industrial Estate, Corby, NN17 2BA |
Proposal | Retrospective planning application to amend the layout of the waste management operations including the installation of 2 outside pickings lines, storage bays, outside storage areas and construction of 2 weighbridge |
Decision | Approved by Delegation |
Decision date | 05 January 2020 |
Relevant documents |
Supporting InformationPlan |
2019
Application number |
NCC - 19/00027/WASFUL |
---|---|
Location | Land at Shelton Road, Willowbrook East Industrial Estate, Shelton Road, Corby, NN17 5XH |
Proposal | Construction of an Energy Recovery Facility comprising proven combustion technology with an education and visitor centre, access, landscaping and associated works. |
Decision | Approved by Committee on 24 September 2019 |
Decision date | 04 October 2019 |
Relevant documents |
Application number |
NCC - 17/00057/WASVOC |
---|---|
Location | Crown House, Gretton Brook Road, Earlstrees Industrial Estate, Corby, Northamptonshire, NN17 2BA |
Proposal | Variation of Condition 3 (Waste Throughputs) of planning consent ref. 16/00039/WASFUL to increase approved limit |
Decision | Withdrawn by applicant |
Decision date | 29 July 2019 |
Application number |
NCC - 19/00019/WASCOU |
---|---|
Location | A1 Priors Court, Priors Haw Road, Corby, Northamptonshire, NN17 5JG |
Proposal | Change of use to a waste management facility processing end of life vehicles, segregating parts and materials, plus sorting other metals for scrap as well as the continuation of use of part of the building as an office (Class B1). |
Decision | Withdrawn by applicant |
Decision date | 09 July 2019 |
2018
Application number |
NCC - 17/00061/WASFUL |
---|---|
Location | Crown House, Gretton Brook Road, Earlstrees Industrial Estate, Corby, Northamptonshire, NN17 2BA |
Proposal | Amendment of approved site layout including the installation of two outside picking lines, storage bays, outside storage areas and two weighbridges (retrospective application). |
Decision | Approved by Delegation |
Decision date | 04 October 2018 |
Relevant documents |
Supporting information
Plans |
Application number |
NCC - 18/00033/WASNMA |
---|---|
Location | Land To The North Of Princewood Road, Earlstrees Industrial Estate, Corby, Northamptonshire |
Proposal | Non-Material Amendment to planning consent ref. 16/00038/WASVOC for the removal of hardcore stockpiles |
Decision | Approved by Delegation |
Decision date | 24 September 2018 |
Relevant documents |
Supporting informationPlans |
Application number |
NCC - 18/00030/WASVOC |
---|---|
Location | Land To The North Of Princewood Road, Earlstrees Industrial Estate, Corby, Northamptonshire |
Proposal | Variation of Conditions 23 (Finished Ground Levels) and 24 (Ecological Management, Restoration and Aftercare) of planning consent ref. 16/00038/WASVOC |
Decision | Approved by Delegation |
Decision date | 24 September 2018 |
Relevant documents |
Supporting informationPlans |
Application number |
NCC - 17/00058/WASVOC |
---|---|
Location | Weldon Landfill Site, Kettering Road, Weldon, Northamptonshire, NN17 3JG |
Proposal | Variation of Condition 10 (Cessation of Development) of planning consent ref. CO/02/280C to extend the End Date |
Decision | Approved by Delegation |
Decision date | 01 March 2018 |
Relevant documents |
Supporting informationPlans |
Application number |
NCC - 17/00059/WASVOC |
---|---|
Location | Weldon Landfill Site, Kettering Road, Weldon, Northamptonshire, NN17 3JG |
Proposal | Variation of Condition 8 (Cessation of Development) of planning consent ref. CO/96/155C to extend the End Date |
Decision | Approved by Delegation |
Decision date | 01 March 2018 |
Relevant documents |
Supporting informationPlans |
Application number |
NCC - 17/00060/WASVOC |
---|---|
Location | Weldon Landfill Site, Kettering Road, Weldon, Northamptonshire, NN17 3JG |
Proposal | Variation of Condition 7 (Cessation of Development) of planning consent ref. CO/97/42C to extend the End Date |
Decision | Approved by Delegation |
Decision date | 01 March 2018 |
Relevant documents |
Supporting informationPlans |
2017
Application Number |
NCC - 16/00039/WASFUL |
---|---|
Location | Crown House, Gretton Brook Road, Earlstrees Industrial Estate, Corby, Northamptonshire, NN17 4LS |
Proposal |
Redevelopment of existing materials recycling facility including reconstruction of a fire-damaged building |
Decision | Approved by Delegation |
Decision Date | 19 January 2017 |
Relevant Documents |
2016
Application Number |
NCC - 16/00038/WASVOC |
---|---|
Location | Land To The North Of Princewood Road, Earlstrees Industrial Estate, Corby, Northamptonshire |
Proposal |
Variation of Condition 26 of planning permission 08/00067/WAS to extend the end date for landfilling and subsequent restoration of Princewood Road ironstone gullet to October 2020 |
Decision | Approved by Delegation |
Decision Date | 12 December 2016 |
Relevant Documents |
Application Number |
NCC - 15/00037/WASNMA |
---|---|
Location | Weldon Landfill Site, Kettering Road, Weldon, Northamptonshire, NN17 3JG |
Proposal |
Non Material Amendment to Planning Permission 13/00042/WASVOC to amend the route of the surface water management ditch and lagoon, small area of regrading and amendment to route of access track |
Decision | Approved by Delegation |
Decision Date | 28 September 2016 |
Relevant Documents |
Application Number |
NCC - 16/00011/WASFUL |
---|---|
Location | Corby Sewage Treatment Works, Weldon Road, Corby, NN17 3LD |
Proposal |
Erection of a glass reinforced plastic kiosk to house electrical control equipment |
Decision | Approved by Delegation |
Decision Date | 24 June 2016 |
Relevant Documents |
Application Number |
NCC - 16/00013/WASFUL |
---|---|
Location | Viridor, Pilot Road, Corby, NN17 5YH |
Proposal |
Glass sorting and recovery facility |
Decision | Approved by Delegation |
Decision Date | 20 May 2016 |
Relevant Documents |
Application Number |
NCC - 15/00026/WASFUL |
---|---|
Location | Composting Waste Facility, Stamford Road, Weldon |
Proposal |
Use of land for open air windrow composting of green waste, with creation of new vehicular access, car parking, storage areas, portable office building and formation of surfacing, balancing pond and leachate lagoon |
Decision | Approved by DC Committee |
Decision Date | 28 April 2016 |
Relevant Documents |
2015
Application Number |
NCC - 15/00027/WASFUL |
---|---|
Location | Viridor Waste Management, Pilot Road, Corby, Northamptonshire, NN17 5YH |
Proposal |
Glass sorting and recovery facility |
Decision | Approved |
Decision Date | 30 June 2015 |
Relevant Documents |
|
Application Number |
NCC - 14/00097/WASFUL |
---|---|
Location | 12B Earlstree Road, Corby, Northamptonshire, NN17 4AZ |
Proposal |
Proposed use of land and building for an AD facility accepting specialised difficult to treat liquid waste, involving a pre-treatment process |
Decision | Approved |
Decision Date | 16 April 2015 |
Relevant Documents |
Application Number |
NCC - 15/00003/WASFUL |
---|---|
Location | Vayland Ltd, Heritage Way, Corby, Northamptonshire, NN17 5XW |
Proposal |
Construction and operation of a Soils Treatment Hub |
Decision | Approved |
Decision Date | 15 April 2015 |
Relevant Documents |
Application Number |
NCC - 15/00004/WASVOC |
---|---|
Location | Land at Shelton Road, Willowbrook East Industrial Estate, Corby, Northamptonshire, NN17 5XH |
Proposal |
Variation of Condition 30 of Planning Permission 13/00079/WASFUL to amend the catchment area |
Decision | Approved |
Decision Date | 25 March 2015 |
Relevant Documents |
Application Number |
NCC - 14/00094/WASVOC |
---|---|
Location | Storefield Plant, Gretton Brook Road, Earlstrees Industrial Estate, Corby, Northamptonshire, NN17 4BA |
Proposal |
Variation of Condition 21 of Planning Permission 09/00052/WAS for a revised catchment area |
Decision | Approved |
Decision Date | 24 March 2015 |
Relevant Documents |
Application Number |
NCC - 14/00093/WASVOC |
---|---|
Location | Storefield Plant, Gretton Brook Road, Earlstrees Industrial Estate, Corby, Northamptonshire, NN17 4BA |
Proposal |
Variation of Condition 20 of Planning Permission 08/00097/WAS for a revised catchment area |
Decision | Approved |
Decision Date | 24 March 2015 |
Relevant Documents |
2014
Application Number | NCC - 14/00072/WASVOC CBC - 14/00387/COC |
---|---|
Location | Land at Shelton Road, Willowbrook East Industrial Estate, Corby, Northamptonshire, NN17 5XH |
Proposal | Removal of Condition 30 (Waste Catchment Area) on Planning Permission 13/00079/WASFUL |
Decision | Withdrawn on 11 December 2014 |
Application Number |
NCC - 14/00043/WASFUL |
---|---|
Location | Heritage Way, Corby, Northamptonshire, NN17 5XW |
Proposal |
Retrospective planning application for an office and canteen building |
Decision | Approved |
Decision Date | 11 August 2014 |
Relevant Documents |
Application Number |
NCC - 14/00007/WASVOC |
---|---|
Location | 5 Brunel Road, Earlstrees Industrial Estate, Corby, Northamptonshire NN17 4JW |
Proposal |
Variation of Conditions 2 and 5 of planning permission ref 12/00011/WAS to allow the storage of baled waste at 5m high, with litter netting at 6m high and the storage of repaired pallets at 6m high |
Decision | Approved |
Decision Date | 14 May 2014 |
Relevant Documents |
Application Number |
NCC - 14/00006/WASFUL |
---|---|
Location | Crown House, Gretton Brook Road, Earlstrees Industrial Estate, Corby, Northamptonshire NN17 2BA |
Proposal | Outside storage of waste including loose metal and glass, installation of an outside conveyor and a glass storage container (Retrospective Application). |
Decision | Approved |
Decision Date | 14 May 2014 |
Relevant Documents |
Application Number |
NCC - 13/00104/WASNMA |
---|---|
Location | Viridor, Pilot Road, Corby |
Proposal | Non-Material Amendment to planning permission 11/00021/WAS for the addition of a Mobile Sorting Platform for plastics |
Decision | Approved by Delegation |
Decision Date | 20 January 2014 |
Relevant Documents |
2013
Application Number |
NCC - 13/00060/WASNMA |
---|---|
Location | Shore Energy, Gretton Brook Road, Corby, Northamptonshire |
Proposal | Non-Material amendment to planning permission 09/00052/WAS for alterations to the building elevations and location of openings and revised site layout |
Decision | Approved by Committee |
Decision Date | 18 December 2013 |
Relevant Documents |
Application Number |
NCC - 13/00061/WASNMA |
---|---|
Location | Shore Energy Site, Gretton Brook Road, Corby, Northamptonshire. |
Proposal | Non-Material amendment to planning permission 08/00097/WAS for alterations to the building elevations and location of openings and revised site layout |
Decision | Approved by Committee |
Decision Date | 18 December 2013 |
Relevant Documents |
Application Number |
NCC - 13/00087/WASCOU |
---|---|
Location | Connect Motorcycles, 3 Princewood Road, Earlstrees Industrial Estate, Corby NN17 4AP |
Proposal | Retrospective change of use of 318 sqm from B2 to use for decommissioning end of life motorcycles, segregating parts and materials, plus sorting other metals for scrap |
Decision | Approved by Delegation |
Decision Date | 17 December 2013 |
Relevant Documents |
Application Number | NCC - 13/00042/WASVOC CBC - 13/00162/COC |
---|---|
Location | Corby Landfill Site, Kettering Road, Weldon, Northamptonshire, NN17 3JQ |
Proposal | Variation of time limit specified in condition 22 of planning permission CO/04/00498/COC, extension of the disposal of waste materials to achieve restoration to agriculture of former limestone quarry and extraction of clay for the use solely in connection with on site engineering operations |
Decision | Approved by Delegation |
Decision Date | 13 August 2013 |
Relevant Documents |
Application Number | NCC - 13/00044/WASNMA CBC - 13/00166/COC |
---|---|
Location | Pilot Road, Corby, Northamptonshire, NN17 5YH |
Proposal | Non-Material Amendment to planning permission 13/00016/WASFUL to amend details and position of substation |
Decision | Approved by Delegation |
Decision Date | 20 June 2013 |
Relevant Documents |
Application Number | NCC - 13/00039/WASNMA CBC - 13/00135/COC |
---|---|
Location | Crown House, Gretton Brook Road, Earlstrees Industrial Estate, Corby, NN17 2BA |
Proposal | Non Material Amendment to planning permission 12/00011/WAS to change the site layout to regularise the landscape bund constructed on the North Eastern corner |
Decision | Approved by Delegation |
Decision Date | 20 June 2013 |
Relevant Documents |
Application Number | NCC - 13/00016/WASFUL CBC - 13/00074/COC |
---|---|
Location | Pilot Road, Corby, Northamptonshire, NN17 5YH |
Proposal | Erection of sub-station together with underground cables |
Decision | Approved by Delegation |
Decision Date | 19 April 2013 |
Relevant Documents |
Application Number | NCC - 12/00084/WASCOU CBC - 12/00435/COC |
---|---|
Location | Crown House, Gretton Brook Road, Corby, NN17 2BA |
Proposal | Change of use to allow a picking line with baler and to extend the range of waste allowed to be stored in the building to include dry recyclables |
Decision | Approved by Delegation |
Decision Date | 13 February 2013 |
Relevant Documents |
Application Number | NCC - 12/00080/WASFUL CBC - 12/00396/COC |
---|---|
Location | Heritage Way, Corby, Northamptonshire, NN17 5XW |
Proposal | Construction of a waste transfer station and materials recycling facility, including the installation of a weighbridge and associated infrastructure, and site preparation work |
Decision | Approved by Committee |
Decision Date | 7 February 2013 |
Relevant Documents |
|
Application Number | NCC - 12/00065/WASCOU CBC - 12/00325/COC |
---|---|
Location | Earlstrees Road, Earlstrees Industrial Estate, Corby, NN17 4AZ |
Proposal | Change of Use to a recycling facility to manage Waste Electrical and Electronic Equipment, ELV's, cardboard, plastics and tyres. |
Decision | Withdrawn |
Decision Date | 5 February 2013 |
Application Number | NCC - 12/00077/WASVOC CBC - 12/00394/COC |
---|---|
Location | Corby Household Waste Recycling Centre, Kettering Road, Weldon, NN17 3JQ |
Proposal | Variation of condition 16 on planning permission 10/00037/WAS to retain the Civic Amenity Facility until 2025 |
Decision | Approved by Delegation |
Decision Date | 30 January 2013 |
Relevant Documents |
2012
Application Number | NCC - 12/00011/WAS CBC - 12/00065/COC |
---|---|
Location | Crown House, Gretton Brook Road, Earlstrees Industrial Estate, Corby, NN17 4BA |
Proposal | Change of use to allow the temporary storage of baled waste, WEEE processing and WEEE storage at Brunel Road site and the extension to Materials Recycling Facility yard to provide parking, storage of baled waste, skips/containers and storage bays for green waste and glass, and a lorry wash at Crown House site |
Decision | Approved by Delegation |
Decision Date | 21 May 2012 |
Relevant Documents |
|
Application Number | NCC - 12/00022/NMA CBC - 12/00114/NMA |
---|---|
Location | Land off Gretton Brook Road, Corby, NN17 2BA |
Proposal | Non-material amendment of condition 2 of planning permission OS/00097M1AS to lower the height of the proposed new structures in order to reduce waste of construction materials and reduce volume of air requiring management. |
Decision | Approved by Delegation |
Decision Date | 3 May 2012 |
Relevant Documents |
Application Number | NCC - 11/00087/WAS CBC - 11/00475/COC |
---|---|
Location | Unit 6B, Sallow Road, Corby, NN16 8EG |
Proposal | Change of Use of Unit 6B, Sallow Road, Corby, NN16 8EG from B2 to use for decommissioning of end of life vehicles, segregating parts and materials, plus sorting other metals for scrap. |
Decision | Approved by Delegation |
Decision Date | 12 March 2012 |
Relevant Documents |
Application Number | NCC - 11/00076/WAS CBC - 11/00445/COC |
---|---|
Location | Crown House, Gretton Brook Road, Earlstrees Industrial Estate, Corby, NN17 4BA |
Proposal | Extension of Material Recycling Facility yard to include lorry wash, glass and green waste storage bays, and storage of baled waste. |
Decision | Withdrawn on 15 February 2012 |
2011
Application Numbers | NCC - 11/00051/WAS CBC - 11/00293/COC |
---|---|
Location | Corby Sewage Treatment Works, Weldon Road, Corby, NN17 5ZB |
Proposal | Erection of six kiosk buildings |
Decision | Approved by Delegation |
Decision Date | 14 October 2011 |
Relevant Documents |
Application Number | NCC - 10/00067/WAS CBC - 10/00398/COC |
---|---|
Location | Gretton Brook Road, Gretton, Corby, NN17 4BA |
Proposal | Variation of planning permission 08/00097/WAS to remove condition 20 (proximity principle) |
Decision | Withdrawn on 5 July 2011 |
Application Numbers | NCC - 11/00021/WAS CBC - 11/00143/COC |
---|---|
Location | Pilot Road, Phoenix Parkway, Corby, NN17 5YH |
Proposal | Variation of condition 2 of planning permission 07/00044/WAS to amend the site layout and extension of the waste operations to allow for a small scrap metal operation |
Decision | Approved by Delegation |
Decision Date | 30 June 2011 |
Relevant Documents |
Application Numbers | NCC - 11/00014/WAS CBC - 11/00083/COC |
---|---|
Location | Wincanton Site, Mitchell Road, Corby, NN17 5QT |
Proposal | Change of use from a haulage facility to a Waste Transfer Station and Materials Recycling Facility and the installation of a weighbridge |
Decision | Approved by Delegation |
Decision Date | 17 May 2011 |
Relevant Documents |
Application Numbers | NCC - 10/00077/WAS CBC - 10/00461/COC |
---|---|
Location | Land off Arkwright Road, Corby, NN17 5AE |
Proposal | Change of use of land to provide an End of Life Vehicle Treatment Facility, WEEE and scrap metal yard and a portable office, de-pollution buildings and a weighbridge |
Decision | Approved by Delegation |
Decision Date | 31 January 2011 |
Relevant Documents |
2010
Application Numbers | NCC - 10/00064/WAS CBC - 10/00388/COC |
---|---|
Location | Crown House, Gretton Brook Road, Earlstrees Industrial Estate, Corby, NN17 4BA |
Proposal | Certificate of Proposed Lawful Use for a Materials Recycling Facility |
Decision | Approved by Delegation |
Decision Date | 21 December 2010 |
Relevant Documents |
Application Numbers | NCC - 10/00058/WAS CBC - 10/00336/COC |
---|---|
Location | Composting Site, Land off Brigstock Road, Stanion, Corby |
Proposal | Variation of condition 4 of planning permission 10/00025/EXT to revise the site layout |
Decision | Approved by DC Committee |
Decision Date | 8 November 2010 |
Relevant Documents |
Application Numbers | NCC - 10/00051/WAS CBC - 10/00277/COC |
---|---|
Location | Westminster Building, Gretton Brook Road, Gretton, Corby, NN17 4BA |
Proposal | Change of use of industrial building (B2 use class) to waste transfer and recycling facility, including the installation of a weighbridge for a temporary period of 2 years |
Decision | Approved by Delegation |
Decision Date | 15 October 2010 |
Relevant Documents |
Application Numbers | NCC - 10/00047/WAS CBC - 10/00236/COC |
---|---|
Location | Crown House, Gretton Brook Road, Earlstrees Industrial Estate, Corby, NN17 4BA |
Proposal | Change of use of warehouse to a Materials Recycling Facility |
Decision | Approved by Delegation |
Decision Date | 8 September 2010 |
Relevant Documents |
Application Numbers | NCC - 10/00055/NMA CBC - 10/00304/COC |
---|---|
Location | Weldon Landfill Site, Kettering Road, Weldon, NN17 3JG |
Proposal | Non-material amendment to planning permission CO/02/280C for the replacement of existing gas flare with an automatic temperature control flare of the same flow capacity |
Decision | Approved |
Decision Date | 24 August 2010 |
Relevant Documents |
Application Numbers | NCC - 10/00025/EXT CBC - 10/00137/COC |
---|---|
Location | Composting Site, Land off Brigstock Road, Stanion, Corby, Northants |
Proposal | Replacement of extant planning permission 07/00006/WAS to extend the time limit for implementation |
Decision | Approved by Delegated |
Decision Date | 1 July 2010 |
Relevant Documents |
Application Numbers | NCC - 10/00037/WAS CBC - 10/00218/COC |
---|---|
Location | Civic Amenity Facility, Kettering Road, Weldon, Corby, NN17 3JG |
Proposal | Variation of condition 9 of planning permission 08/00019/WAS to extend the current permitted site opening times |
Decision | Approved by Delegated |
Decision Date | 30 June 2010 |
Relevant Documents |
Application Number | NCC - 10/00014/WAS |
---|---|
Location | Crown House, Gretton Brook Road, Earlstrees Industrial Estate, Corby, NN17 4BA |
Proposal | Certificate of Proposed Lawful Use for a material recycling facility |
Decision | Withdrawn on 20 May 2010 |
2009
Application Numbers | NCC - 09/00052/WAS CBC - 09/00302/COC |
---|---|
Location | Land off Gretton Brook Road, Corby, NN17 2BA |
Proposal | Renewable fuel production and recycling facility |
Decision | Approved by Delegated |
Decision Date | 22 October 2009 |
Relevant Documents |
Application Numbers | NCC - 09/00042/WAS CBC - 09/00195/COC & 09/00196/COC |
---|---|
Location | Weldon Landfill Site, Stamford Road, Weldon |
Proposal | Variation of condition 21 of planning permission CO/03/231C and condition 10 of planning permission CO/05/53C for the extension in time for the landfill, office, skip park, recycling area and associated facilities until 2026 |
Decision | Approved by DC Committee |
Decision Date | 30 June 2009 |
Relevant Documents |
Application Numbers | NCC - 09/00019/WAS CBC - 09/00158/COC |
---|---|
Location | Pilot Road, Phoenix Parkway, Corby, NN17 5YH |
Proposal | Construction of a materials recycling facility (MRF) and two storey office building with associated site modifications; removal of two buildings known as 'Able Welding' and rearrangement of site to improve efficiency and safety |
Decision | Approved by Delegation |
Decision Date | 30 June 2009 |
Relevant Documents |
Application Numbers | NCC - 09/00010/WAS CBC - 09/00120/COC |
---|---|
Location | Weldon Landfill Site, Kettering Road, Weldon |
Proposal | Variation of condition 10 of planning permission CO/05/53C to extend the end date until 28/02/2026 for landfill, offices, skip park recycling area and associated facilities |
Decision | Withdrawn on 7 May 2009 |
Application Numbers | NCC - 08/00097/WAS CBC - 08/00551/COC |
---|---|
Location | Land off Gretton Brook Road, Corby, NN17 2BA |
Proposal | Establishment of a renewable fuel production and recycling facility |
Decision | Approved by DC Committee |
Decision Date | 21 April 2009 |
Relevant Documents |
|
2008
Application Numbers | NCC - 08/00067/WAS CBC - 08/00441/COC |
---|---|
Location | Land to the north of Princewood Road, Corby |
Proposal | Restoration of ironstone gullet with inert waste |
Decision | Approved by Delegation |
Decision Date | 19 November 2008 |
Relevant Documents |
Application Numbers | NCC - 08/00065/WAS CBC - 08/00413/COC |
---|---|
Location | Corby Landfill Site, Kettering Road, Weldon, Corby, NN17 3JG |
Proposal | Installation of an electricity generation plant fuelled by landfill gas |
Decision | Approved by Delegation |
Decision Date | 19 November 2008 |
Relevant Documents |
Application Numbers | NCC - 08/00075/WAS CBC - 08/00457/COC |
---|---|
Location | Weldon Landfill Site, Kettering Road, Weldon, Corby, NN17 3JG |
Proposal | Installation and use of a 50m3 (11,000 gallon) capacity leachate holding tank and compressor pump (retrospective) |
Decision | Approved by Delegation |
Decision Date | 3 November 2008 |
Relevant Documents |
Application Numbers | NCC - 07/00054/WAS CBC - 07/00509/COC |
---|---|
Location | 1 Brunel Road, Earlstrees Industrial Estate, Corby, NN17 4JW |
Proposal | Certificate of Lawful Use for materials recycling centre |
Decision | Withdrawn on 30 June 2008 |
Application Numbers | NCC - 08/00011/WAS CBC - 08/00124/COC |
---|---|
Location | Hunters Point, Hunters Road, Weldon North Industrial Estate, Corby, NN17 5JE |
Proposal | Change of use to tyre sorting and shredding facility and installation of tyre shredding plant |
Decision | Approved by Delegation |
Decision Date | 15 May 2008 |
Relevant Documents |
Application Numbers | NCC - 08/00019/WAS CBC - 08/00164/COC |
---|---|
Location | Corby Landfill Site, Kettering Road, Weldon, Corby, NN17 3JG |
Proposal | Extension of planning permission CO/05/0469 without compliance with condition 15 (end date) for retention of the Civic Amenity Facility until 30/04/2013 |
Decision | Approved by Delegation |
Decision Date | 30 April 2008 |
Relevant Documents |
Application Numbers | NCC - 08/00009/WAS CBC - 08/00091/COC |
---|---|
Location | Corby Sewage Treatment Works, Weldon Road, Corby, NN17 3LD |
Proposal | Erection of three glass reinforced plastic kiosks to house electrical equipment to control bio solids enhancement plant |
Decision | Approved by Delegation |
Decision Date | 10 April 2008 |
Relevant Documents |
Application Numbers | NCC - 07/00071/WAS CBC - 08/00078/COC |
---|---|
Location | Hunters Point, Hunters Road, Weldon North Industrial Estate, Corby, NN17 5JE |
Proposal | Change of use to a materials recycling/recovery facility |
Decision | Approved by Delegation |
Decision Date | 10 April 2008 |
Relevant Documents |
2007
Application Numbers | NCC - 07/00058/WAS CBC - 07/00506/COC |
---|---|
Location | 1 Brunel Road, Earlstrees Industrial Estate, Corby, NN17 4JW |
Proposal | Change of use of warehouse to materials recycling facility and extension of the main building |
Decision | Approved by Delegation |
Decision Date | 21 December 2007 |
Relevant Documents |
Application Numbers | NCC - 07/00044/WAS CBC - 07/00413/COC |
---|---|
Location | Pilot Road, Phoenix Parkway, Corby, NN17 5YH |
Proposal | Change of use of truck stop and adjacent land to waste related activities, replacement Portacabin offices and staff welfare facilities, extension to transfer and recycling building |
Decision | Approved by Delegation |
Decision Date | 14 November 2007 |
Relevant Documents |
Application Numbers | NCC - 07/00006/WAS CBC - 07/00192/COC |
---|---|
Location | Land off Brigstock Road, Stanion, Corby |
Proposal | In-vessel composting facility and related building and structures |
Decision | Approved by Delegation |
Decision Date | 18 September 2007 |
Relevant Documents |
Application Numbers | NCC - 07/00007/WAS CBC - 07/00984/EXT |
---|---|
Location | Kirby Lodge, Gretton Road, Corby |
Proposal | In-vessel composting facility and related building and structures |
Decision | Approved by Delegation |
Decision Date | 17 September 2007 |
Relevant Documents |
Application Numbers | CBC - 07/00088/COC |
---|---|
Location | 79 Manton Road, Earlstrees Industrial Estate, Corby, NN17 4SL |
Proposal | Anaerobic digestion and electricity generation for use on site and for onward sale |
Decision | Approved by Delegation |
Decision Date | 15 June 2007 |
Relevant Documents |
Application Numbers | CBC - 07/00048/COC |
---|---|
Location | Pilot Road, Corby |
Proposal | Stopping up of public highway and change of use to waste recycling centre with the installation of two weighbridges and one office |
Decision | Approved by Delegation |
Decision Date | 5 April 2007 |
Relevant Documents |
2006
Application Numbers | CBC - 06/00091/COC |
---|---|
Location | Priors Hall Quarry, Weldon, Corby |
Proposal | Modification of conditions 1, 12, 15, 17, 23, 26 and 40 of planning permission EN/97/145 and CO/97/55 |
Decision | Approved by Delegation |
Decision Date | 21 July 2006 |
Relevant Documents |
Application Numbers | CBC - 06/00058/COC |
---|---|
Location | Waste transfer and recycling site, Pilot Road, Corby |
Proposal | Modification of condition 6 of planning permission CO/97/267 and condition 6 of planning permission CO/00418 to enable 24 hour working to take place at the site on Mon-Fri |
Decision | Approved by Delegation |
Decision Date | 6 April 2006 |
Relevant Documents |
2005
Application Numbers | CBC - 05/00426/COC |
---|---|
Location | Crucible Road, Corby |
Proposal | Stationing of mobile sludge treatment and dewatering equipment |
Decision | Approved by Delegation |
Decision Date | 24 October 2005 |
Relevant Documents |
Application Numbers | CBC - 05/00187/COC |
---|---|
Location | Corby Leachate Works, Princewood Road, Corby |
Proposal | Extension in time for the retention of leachate treatment plant (modification of condition 7 of planning permission CO/94/292) |
Decision | Approved by Delegation |
Decision Date | 13 June 2005 |
Relevant Documents |
Application Numbers | CBC - 05/00065/COC |
---|---|
Location | Land at Gretton Brook Road, Corby |
Proposal | Change of use from scrap metal yard to use for sorting and crushing of inert waste materials to provide recycled aggregates and soils |
Decision | Approved by Delegation |
Decision Date | 10 May 2005 |
Relevant Documents |
Application Numbers | CBC - 05/00053/COC |
---|---|
Location | Weldon Landfill Site, Kettering Road, Corby, NN17 3JG |
Proposal | Extension of time for offices, skip park, recycling area and associated facilities |
Decision | Approved by Delegation |
Decision Date | 6 May 2005 |
Relevant Documents |
Application Numbers | CBC - 05/00469/COC |
---|---|
Location | Corby Landfill Site, Kettering Road, Corby, NN17 3JG |
Proposal | Application for the removal of condition 9 of planning permission CO/01/54 |
Decision | Approved by Delegation |
Decision Date | 26 January 2005 |
Relevant Documents |
2004
Application Numbers | CBC - 04/00236/COC |
---|---|
Location | Corby Landfill Site, Kettering Road, Corby, NN17 3JG |
Proposal | Landfill gas control flare compound |
Decision | Approved by Delegation |
Decision Date | 2 September 2004 |
Relevant Documents |
Application Numbers | CBC - 04/00498/COC |
---|---|
Location | Land at Stamford Road, Weldon |
Proposal | Variation of condition 22 of planning permission CO/89/54C to extend the time limit for the disposal of waste materials to achieve restoration to agriculture of former limestone quarry and extraction of clay for the use solely in connection with on site engineering operations. |
Decision | Approved by Delegation |
Decision Date | 13 January 2004 |
Relevant Documents |
2023
Application number |
NN/22/00040/WASFUL |
---|---|
Location |
Land off Woodford Road, Woodwell, NN14 4JD |
Proposal |
Proposed green and wood waste recycling facility |
Decision | Withdrawn |
Decision date |
29 August 2023 |
Relevant documents |
Submitted documentsTo view the submitted documents for this planning application, please use the links below: Supporting information
Plans
|
Application number | NN/21/00057/WASFUL |
---|---|
Location | Lilford Lodge Farm, Barnwell Road, Barnwell, PE8 5SA |
Proposal | Relocation of existing materials recycling facility and the infilling of a redundant agricultural quarry with inert soils and clays |
Decision | Approved by Delegation |
Decision date |
6 January 2023 |
Relevant documents |
Supporting Information
Plan |
2022
Application number | NN/22/00012/WASFUL |
---|---|
Location | Lowick Compost Site, Old Aldwincle Road, Lowick, Northamptonshire |
Proposal | Extension to the current concrete compost processing pad |
Decision | Approved by Delegation |
Decision date |
29 July 2022 |
Relevant documents |
Supporting InformationPlans |
Application number | 20/00072/WASFUL |
---|---|
Location | Kings Cliffe Industrial Estate, Wansford Road, Kings Cliffe, PE8 6PB |
Proposal | Construction of a screening bund, implementation of landscape planting scheme along with the installation of associated infrastructure (part retrospective) |
Decision | Withdrawn by applicant |
Withdrawal date |
11 May 2022 |
2021
Application number | 20/00030/MINVOC |
---|---|
Location | Wakerley Quarry, Wakerley, Northamptonshire, NN17 3AZ |
Proposal | Variation of condition 5 on planning permission EN.97.522C to increase the site operational hours from 07:00 to 18:00 to 07:00 to 19:00 Mondays to Fridays, and to allow the essential maintenance of plant and machinery between 07:00 to 21:00 Mondays to Fridays and 07:00 to 16:00 Saturdays, with no works on Sundays, Bank or Public Holidays |
Decision | Withdrawn by applicant |
Withdrawal date |
21 December 2021 |
Application number | 20/00029/MINVOC |
---|---|
Location | Wakerley Quarry, Wakerley, Northamptonshire, NN17 3AZ |
Proposal | Variation of condition 5 on planning permission 08/00026/MIN to increase the site operational hours from 07:00 to 18:00 to 07:00 to 19:00 Mondays to Fridays, and to allow the essential maintenance of plant and machinery between 07:00 to 21:00 Mondays to Fridays and 07:00 to 16:00 Saturdays, with no works on Sundays, Bank or Public Holidays |
Decision | Withdrawn by applicant |
Withdrawal date |
21 December 2021 |
Application number | NN/21/00015/MINVOC |
---|---|
Location | Wakerley Quarry, Fineshade Road, Wakerley, NN17 3BA |
Proposal | Variation of Condition 5 of Planning Permission EN/97/522C to extend hours of HGV movements. |
Decision | Approved by Committee on 01 November 2021 |
Decision date |
23 November 2021 |
Relevant documents |
Supporting InformationPlans |
Application number | 21/00014/MINVOC |
---|---|
Location | Wakerley Quarry, Fineshade Road, Wakerley, NN17 3BA |
Proposal | Variation of Condition 5 of Planning Permission 08/00026/MIN to extend hours of HGV movements |
Decision | Approved by Committee on 01 November 2021 |
Decision date |
23 November 2021 |
Relevant documents |
Supporting InformationPlans |
Application number | 20/00062/WASFUL |
---|---|
Location | Plots 19 to 26, Sanders Lodge Industrial Estate, Rushden, Northamptonshire, NN10 6BQ |
Proposal | An additional industrial building for the storage and processing of recyclable waste |
Decision | Approved by Committee on 06 September 2021 |
Decision date |
09 September 2021 |
Relevant documents |
Supporting InformationPlans |
Application number | NCC - 20/00038/MINFUL ENC - 20/00938/NCC |
---|---|
Location | Elton Quarry, Peterborough Old Road, Eaglethorpe, Warmington, Peterborough, PE8 6SN |
Proposal | Retrospective mineral application for an extension to the existing plant and ancillary works site in order to provide additional operational space for material treatment, stockpiling and temporary storage with restoration to agricultural land |
Decision | Approved by Delegation |
Decision date |
31 March 2021 |
Relevant documents |
Supporting Information
Plan |
Application number | NCC - 20/00037/MINVOC ENC - 20/00936/NCC |
---|---|
Location |
Elton Quarry, Peterborough Old Road, Eaglethorpe, Warmington, Peterborough, PE8 6SN |
Proposal | Variation of condition 26 (End Date) of planning permission 18/00032/MINVOC to extend the end date for the plant site and ancillary works associated with the construction of an agricultural reservoir until 31 July 2022 |
Decision | Approved by Delegation |
Decision date |
31 March 2021 |
Relevant documents |
Supporting Information
Plan |
Application number | NCC - 20/00036/MINVOC ENC - 20/00935/NCC |
---|---|
Location | Elton Quarry, Peterborough Old Road, Eaglethorpe, Warmington, Peterborough, PE8 6SN |
Proposal | Variation of condition 26 (End Date) of planning permission 18/00031/MINVOC to extend the end date for completion of the agricultural reservoir until 31 July 2022 |
Decision | Approved by Delegation |
Decision date |
31 March 2021 |
Relevant documents |
Supporting Information
Plan |
Application number | NCC - 19/00035/MINFUL ENC - 19/00862/NCC |
---|---|
Location | Elton Quarry, Peterborough Old Road, Eaglethorpe, Warmington, Peterborough, PE8 6SN |
Proposal | Retrospective mineral application for an extension to the existing plant and ancillary works site in order to provide additional operational space for material treatment, stockpiling and temporary storage with restoration to agricultural land |
Decision | Approved by Committee on 17 November 2020 |
Decision date |
31 March 2021 |
Relevant documents |
Application number | NCC - 19/00034/MINVOC ENC - 19/00857/NCC |
---|---|
Location | Elton Quarry, Peterborough Old Road, Eaglethorpe, Warmington, Peterborough, PE8 6SN |
Proposal | Section 73 application to vary conditions 2, 3, 7 & 26 of planning permission 18/00032/MINVOC to enable a new replacement low profile processing plant to be erected as well as to import reclamation material a proportion of which will need to be treated to make it suitable for restoration and an extension of the completion date to 31 July 2030 |
Decision | Approved by Committee on 17 November 2020 |
Decision date |
31 March 2021 |
Relevant documents |
Application number | NCC - 19/00033/MINFUL ENC - 19/00856/NCC |
---|---|
Location | Elton Quarry, Peterborough Old Road, Eaglethorpe, Warmington, Peterborough, PE8 6SN |
Proposal | Phased mineral extraction, construction of a bailey bridge to cross a branch of the River nene, importation of reclamation material including ancillary activities, with restoration to agricultural pasture and wet woodland |
Decision | Approved by Committee on 17 November 2020 |
Decision date |
31 March 2021 |
Relevant documents |
2020
Application number | NCC - 20/00018/MINVOC ENC - 20/00513/NCC |
---|---|
Location | Stonehill Quarry, Off King's Cliffe Road, Near Wansford/Yarwell, PE8 6NU |
Proposal | Variation of conditions 9 and 19 of planning consent ref: 15/00092/WASFUL to allow crushing to produce recycled aggregate |
Decision | Approved by delegation |
Decision date |
06 July 2020 |
Relevant documents |
Supporting information
Plans |
Application number | NCC - 20/00024/MINNMA ENC - |
---|---|
Location | Wakerley Quarry, Wakerley, Northamptonshire, NN17 3AZ |
Proposal | Temporary extended working hours |
Decision | Refused by delegation |
Decision date |
21 May 2020 |
Relevant documents |
Supporting informationPlans |
Application number | NCC - 20/00006/MINFUL ENC - 20/0275/NCC |
---|---|
Location | Wakerley Quarry, Wakerley, Northamptonshire, NN17 3AZ |
Proposal | Wakerley Quarry access road additional drainage provisions |
Decision | Approved by delegation |
Decision date |
06 May 2020 |
Relevant documents |
Supporting informationPlans |
Application number | NCC - 19/00060/WASFUL ENC - 19/001651/NCC |
---|---|
Location | Wakerley Quarry, Wakerley, Northamptonshire, NN17 3AZ |
Proposal | Proposed importation of suitable inert material to the quarry site to restore land close to pre-development contours to produce a more naturalistic profile upon restoration across the entire site than approved at present |
Decision | Approved by delegation |
Decision date |
28 February 2020 |
Relevant documents |
Supporting information
PlansEnvironmental Statement
|
2019
Application number | NCC - 19/00025/MINNMA ENC - 19/000631/NCC |
---|---|
Location | Collyweston Quarry, Duddington, Peterborough Road, Northamptonshire, PE9 3QA |
Proposal | Non-Material Amendment relating to the changing of the current wet wheel wash for a dry wheel cleaning system of planning consent ref: 14/00035/MINFUL |
Decision | Approved by delegation |
Decision date |
11 June 2019 |
Relevant documents |
Supporting informationPlans |
Application number | NCC - 19/00024/MINVOC ENC - 19/00632/NCC |
---|---|
Location | Ringstead Grange Quarry, Raunds Road, Ringstead, Northamptonshire, NN9 6FZ |
Proposal | Variation of Conditions 5 and 17 of planning consent ref: 12/00016/MIN to allow disposal of inert materials from essential highway maintenance works |
Decision | Approved by delegation |
Decision date | 08 May 2019 |
Relevant documents |
Supporting informationPlans |
Application number | NCC - 19/00011/MINVOC ENC - 19/00426/NCC |
---|---|
Location | Ringstead Grange Quarry, Raunds Road, Ringstead, Northamptonshire, NN9 6FZ |
Proposal | Variation of Conditions 2, 42, 48 and 52 of Planning Permission 15/00073/MINVOC to amend the Restoration Scheme and Ecological Management Plan to remove references to agricultural grassland |
Decision | Approved by delegation |
Decision date | 08 May 2019 |
Relevant documents |
Supporting informationPlans |
Application number | NCC - 19/00002/WASNMA ENC - 19/000026/NCC |
---|---|
Location | Slipe Clay Pit Landfill Site, Stamford Road, Kings Cliffe, Northamptonshire, PE8 6XX |
Proposal | Changes to the approved phasing plans to work Phase 10 in advance of Phases 7 to 9. |
Decision | Approved by delegation |
Decision date | 28 March 2019 |
Relevant documents |
Plans |
Application number | NCC - 18/00045/WASNMA ENC - 19/00095/NCC |
---|---|
Location | Westwood AD Facility, Bedford Road, Rushden, Northamptonshire, NN10 0QS |
Proposal | Non material amendments for extension of hours of working. |
Decision | Approved by delegation |
Decision date | 25 January 2019 |
Relevant documents |
Supporting informationPlans |
2018
Application number | NCC - 18/00040/WASVOC ENC - 18/0195/NCC |
---|---|
Location | Quarry And Premises, Lilford Lodge Farm, Thrapston Road, Barnwell, Northamptonshire PE8 5SA |
Proposal | Variation of Conditions 7 (Waste Materials), 8 and 10 (Permitted Operations) of planning consent ref.: 09/00049/WAS to allow for the operation of a Screener and Crusher on site, and to clarify the quantity of materials to be imported and associated vehicle movements. |
Decision | Approved by delegation |
Decision date | 13 December 2018 |
Relevant documents |
Supporting informationPlans |
Application number |
NCC - 18/00031/MINVOC |
---|---|
Location |
Elton Quarry, Peterborough Road, Warmington, Northamptonshire PE8 6SN |
Proposal | Variation of Condition 26 (End Date) of planning consent ref. 13/00073/MINVOC to retrospectively extend the end date of operations |
Decision | Approved by delegation |
Decision date | 26 October 2018 |
Relevant documents |
Supporting information
Plans |
Application number |
NCC - 18/00032/MINVOC |
---|---|
Location | Elton Quarry, Peterborough Road, Warmington, Northamptonshire PE8 6SN |
Proposal | Variation of Condition 25 (End Date) of planning consent ref. 13/00074/MINVOC to retrospectively extend the end date of operations |
Decision | Approved by delegation |
Decision date | 26 October 2018 |
Relevant documents |
Supporting information
Plans |
Application number |
NCC - 18/00038/MINNMA |
---|---|
Location | Wakerley Quarry, Wakerley, Northamptonshire |
Proposal | Non-Material Amendment to planning consent ref. 17/00065/MINFUL for the importation of additional materials for the creation of a seal for previously-approved dust suppression/water attenuation ponds |
Decision | Approved by delegation |
Decision date | 14 September 2018 |
Relevant documents |
Supporting informationPlans |
Application number |
NCC - 18/00034/MINNMA |
---|---|
Location | Wakerley Quarry, Wakerley, Northamptonshire |
Proposal | Non-Material Amendment of planning consent ref. 16/00025/MINFUL for the erection of additional fencing |
Decision | Approved by delegation |
Decision date | 12 September 2018 |
Relevant documents |
Supporting informationPlans |
Application number |
NCC - 18/00035/MINNMA |
---|---|
Location | Wakerley Quarry, Laxton Park, Laxton, Northamptonshire |
Proposal |
Non-Material Amendment to planning consent ref.: 08/00026/MIN to remove the provision of establishing a temporary hedgerow along the northern embankment of the quarry access road |
Decision | Withdrawn by Applicant |
Decision date | 07 September 2018 |
Application number |
NCC - 18/00019/MINVOC |
---|---|
Location | Collyweston Quarry, Peterborough Road, Duddington, Northamptonshire, PE9 3QA |
Proposal | Variation of Conditions 22, 24, 26 (Survey and Restoration), 29 (Woodland Planting), 31 (Aftercare and Woodland) and 33 (End Date) of planning consent ref. EN/06/1279C to extend the end date |
Decision | Approved by delegation |
Decision date | 01 August 2018 |
Relevant documents |
Supporting informationPlans |
Application number |
NCC - 18/00014/WASVOC |
---|---|
Location | Westwood A D Plant, Bedford Road, Rushden, Northamptonshire, NN10 0SQ |
Proposal | Variation of Condition 20 (Visual Amenity) of planning consent ref.: 17/00048/WASVOC to alter an approved drawing |
Decision | Approved by delegation |
Decision date | 19 June 2018 |
Relevant documents |
Supporting informationPlans |
Application number |
NCC - 17/00065/MINFUL |
---|---|
Location | Wakerley Quarry, Wakerley, Northamptonshire |
Proposal | Importation of materials for the creation of a seal for previously-approved dust suppression and water attenuation ponds |
Decision | Approved by delegation |
Decision date | 06 April 2018 |
Relevant documents |
Supporting informationPlans |
2017
Application number |
NCC - 17/00052/WASFUL |
---|---|
Location |
Easton On The Hill WRC, Park Walk, Easton On The Hill, Northamptonshire, PE9 3LW |
Proposal | Erection of 2no. glass-reinforced kiosk to house electrical control equipment |
Decision | Approved by delegation |
Decision date | 06 December 2017 |
Relevant documents |
Supporting informationPlans |
Application number |
NCC - 17/00047/WASFUL |
---|---|
Location | Broadholme Treatment Works, Ditchford Lane, Irthlingborough, Northamptonshire, NN8 1RR |
Proposal | Erection of a kiosk to house electrical and control equipment |
Decision | Approved by delegation |
Decision date | 06 December 2017 |
Relevant documents |
Supporting InformationPlans |
Application number |
NCC - 17/00039/MINFUL |
---|---|
Location | Slate Drift Industrial Estate, Collyweston, Northamptonshire PE9 3PG |
Proposal | Partially retrospective application for the installation of 2 no. cold stores for mineral processing |
Decision | Approved by delegation |
Decision date | 31 October 2017 |
Relevant documents |
Supporting documentsPlans |
Application Number |
NCC - 17/00042/MINMNA |
---|---|
Location | Wakerley Quarry, Laxton Park, Laxton, Northamptonshire |
Proposal | Non-Material Amendment to planning consent ref. 08/00026/MIN for the installation of a temporary weighbridge and associated office building |
Decision | Approved by Delegation |
Decision Date | 11 September 2017 |
Relevant Documents |
Application Number |
NCC - 17/00011/WASVOC |
---|---|
Location | Westwood A D Plant, Bedford Road, Rushden, Northamptonshire, NN10 0SQ |
Proposal | Variation of Condition 23 (Catchment Area) of planning permission 13/00090/WASVOC to amend the approved catchment area condition to increase the catchment area from which wastes could be imported to the facility |
Decision | Approved by Delegation |
Decision Date | 08 June 2017 |
Relevant Documents |
Plans:Supporting Information: |
Application Number |
NCC - 17/00025/MINNMA |
---|---|
Location | Wakerley Quarry, Wakerley, Northamptonshire |
Proposal | Non-Material Amendment to planning application 08/00026/MIN to alter approved plans |
Decision | Approved by Delegation |
Decision Date | 18 May 2017 |
Relevant Documents |
Application Number |
NCC - 17/00012/MINNMA |
---|---|
Location | Wakerley Quarry, Wakerley, Northamptonshire |
Proposal | Non-material amendment to application ref. 08/00026/MIN for the creation of multi-functional ponds within the approved mineral extraction area (Phase E) |
Decision | Approved by Delegation |
Decision Date | 29 March 2017 |
Relevant Documents |
Application Number |
NCC - 17/00005/MINNMA |
---|---|
Location | Wakerley Quarry, Wakerley, Northamptonshire |
Proposal | Non-Material Amendment to planning permission 08/00026/MIN for the establishment of three temporary soil mounds |
Decision | Approved by Delegation |
Decision Date | 07 March 2017 |
Relevant Documents |
Application Number |
NCC - 17/00006/WASNMA |
---|---|
Location | Westwood A D Plant, Bedford Road, Rushden, Northamptonshire, NN10 0SQ |
Proposal | Non-Material Amendment to planning permission 13/00090/WASVOC to reflect difference in quantity of CHP units installed against original proposal |
Decision | Approved by Delegation |
Decision Date | 20 February 2017 |
Relevant Documents |
Application Number |
NCC - 16/00055/MINNMA |
---|---|
Location | Ringstead Grange Quarry, Raunds Road, Ringstead, Northamptonshire |
Proposal | Non-Material Amendment to planning permission 15/00073/MINVOC for revisions to parking areas and site compound layout, including installation of a wheel bath |
Decision | Approved by Delegation |
Decision Date | 9 January 2017 |
Relevant Documents |
Application Number |
NCC - 16/00053/WASFUL |
---|---|
Location | Plots 19 To 26, Sanders Lodge Industrial Estate, Rushden, Northamptonshire, NN10 6BQ |
Proposal | Construction of building for storage and recyclable waste processing purposes |
Decision | Approved by Delegation |
Decision Date | 10 February 2017 |
Relevant Documents |
2016
Application Number |
NCC - 16/00050/WASFUL |
---|---|
Location | Broadholme Treatment Works, Ditchford Lane, Irthlingborough, Northamptonshire, NN8 1RR |
Proposal | Erection of a glass-reinforced kiosk to house electrical equipment |
Decision | Approved by Delegation |
Decision Date | 19 December 2016 |
Relevant Documents |
Application Number |
NCC - 16/00061/MINFUL |
---|---|
Location | Builders Yard, Slate Drift, Collyweston, Northamptonshire, PE9 3PG |
Proposal | Installation of cold store for mineral processing |
Decision | Withdrawn |
Decision Date | 07 December 2016 |
Application Number |
NCC - 16/00051/MINNMA |
---|---|
Location | Wakerley Quarry, Laxton Park, Laxton, Northamptonshire, NN17 3AZ |
Proposal | Non-Material Amendment to planning permission 08/00026/MIN for modifications to the existing site infrastructure layout |
Decision | Approved by Delegation |
Decision Date | 30 November 2016 |
Relevant Documents |
Application Number |
NCC - 16/00042/MINNMA |
---|---|
Location | Wakerley Quarry, Laxton Park, Laxton, Northamptonshire, NN17 3AZ |
Proposal | Non-Material Amendment to planning permission 08/00026/MIN to amend the location of topsoil storage bund No. 5 |
Decision | Approved by Delegation |
Decision Date | 30 November 2016 |
Relevant Documents |
Application Number |
NCC - 16/00037/MINFUL |
---|---|
Location | Wakerley Quarry, Laxton Park, Laxton, Northamptonshire, NN17 3AZ |
Proposal | Revised internal access road alignment |
Decision | Approved by Delegation |
Decision Date | 28 November 2016 |
Relevant Documents |
Application Number |
NCC - 16/00049/WASNMA |
---|---|
Location | Stonehill Quarry, Off Kings Cliffe Road, Northamptonshire, PE8 6NU |
Proposal | Non-Material Amendment of planning permission 15/00092/WASFUL to better clarify the nature of the materials to be imported to the site for restoration purposes |
Decision | Approved by Delegation |
Decision Date | 9 November 2016 |
Relevant Documents |
Application Number |
NCC - 16/00025/MINFUL |
---|---|
Location | Wakerley Quarry, Laxton Park, Laxton, Northamptonshire |
Proposal | Revised access onto Duddington Road |
Decision | Approved by Delegation |
Decision Date | 6 September 2016 |
Relevant Documents |
Application Number |
NCC - 15/00092/WASFUL |
---|---|
Location | Stonehill Quarry, Off Kings Cliffe Road, Northamptonshire, PE8 6NU |
Proposal | Importation of inert materials for the final restoration of the Stonehill Quarry including the creation of calcareous grassland. |
Decision | Approved by DC Committee |
Decision Date | 21 September 2016 |
Relevant Documents |
Supporting information:
|
Application Number |
NCC - 16/00020/WASFUL |
---|---|
Location | Land At Upper Higham Lane, Rushden, Northamptonshire, NN10 0SU |
Proposal | Replacement of an industrial unit to house a Combined Heat and Power plant to convert Refuse Derived Fuel/Solid Recovered Fuel into energy pellets |
Decision | Approved by Delegation |
Decision Date | 16 August 2016 |
Relevant Documents |
Application Number |
NCC - 16/00016/MINNMA |
---|---|
Location | Ringstead Grange Quarry, Raunds Road, Ringstead |
Proposal | Non material amendment to planning permission 15/00073/MINVOC to temporarily stockpile overburden clay prior to use as engineering material |
Decision | Approved |
Decision Date | 27 May 2016 |
Relevant Documents |
Application Number |
NCC - 16/00004/MINNMA |
---|---|
Location | Wakerley Quarry, Laxton Park, Laxton |
Proposal | Non material amendment to planning permission 08/00026/MIN to revise the sequence of working |
Decision | Approved |
Decision Date | 24 May 2016 |
Relevant Documents |
Application Number |
NCC - 16/00007/MINNMA |
---|---|
Location | Wakerley Quarry, Laxton Park, Laxton |
Proposal | Non material amendment to planning permission EN/97/522C to revise the sequence of working |
Decision | Approved |
Decision Date | 24 May 2016 |
Relevant Documents |
Application Number |
NCC - 15/00038/WASFUL |
---|---|
Location | The Caravan Site, Station Road, Irthlingborough, NN9 5QF |
Proposal | Retrospective planning application for the erection of a steel framed building |
Decision | Approved by Delegation |
Decision Date | 5 May 2016 |
Relevant Documents |
Application Number |
NCC - 16/00001/MINVOC |
---|---|
Location | Collyweston Quarry, Peterborough Road, Duddington, Northamptonshire, PE9 3QA |
Proposal | Variation of condition 2 of planning permission 13/00120/MINVOC to extend time for in-filling and restoration operations |
Decision | Approved by Delegation |
Decision Date | 20 April 2016 |
Relevant Documents |
2015
Application Number |
NCC - 15/00073/MINVOC |
---|---|
Location | Ringstead Grange Quarry, Raunds Road, Ringstead, NN14 4DT |
Proposal | Variation of conditions 5 and 17 of planning permission 12/00016MINFUL to allow disposal of inert materials from essential highway maintenance works |
Decision | Approved by Delegation |
Decision Date | 9 December 2015 |
Relevant Documents |
Application Number |
NCC - 15/00073/MINVOC |
---|---|
Location | Ringstead Grange Quarry, Raunds Road, Ringstead, NN14 4DT |
Proposal | Variation of conditions 5 and 17 of planning permission 12/00016MINFUL to allow disposal of inert materials from essential highway maintenance works |
Decision | Approved by Delegation |
Decision Date | 9 December 2015 |
Relevant Documents |
Application Number |
NCC - 15/00073/MINVOC |
---|---|
Location | Ringstead Grange Quarry, Raunds Road, Ringstead, NN14 4DT |
Proposal | Variation of conditions 5 and 17 of planning permission 12/00016MINFUL to allow disposal of inert materials from essential highway maintenance works |
Decision | Approved by Delegation |
Decision Date | 9 December 2015 |
Relevant Documents |
Application Number |
NCC - 15/00073/MINVOC |
---|---|
Location | Ringstead Grange Quarry, Raunds Road, Ringstead, NN14 4DT |
Proposal | Variation of conditions 5 and 17 of planning permission 12/00016MINFUL to allow disposal of inert materials from essential highway maintenance works |
Decision | Approved by Delegation |
Decision Date | 9 December 2015 |
Relevant Documents |
Application Number |
NCC - 15/00072/MINFUL |
---|---|
Location | Ringstead Grange Quarry, Raunds Road, Ringstead, NN14 4DT |
Proposal | Installation of a mobile concrete batching system along with the establishment of two aggregate bays and associated HGV movements |
Decision | Approved by Delegation |
Decision Date | 9 December 2015 |
Relevant Documents |
Application Number |
NCC - 15/00030/MINFUL |
---|---|
Location | Builders Yard, Slate Drift, Collyweston, Northamptonshire, PE9 3PG |
Proposal | Re-opening of the Collyweston Slate Mine |
Decision | Approved |
Decision Date | 16 September 2015 |
Relevant Documents |
|
Application Number |
NCC - 15/00050/MINNMA |
---|---|
Location | Collyweston Quarry, Peterborough Road, Duddington, Northamptonshire, PE9 3QA |
Proposal | Non Material Amendment to Planning Permission EN/06/1279C relating to phasing of extraction and associated soils storage in the Eastern Extension |
Decision | Approved |
Decision Date | 23 July 2015 |
Relevant Documents |
Application Number |
NCC - 15/00034/WASFUL |
---|---|
Location | Plots 19 to 26, Sanders Lodge Industrial Estate, Rushden, Northamptonshire, NN10 6BQ |
Proposal | Construction of an additional industrial style building; 48 metres long, 48 metres wide and 5.5 metres high to the eaves for the storage of recyclable materials |
Decision | Approved |
Decision Date | 23 July 2015 |
Relevant Documents |
Application Number |
NCC - 15/00039/MINNMA |
---|---|
Location | Ringstead Grange Quarry, Raunds Road, Ringstead, Northamptonshire |
Proposal | Non Material Amendment to Planning Permission 12/00016/MIN for importation of fill material in the western sector to extend the "Landscaping Zone" by approximately 5HA |
Decision | Approved |
Decision Date | 22 June 2015 |
Relevant Documents |
Application Number |
NCC - 15/00029/MINNMA |
---|---|
Location | Ringstead Grange Quarry, Raunds Road, Ringstead, Northamptonshire |
Proposal | Non Material Amendment to Planning Permission 12/00016/MIN to allow the overnight parking of HGVs, adjusted location of office and weighbridge together with amendment of the scheme of works |
Decision | Approved |
Decision Date | 19 June 2015 |
Relevant Documents |
Application Number |
NCC - 15/00025/WASFUL |
---|---|
Location | Plot 19 to 26, Sanders Lodge Industrial Estate, Wellingborough Road, Rushden, Northamptonshire, NN10 6BQ |
Proposal | Installation of a boiler extractor flue |
Decision | Approved |
Decision Date | 10 June 2015 |
Relevant Documents |
Application Number |
NCC - 15/00023/WASFUL |
---|---|
Location | Plot 19 to 26, Sanders Lodge Industrial Estate, Wellingborough Road, Rushden, Northamptonshire, NN10 6BQ |
Proposal | Installation of barrier walls for health and safety purposes |
Decision | Approved |
Decision Date | 10 June 2015 |
Relevant Documents |
2014
Application Number |
NCC - 14/00091/WASNMA |
---|---|
Location | Slipe Clay Pit Landfill Site, Stamford Road, Kings Cliffe, Northamptonshire |
Proposal | Non-Material Amendment for alterations to the site entrance |
Decision | Approved |
Decision Date | 09 January 2015 |
Relevant Documents |
Application Number |
NCC - 14/00058/WASFUL |
---|---|
Location | Plots 19-26, Sanders Lodge Industrial Estate, Rushden, Northamptonshire, NN10 6BQ |
Proposal | Construction of an additional industrial style building for the storage and processing of recyclable materials |
Decision | Approved |
Decision Date | 24 October 2014 |
Relevant Documents |
Application Number |
NCC - 13/00074/MINVOC |
---|---|
Location | Land North of Eaglethorpe, Warmington, Northamptonshire |
Proposal | Variation of Condition 26 to retrospectively extend the end date to 2018 for Planning Permission 09/00047/MIN for the Variation of Condition 3 of Planning Permission EN/05/2356C to vary the details of the plant and ancillary works |
Decision | Approved |
Decision Date | 26 September 2014 |
Relevant Documents |
|
Application Number |
NCC - 13/00073/MINVOC |
---|---|
Location | Land North of Eaglethorpe, Warmington, Northamptonshire |
Proposal | Variation of Condition 28 to retrospectively extend the end date to 2018 for Planning Permission EN/02/0846C for the construction of an agricultural reservoir together with removal of surplus material arising in the course of construction and the importation of a limited quantity of engineering clay |
Decision | Approved |
Decision Date | 26 September 2014 |
Relevant Documents |
|
Application Number |
NCC - 14/00020/WASNMA |
---|---|
Location | Slipe Clay Pit Landfill Site, Stamford Road, Kings Cliffe, Northamptonshire, PE8 6XX |
Proposal | Non-material amendment relating to revised layout of the soil treatment area |
Decision | Approved |
Decision Date | 07 August 2014 |
Relevant Documents |
Application Number |
NCC - 14/00040/MINNMA |
---|---|
Location | Collyweston Quarry, Peterborough Road, Duddington, Northamptonshire, PE9 3QA |
Proposal | Non-material amendment relating to soil storage (condition 14) of permission EN/06/1279C to retain soils in their current location |
Decision | Approved |
Decision Date | 16 July 2014 |
Relevant Documents |
Application Number |
NCC - 14/00008/MINFUL |
---|---|
Location | Lilford Lodge Farm, Thrapston Road, Barnwell, Northamptonshire, PE8 5SA |
Proposal | Importation of aggregate from Rectory Farm Quarry, Titchmarsh, Thrapston to Lilford Lodge |
Decision | Approved by Delegation |
Decision Date | 09 June 2014 |
Relevant Documents |
Application Number |
NCC - 13/00121/MINVOC |
---|---|
Location | Collyweston Quarry, Peterborough Road, Duddington, PE9 3QA |
Proposal | Variation of condition 1 of planning permission EN/98/374C - Extension of time for restoration operations |
Decision | Approved by Delegation |
Decision Date | 1 April 2014 |
Relevant Documents |
Application Number |
NCC - 13/00120/MINVOC |
---|---|
Location | Collyweston Quarry, Peterborough Road, Duddington, PE9 3QA |
Proposal | Variation of condition 30 of planning permission EN/97/802C - Extension of time for infilling and restoration operations |
Decision | Approved by Delegation |
Decision Date | 1 April 2014 |
Relevant Documents |
Application Number |
NCC - 13/00099/MINVOC |
---|---|
Location | Harley Way Quarry, Oundle |
Proposal | Regularise working - Variation of condition 7 (sequence of working), 14 (Details of Site Building), 18 (Internal Haul Road, 31 (Internal Routing Arrangements) and 43 (Stockpiling of Material) of planning permission 12/00001/MIN in order to regularise a number of mineral extraction related activities |
Decision | Approved by Delegation |
Decision Date | 20 January 2014 |
Relevant Documents |
|
Application Number |
NCC - 13/00086/WASFUL |
---|---|
Location | Kirby Lodge Composting Facility, Gretton Brook Road, Deene, Corby, NN17 3ES |
Proposal | Regrading of earth bund, the placement of inert material for storage purposes, retention of existing lagoon and provision of revised landscape scheme |
Decision | Approved by Delegation |
Decision Date | 13 January 2014 |
Relevant Documents |
2013
Application Numbers | NCC - 13/00090/WASVOC ENC - 13/01690/NCC |
---|---|
Location | Westwood AD Plant, Bedford Road, Rushden, NN10 0SQ |
Proposal | Variation of conditions 2 and 25 of planning permission 11/00078/WAS to increase throughputs from 49,000 to 65,000 tonnes per year, to remove the radial restriction on the area for digestate spreading and to increase the catchment area from which waste can be sourced |
Decision | Approved by Committee |
Decision Date | 20 December 2013 |
Relevant Documents |
Application Numbers | NCC - 13/00041/MINNMA ENC - 13/00870/NCC |
---|---|
Location | Ringstead Grange Quarry, Raunds Road, Ringstead, Northamptonshire |
Proposal | Non Material Amendment to planning permission 12/00016/MIN for the creation of a temporary site access and route to undertake initial earthworks |
Decision | Approved by Delegation |
Decision Date | 26 July 2013 |
Relevant Documents |
Application Numbers | NCC - 13/00022/WASFUL ENC - 13/00509/NCC |
---|---|
Location | Kirby Lodge Composting Facility, Gretton Brook Road, Deene |
Proposal | The installation of 2 leachate holding tanks |
Decision | Approved by Delegation |
Decision Date | 13 June 2013 |
Relevant Documents |
Application Numbers | NCC - 13/00004/MINVOC ENC - 13/00115/NCC |
---|---|
Location | Stonehill Quarry, Off Kings Cliffe Road, Northamptonshire, PE8 6NU |
Proposal | Variation of condition 14 (Time Limit) of planning permission 12/00078/MINFUL to change the time limit for completion to two years from the commencement of the development |
Decision | Approved by Delegation |
Decision Date | 28 March 2013 |
Relevant Documents |
Application Numbers | NCC - 12/00064/WASVOC ENC - 12/01888/NCC |
---|---|
Location | Rushden Waste Recycling Centre, Northampton Road, Rushden, NN10 6BW |
Proposal | Variation of conditions of planning permission EN/92/376C to alter the site layout and access |
Decision | Approved by Delegation |
Decision Date | 11 February 2013 |
Relevant Documents |
Application Numbers | NCC - 12/00078/MIN ENC - 12/01784/NCC |
---|---|
Location | Stonehill Quarry, Off Kings Cliffe Road, Northamptonshire, PE8 6NU |
Proposal | The extraction of limestone and importation of materials for engineering works associated with the construction of lakes |
Decision | Approved by Committee |
Decision Date | 04 January 2013 |
Relevant Documents |
2012
Application Numbers | NCC - 12/00016/MIN ENC - 12/000506/NCC.PRHAB |
---|---|
Location | Ringstead Grange, Ringstead, Northamptonshire, NN14 4DT |
Proposal | Proposed Limestone Quarry incorporating extraction of limestone and clay, inert waste recycling and progressive restoration of the site to a beneficial after use using imported inert material |
Decision | Approved by Committee |
Decision Date | 21 December 2012 |
Relevant Documents |
Application Numbers | NCC - 12/00031/WAS ENC - 12/00746/NCC/PJXW |
---|---|
Location | East Northants Resource Management Facility, Stamford Road, Kings Cliffe, Northamptonshire, PE8 6XX |
Proposal | Variation of conditions 7, 27 and 28 of planning permission APP/K2800/A/10/2126938/NWF to extend the end date until 31/12/2016 |
Decision | Approved by Committee |
Decision Date | 25 October 2012 |
Relevant Documents |
Application Forms |
Application Numbers | NCC - 12/00030/WAS ENC - 12/00745/NCC/PJXW |
---|---|
Location | East Northants Resource Management Facility, Stamford Road, Kings Cliffe, Northamptonshire, PE8 6XX |
Proposal | Variation of condition 22 of planning permission 07/00048/WAS to extend the end date until 31/12/2016 |
Decision | Approved by Committee |
Decision Date | 25 October 2012 |
Relevant Documents |
Application Forms |
Application Numbers | NCC - 12/00029/WAS ENC - 12/00744/NCC/PJXW |
---|---|
Location | East Northants Resource Management Facility, Stamford Road, Kings Cliffe, Northamptonshire, PE8 6XX |
Proposal | Variation of conditions 32 and 33 of planning permission EN/05/1264C to extend the end date until 31/12/2016 |
Decision | Approved by Committee |
Decision Date | 25 October 2012 |
Relevant Documents |
Application Forms |
Application Numbers | NCC - 12/00017/WAS ENC - EN/12/00505/NCC |
---|---|
Location | Islip STW, Ridge Road, Islip, Kettering, NN14 3LD |
Proposal | Erection of a GRP kiosk to house electrical and control equipment |
Decision | Approved by Delegation |
Decision Date | 24 May 2012 |
Relevant Documents |
Application Numbers | NCC - 12/00001/MIN ENC - EN/12/00135/NCC |
---|---|
Location | Harley Way Quarry, Harley Way, Churchfield, Oundle, PE8 5AU |
Proposal | Conservation Stone Quarry |
Decision | Approved by Committee |
Decision Date | 4 May 2012 |
Relevant Documents |
Application Numbers | NCC - 11/00089/WAS ENC - EN/12/00030/NCC |
---|---|
Location | Lowick Compost Site, Old Aldwincle Road, Lowick, Thrapston, NN14 3BL |
Proposal | Variation of condition 10 of planning permissions EN/07/0051C to allow receipt of green waste on Sundays and Bank and Public Holidays and for compost operations and receipt of waste for longer hours on Saturdays |
Decision | Approved by Committee |
Decision Date | 15 March 2012 |
Relevant Documents |
Application Numbers | NCC - 11/00084/WAS ENC - EN/11/02071/NCC/PAB |
---|---|
Location | Land of Wakerley Road, Harringworth |
Proposal | Construction of a new Sewage Treatment Works |
Decision | Approved by Delegation |
Decision Date | 1 March 2012 |
Relevant Documents |
Application Numbers | NCC - 09/00079/MIN ENC - EN/10/00013/NCC |
---|---|
Location | Lilford Lodge Farm, Lilford, Oundle, Peterborough, PE8 5SA |
Proposal | Excavation of sand and gravel mineral reserves to enable the construction of a 100 berth marina basin for recreational and leisure use |
Decision | Approved by Committee |
Decision Date | 2 February 2012 |
Relevant Documents |
Application Numbers | NCC - 11/00078/WAS ENC - EN/11/01863/NCC |
---|---|
Location | Westwood AD Plant, Bedford Road, Rushden, NN10 0SQ |
Proposal | Variation of condition 2 of planning permission 08/00002/WAS to increase the annual throughputs from 45,000 to 49,000 tpa and to allow digestate to be applied to farmland up to 5 miles from the plant |
Decision | Approved by Committee |
Decision Date | 23 January 2012 |
Relevant Documents |
Application Numbers | NCC - 11/00073/WAS ENC - EN/11/01938/NCC |
---|---|
Location | Westwood AD Plant, Bedford Road, Rushden, NN10 0SQ |
Proposal | Variation of condition 5 of planning permission 08/00002/WAS to allow public and bank holiday working |
Decision | Approved by Committee |
Decision Date | 23 January 2012 |
Relevant Documents |
2010
Application Numbers | NCC - 10/00002/WAS ENC - 10/00091/EXT |
---|---|
Location | Dodson and Horrell Ltd, Kettering Road, Islip, Kettering, NN14 3JW |
Proposal | Installation of a reedbed system to provide waste water processing plant |
Decision | Approved by Delegation |
Decision Date | 1 April 2010 |
Relevant Documents |
Application Numbers | NCC - 09/00053/WAS ENC - 09/01269/NCC |
---|---|
Location | East Northants Resource Management Facility, Stamford Road, King's Cliffe, Northamptonshire, PE8 6XX |
Proposal | Landfill disposal of low level radioactive waste in Phases 4B, 5A and 5B of the permitted hazardous waste landfill |
Decision | Refused by DC Committee |
Decision Date | 25 March 2010 |
Relevant Documents |
2009
Application Numbers | NCC - 09/00049/WAS ENC - 09/01143/NCC |
---|---|
Location | Lilford Lodge Farm, Lilford, Barnwell, Oundle, Peterborough, PE8 5SA |
Proposal | Retention of structures and operations in connection with the processing of construction and demolition waste and stone to produce building stone and other recycled building products |
Decision | Approved by Delegation |
Decision Date | 14 October 2009 |
Relevant Documents |
Application Numbers | NCC - 09/00047/MIN ENC - 09/01072/NCC |
---|---|
Location | Land north of Eaglethorpe, Warmington, Northants |
Proposal | Variation of condition 3 of planning permission EN/05/0236 to vary the details of the plant and ancillary works |
Decision | Approved by Delegation |
Decision Date | 2 October 2009 |
Relevant Documents |
Application Numbers | NCC - 09/00040/WAS ENC - 09/00808/NCC |
---|---|
Location | Churchfield Farm, Oundle, PE8 5AU |
Proposal | Restoration of old quarry using inert fill material, to provide a site for future biodiversity and recreation use |
Decision | Approved by Delegation |
Decision Date | 6 August 2009 |
Relevant Documents |
Application Numbers | NCC - 09/00027/WAS ENC - 09/00698/EXT |
---|---|
Location | Kirby Lodge, Gretton Road, Corby |
Proposal | Application to vary condition 15 that restricts waste sources to within a 20 mile radius of the site, under planning permission 07/00007/WAS that consent an In-vessel composting facility |
Decision | Approved by Delegation |
Decision Date | 9 July 2009 |
Relevant Documents |
Application Numbers | NCC - 09/00006/MIN ENC - 09/00193/EXT |
---|---|
Location | Castle Manor Farm, Titchmarsh Road, Thrapston, NN14 4NJ |
Proposal | Variation of condition 40 of planning permission 07/00035/MIN to extend the end date to 30/09/2015 |
Decision | Approved by Delegation |
Decision Date | 22 April 2009 |
Relevant Documents |
2008
Application Numbers | NCC - 08/00003/WAS ENC - 08/00194/NCC |
---|---|
Location | Land at Chelveston Renewable Energy Park, Chelveston |
Proposal | Construction and use of a biomass renewable energy plant |
Decision | Approved by Committee |
Decision Date | 22 December 2008 |
Relevant Documents |
Application Numbers | NCC - 08/00076/WAS ENC - 08/01845/NCC |
---|---|
Location | Land near Sewage Works, Armston Road, Barnwell |
Proposal | Creation of flood plain in compensation for tipping of inert waste to construct a track and bunds on land immediately to the north of the application site |
Decision | Approved by Delegation |
Decision Date | 8 December 2008 |
Relevant Documents |
Application Numbers | NCC - 08/00084/WAS ENC - 08/01898/EXT |
---|---|
Location | Hill Farm Estate, Irthlingborough Road, Little Addington, Kettering, NN14 4AS |
Proposal | Variation of condition 2a and 2b of planning permission EN/99/69C to allow Atlas Recycling to operate site |
Decision | Approved by Delegation |
Decision Date | 11 December 2008 |
Relevant Documents |
Application Numbers | NCC - 08/00048/WAS ENC - 08/01066/NCC |
---|---|
Location | Land at Kirby Lodge, Corby |
Proposal | Extension of the area for in-vessel composting |
Decision | Approved by Delegation |
Decision Date | 27 August 2008 |
Relevant Documents |
Application Numbers | NCC - 08/00002/WAS ENC - 08/00056/NCC |
---|---|
Location | Westwood, Higham Park, Rushden |
Proposal | Construction and operation of a farm-based anaerobic digestion plant |
Decision | Approved by Committee |
Decision Date | 15 May 2008 |
Relevant Documents |
Application Numbers | NCC - 08/00013/WAS ENC - 08/00518/NCC |
---|---|
Location | Raunds Sewage Treatment Works, Stanwick Road, Raunds, NN9 6TQ |
Proposal | Erection of a kiosk to house dosing equipment |
Decision | Approved by Delegation |
Decision Date | 31 March 2008 |
Relevant Documents |
Application Numbers | NCC - 07/00048/WAS ENC - 07/01838/NCC |
---|---|
Location | King's Cliffe Landfill Site, Stamford Road, King's Cliffe, Peterborough, PE8 6XX |
Proposal | Soil treatment facility |
Decision | Approved by Delegation |
Decision Date | 10 January 2008 |
Relevant Documents |
2007
Application Numbers | NCC - 07/00039/WAS ENC - 07/01572/NCC |
---|---|
Location | King's Cliffe Industrial Estate, King's Cliffe |
Proposal | Variation of condition 14 of planning permission EN/06/02506 |
Decision | Approved by Delegation |
Decision Date | 18 October 2007 |
Relevant Documents |
Application Numbers | NCC - 07/00038/WAS ENC - 07/01568/NCC |
---|---|
Location | Westwood, Higham Park, Rushden |
Proposal | Construction of anaerobic digestion plant for the processing of food chain waste into bio fertilizer and renewable energy |
Decision | Withdrawn |
Application Numbers | NCC - 07/00035/MIN ENC - 07/01478/NCC |
---|---|
Location | Land at Castle Manor Farm, Titchmarsh, Thrapston |
Proposal | Variation of conditions 7 and 8 of planning permission EN/01/23C to extend mineral workings |
Decision | Approved by Delegation |
Decision Date | 27 September 2007 |
Relevant Documents |
Application Numbers | ENC - 07/00099/NCC |
---|---|
Location | Hemington Sewage Treatment Works, off Main Street, Hemington, PE8 5QQ |
Proposal | Replacement of privately owned sewage treatment works, new kiosk, access road and telemetry aerial |
Decision | Approved by Delegation |
Decision Date | 16 April 2007 |
Relevant Documents |
Application Numbers | ENC - 07/00051/NCC |
---|---|
Location | Lowick Composting Site, Old Aldwincle Road, Lowick |
Proposal | Extension of composting area by means of mineral extraction and importation of wood waste |
Decision | Approved by Committee |
Decision Date | 21 March 2007 |
Relevant Documents |
Application Numbers | ENC - 06/02516/NCC |
---|---|
Location | The Potato Store, Barnwell Road, Oundle, Peterborough, PE8 5PB |
Proposal | Variation of condition 13 and 14 of planning permission EN/05/1247C |
Decision | Approved by Committee |
Decision Date | 19 February 2007 |
Relevant Documents |
Application Numbers | ENC - 06/02508/NCC |
---|---|
Location | King's Cliffe Industrial Estate, Wansford Road, King's Cliffe |
Proposal | Provision of a facility for recovery and sorting of glass to provide material suitable for recycling (retrospective) |
Decision | Approved by Committee |
Decision Date | 19 February 2007 |
Relevant Documents |
Application Numbers | ENC - 06/02506/NCC |
---|---|
Location | Land adjacent to King's Cliffe Industrial Estate, Wansford Road, King's Cliffe |
Proposal | Provision of a facility for sorting and processing mixed inert waste to provide material suitable for recycling (retrospective) |
Decision | Approved by Committee |
Decision Date | 19 February 2007 |
Relevant Documents |
2006
Application Numbers | ENC - 06/01279/NCC |
---|---|
Location | Collyweston Quarry, Near Duddington |
Proposal | Proposed extension of limestone quarry and restoration to woodland using imported inert waste |
Decision | Approved by Delegation |
Decision Date | 2 November 2006 |
Relevant Documents |
Application Numbers | ENC - 06/01517/NCC |
---|---|
Location | King's Cliffe Landfill Site |
Proposal | Installation and operation of gas flare and surface water pumping station |
Decision | Approved by Delegation |
Decision Date | 19 September 2006 |
Relevant Documents |
Application Numbers | ENC - 06/01419/NCC |
---|---|
Location | Lowick Composting Site, Old Aldwincle Road, Lowick |
Proposal | Extension to composting site |
Decision | Refused by Delegation |
Decision Date | 1 September 2006 |
Relevant Documents |
Application Numbers | ENC - 06/01416/NCC |
---|---|
Location | Land at Old Aldwincle Road, Lowick |
Proposal | Variation of condition 2 for planning permission EN/03/1434C |
Decision | Approved by Delegation |
Decision Date | 1 September 2006 |
Relevant Documents |
Application Numbers | ENC - 05/02356/NCC |
---|---|
Location | Land to the North of Eaglethorpe, Warmington |
Proposal | Erection of a low profile sand and gravel processing plant |
Decision | Approved by Delegation |
Decision Date | 23 February 2006 |
Relevant Documents |
Application Numbers | ENC - 05/01694/NCC |
---|---|
Location | Barnwell Country Park, Barnwell Road, Oundle, Peterborough |
Proposal | Erection of new visitor facilities |
Decision | Approved by Delegation |
Decision Date | 19 January 2006 |
Relevant Documents |
2005
Application Numbers | ENC - 05/01484/NCC |
---|---|
Location | Land adjacent to Willow Brook, Bulwick Road, Blatherwycke |
Proposal | Extraction of soils to create siltation control lake |
Decision | Approved by Delegation |
Decision Date | 12 October 2005 |
Relevant Documents |
Application Numbers | ENC - 05/01247/NCC |
---|---|
Location | The Potato Store, Oundle Road, Barnwell, Oundle, Peterborough |
Proposal | Change of use to materials recovery facility for construction and demolition waste |
Decision | Approved by Delegation |
Decision Date | 5 September 2005 |
Relevant Documents |
2004
Application Numbers | ENC - 04/01694/NCC |
---|---|
Location | Land at Old Aldwincle Road, Lowick |
Proposal | Minor extraction of limestone aggregate |
Decision | Approved by Delegation |
Decision Date | 8 November 2004 |
Relevant Documents |
Application Numbers | ENC - 04/01726/NCC |
---|---|
Location | Land off Kettering Road, Islip |
Proposal | Excavation of borrow pit in association with Thrapston Flood Management Scheme |
Decision | Approved by Delegation |
Decision Date | 20 October 2004 |
Relevant Documents |
Application Numbers | ENC - 04/00979/NCC |
---|---|
Location | Land at The Warg, Bridge Street, Thrapston |
Proposal | Extension of time of planning permission EN/01/822C for the raising of ground level to 30.5m AOD through the importation of inert waste material |
Decision | Approved by Delegation |
Decision Date | 7 July 2004 |
Relevant Documents |
Application Numbers | ENC - 02/00846/NCC |
---|---|
Location | Land north of Eaglethorpe, Warmington, Peterborough |
Proposal | Construction of agricultural reservoir, extraction of sand and gravel and importation of engineering clay |
Decision | Approved by Delegation |
Decision Date | 2 July 2004 |
Relevant Documents |
Application Numbers | ENC - 03/01434/NCC |
---|---|
Location | Land at Old Aldwincle Road, Lowick |
Proposal | Green waste composting facility |
Decision | Approved by Delegation |
Decision Date | 9 February 2004 |
Relevant Documents |
2022
Application number | NN/22/00050/WASFUL |
---|---|
Location |
Rothwell Lodge AD Facility, Rothwell Road, Kettering, Northamptonshire, NN16 8XF |
Proposal |
Construction of additional feedstock storage, digester, pasteuriser, digestate storage tanks and installation of associated pipework and equipment, relocation of biogas upgrading equipment, propane tanks and associated infrastructure, increase waste throughput from 49,000 to 100,000 tonnes per annum, extension of waste reception building and installation of second feedstock line internally and replacement / upgrading of existing odour abatement systems |
Decision | Approved by committee |
Decision date | 15 May 2023 |
Submitted information
View the submitted documents for this application:
Location |
Fernbrook Bio Limited, Rothwell Road, Kettering, NN16 8XF |
---|---|
Proposal |
Construction of additional feedstock storage, digester, pasteuriser, digestate storage tanks and installation of associated pipework and equipment, relocation of biogas upgrading equipment, propane tanks and associated infrastructure, increase waste throughput from 49,000 to 100,000 tonnes per annum, extension of waste reception building and installation of second feedstock line internally and replacement / upgrading of existing odour abatement systems |
Decision | Approved by committee |
Decision date | 15 May 2023 |
Submitted information
View the submitted documents for this application:
Supporting information
- Planning Statement (PDF 1.3MB)
- Transport Statement (PDF 2.2MB)
- Air Quality Assessment (PDF 906KB)
- Noise Assessment (PDF 2MB)
- Preliminary Ecological Appraisal (PDF 4.6MB)
- Landscape and Visual Assessment (PDF 1MB)
- Landscape and Visual Assessment - Appendix 1 Methodology (PDF 684KB)
- Landscape and Visual Assessment - Appendix 2 Figures (PDF 7MB)
- Landscape and Visual Assessment - Appendix 3 Viewpoints Part 1 (PDF 4.5MB)
- Landscape and Visual Assessment - Appendix 3 Viewpoints Part 2 (PDF 5.4MB)
- Landscape and Visual Assessment - Appendix 3 Viewpoints Part 3 (PDF 5.1MB)
- Landscape and Visual Assessment - Appendix 3 Viewpoints Part 4 (PDF 5.7MB)
- Landscape and Visual Assessment - Appendix 3 Viewpoints Part 5 (PDF 932KB)
- Pre-App Response (PDF 129KB)
Plans
- Site Location Plan (PDF 596KB)
- Planning Boundary (PDF 2.8MB)
- Proposed Elevations A (PDF 1.1MB)
- Proposed Elevations B (PDF 417KB)
- Piping Plan (PDF 911KB)
Make a comment
2021
Application numbers | NN/21/00012/WASVOC |
---|---|
Location |
Rushton Landfill Generating Station, Rushton Landfill, Oakley Road, Rushton, Kettering, Northamptonshire, NN14 1QT |
Proposal |
Variation of condition 9 of planning permission KE/06/245 to extend the life of the generation station for a further 15 years |
Decision | Approved by Delegation |
Decision date | 21 July 2021 |
Relevant documents |
Supporting InformationPlans |
Application numbers | NCC - 20/00063/WASFUL KBC - KET/2020/0856/NCC |
---|---|
Location |
Fernbrook Bio Limited, Rothwell Road, Kettering, Northamptonshire, NN16 8XF |
Proposal |
Construction of biogas scrubbing columns, gas clean-up container, compressor, distribution kiosk, propane tanks, grid entry unit and export pipeline to grid |
Decision | Approved by Delegation |
Decision date | 10 February 2021 |
Relevant documents |
Supporting information
Plan |
2020
Application numbers | NCC - 20/00046/WASVOC KBC - KET/2020/0823/NCC |
---|---|
Location |
Cranford Landfill Site, Thrapston Road, Cranford, Kettering, Northamptonshire, NN14 4AW |
Proposal |
Variation of condition 34 (End Date) of planning permission 17/00032/WASVOC to allow a further four year time period (until 31 October 2025) to complete the restoration of the landfill site |
Decision | Approved by Delegation |
Decision date | 09 December 2020 |
Relevant documents |
Supporting information
Plan |
Application numbers | NCC - 18/00028/WASVOC KBC - KET/2018/0533/NCC |
---|---|
Location | Rushton Landfill Site, Oakley Road, Rushton, Kettering, Northamptonshire, NN14 1QS |
Proposal | Variation of Conditions 7 (Fire Risk), 8 (Heavy Goods Vehicle Movements), 12 (Odour, Noise and Dust), 31 and 32 (Lorry Routing, Wheel Cleaning and Vehicle Sheeting) of planning consent ref.: 15/00086/WASVOC to allow the delivery and tipping of inert waste within the Waste Transfer Station building during the night time. |
Decision | Withdrawn |
Decision date | 24 April 2020 |
Relevant documents |
Supporting information |
Application numbers | NCC - 18/00027/WASVOC KBC - KET/2018/0530/NCC |
---|---|
Location | Rushton Landfill Site, Oakley Road, Rushton, Kettering, Northamptonshire, NN14 1QS |
Proposal | Variation of Conditions 18, 19 (Odour, Noise and Dust), 24 and 25 (Hours of Working) of planning consent ref.: 15/00087/WASVOC to allow the delivery and tipping of inert waste within the Waste Transfer Station building during the night time. |
Decision | Withdrawn |
Decision date | 24 April 2020 |
Relevant documents |
Supporting information |
2019
Application numbers | NCC - 19/00052/WASFUL KBC - KET/2019/0567/NCC |
---|---|
Location | Unit 13, Henson Way, Telford Way Industrial Estate, Kettering NN16 8PX |
Proposal | A proposed development of the yard area to accommodate a sealed asbestos waste skip |
Decision | Approved by Delegation |
Decision date | 04 October 2019 |
Relevant documents |
Supporting informationPlans |
2018
Application numbers | NCC - 18/00039/WASCOU KBC - KET/2018/0778 |
---|---|
Location | Pytchley Lodge Road Industrial Estate, Pytchley Lodge Road, Kettering, Northamptonshire NN15 6JJ |
Proposal | Change of use from B2 (General Industrial) to mixed use B2 (General Industrial and processing of end of life vehicles) |
Decision | Approved by Delegation |
Decision date | 11 December 2018 |
Relevant documents |
Supporting informationPlans |
Application numbers |
NCC - 18/00016/WASVOC |
---|---|
Location | Long Drowpits Gullet, A43 Weekley Wood Lane, Weekley, Northamptonshire |
Proposal | Variation of Condition 21 (End Date) of planning consent ref. 08/00082/WAS to extend the end date |
Decision | Approved by Delegation |
Decision date | 26 September 2018 |
Relevant documents |
Supporting informationPlans |
2017
Application numbers |
NCC - 17/00032/WASVOC |
---|---|
Location | Cranford Landfill Site, Thrapston Road, Cranford, Kettering, Northamptonshire, NN14 4AW |
Proposal | Variation of Conditions 3 (Scope of Planning Permission), 24 (Landscaping), 29 (Restoration - Gullets), 32 (Restoration - Access Route), 33 (Aftercare) and 34 (End Date) of planning consent 16/00030/WASVOC to extend the restoration end date, and confirm the site restoration, landscaping and aftercare scheme |
Decision | Approved by Delegation |
Decision date | 26 September 2017 |
Relevant documents |
Application Numbers |
NCC - 17/00004/WASVOC |
---|---|
Location | Rushton Landfill Site, Oakley Road, Rushton, Kettering, Northamptonshire, NN14 1QS |
Proposal | Variation of Condition 12 (Final Landform Profile and Contours) of planning permission 08/00102/WAS |
Decision | Approved by Delegation |
Decision Date | 25 April 2017 |
Relevant Documents |
Application Numbers |
NCC - 17/00003/WASVOC |
---|---|
Location | Rushton Landfill Site, Oakley Road, Rushton, Kettering, Northamptonshire, NN14 1QS |
Proposal | Variation of Condition 39 (Restoration Scheme and Landscaping Scheme) of planning permission 11/00047/WAS |
Decision | Approved by Delegation |
Decision Date | 25 April 2017 |
Relevant Documents |
Application Numbers |
NCC - 17/00002/WASVOC |
---|---|
Location | Rushton Landfill Site, Oakley Road, Rushton, Kettering, Northamptonshire, NN14 1QS |
Proposal | Variation of Condition 39 (Restoration Scheme and Landscaping Scheme) of planning permission 11/00048/WAS |
Decision | Approved by Delegation |
Decision Date | 25 April 2017 |
Relevant Documents |
2016
Application Numbers |
NCC - 16/00030/WASVOC |
---|---|
Location | Cranford Landfill Site, Thrapston Road, Cranford, Kettering, Northamptonshire, NN14 4AW |
Proposal | Variation of Condition 28 of planning permission 09/00016/WAS to amend the final levels of the northern and southern extension (Areas A & B) |
Decision | Approved by Delegation |
Decision Date | 21 October 2016 |
Relevant Documents |
Application Numbers |
NCC - 15/00087/WASVOC |
---|---|
Location | Rushton Landfill Site, Oakley Road, Rushton, Kettering, NN14 1QS |
Proposal | Variation of conditions 8, 22 and 23 of planning permission 15/00068/WASVOC to allow the disposal of inert materials from essential highway maintenance works |
Decision | Approved by Delegation |
Decision Date | 1 April 2016 |
Relevant Documents |
Application Numbers |
NCC - 15/00086/WASVOC |
---|---|
Location | Rushton Landfill Site, Oakley Road, Rushton, Kettering, NN14 1QS |
Proposal | Variation of conditions 7 and 8 of planning permission 15/00067/WASVOC to allow the disposal of inert materials from essential highway maintenance works |
Decision | Approved by Delegation |
Decision Date | 1 April 2016 |
Relevant Documents |
Application Numbers |
NCC - 15/00069/WASCOU |
---|---|
Location | Pytchley Lodge Industrial Estate, Pytchley Lodge Road, Kettering, NN15 6JQ |
Proposal | Change of use of existing small industrial unit (adjacent to the main building) to Waste Transfer Station with incinerator |
Decision | Approved by Delegation |
Decision Date | 28 January 2016 |
Relevant Documents |
2015
Application Numbers |
NCC - 15/00068/WASVOC |
---|---|
Location | Rushton Landfill Site, Oakley Road, Rushton, Kettering, NN14 1QS |
Proposal | Variation of condition 20 of planning permission 14/00019/WASFUL for extended operating hours |
Decision | Approved by Delegation |
Decision Date | 8 December 2015 |
Relevant Documents |
Application Numbers |
NCC - 15/00067/WASVOC |
---|---|
Location | Rushton Landfill Site, Oakley Road, Rushton, Kettering, NN14 1QS |
Proposal | Variation of condition 8 of planning permission 11/00049/WAS for extended operating hours |
Decision | Approved by Delegation |
Decision Date | 8 December 2015 |
Relevant Documents |
Application Numbers |
NCC - 15/00052/WASNMA |
---|---|
Location | Storefield Lodge, Oakley Road, Rushton, Kettering, Northamptonshire, NN14 1QT |
Proposal | Non-Material Amendment to Planning Permission 11/00046/WAS for retrospective installation of an internal road |
Decision | Approved by Delegation |
Decision Date | 28 July 2015 |
Relevant Documents |
Application Numbers |
NCC - 15/00046/WASNMA |
---|---|
Location | Shanks Waste Management, Telford Way, Kettering, Northamptonshire, NN16 8UN |
Proposal | Non-Material Amendment to Planning Permission 11/00020/WAS to alter the site layout for purposes of inert waste washing and screening |
Decision | Approved by Delegation |
Decision Date | 16 July 2015 |
Relevant Documents |
Application Numbers |
NCC - 15/00021/WASFUL |
---|---|
Location | Barton Seagrave Cricket Club, Barton Road, Barton Seagrave, Kettering, Northamptonshire, NN15 6TW |
Proposal | Importation of inert materials to level the land at Barton Seagrave cricket ground |
Decision | Approved by Delegation |
Decision Date | 08 July 2015 |
Relevant Documents |
Application Numbers |
NCC - 14/00081/WASFUL |
---|---|
Location | Volvo Truck and Bus Ltd, Pytchley Lodge Road Industrial Estate, Pytchley Lodge Road, Kettering, Northamptonshire, NN15 6JJ |
Proposal | Proposed change of use from truck sales and service centre to recycling of electrical products |
Decision | Approved by Delegation |
Decision Date | 23 January 2015 |
Relevant Documents |
2014
Application Numbers |
NCC - 14/00068/WASVOC |
---|---|
Location | Fernbrook Bio Ltd, Rothwell Lodge, Rothwell Road, Kettering, Northamptonshire, NN16 8XF |
Proposal | Variation of Condition 23 (Waste Catchment Area) on Planning Permission 11/00067/WAS |
Decision | Approved by Delegation |
Decision Date | 13 September 2014 |
Relevant Documents |
Application Numbers |
NCC - 14/00019/WASFUL |
---|---|
Location | Storefield Lodge, Oakley Road, Rushton, Kettering, NN14 1QT |
Proposal | Proposed extension to the waste reception building and construction of a solid recovered fuel (SRF) facility and concrete batching plant |
Decision | Approved by DC Committee |
Decision Date | 22 July 2014 |
Relevant Documents |
Application Numbers |
NCC - 14/00015/WASVOC |
---|---|
Location | Fernbrook Bio Ltd, Rothwell Lodge Farm, Rothwell Road, Kettering, NN16 8XF |
Proposal | Removal of condition 23 (waste catchment area) on planning permission 11/00067/WAS |
Decision | Refused by Delegation |
Decision Date | 10 June 2014 |
Relevant Documents |
Application Numbers |
NCC - 13/00112/WASFUL |
---|---|
Location | Kettering Household Waste Recycling Centre, Garrard Way, Kettering, NN16 8TD |
Proposal | Installation of a prefabricated re-locatable 2 storey modular building on an existing bitumen surface at Kettering Household Waste Recycling Centre, for use as a teaching classroom for school and community groups to visit and learn about waste and energy |
Decision | Approved by Delegation |
Decision Date | 26 March 2014 |
Relevant Documents |
Application Numbers |
NCC - 14/00014/WASNMA |
---|---|
Location | Cranford Landfill Site, Thrapston Road, Cranford, Kettering, NN14 4AW |
Proposal | Non-material amendment to planning permission KE/06/301C for the re-siting of gas engines |
Decision | Approved |
Decision Date | 24 March 2014 |
Relevant Documents |
Application Numbers |
NCC - 14/00002/WASFUL |
---|---|
Location | Sewage Farm, Church Road, Pytchley, Kettering, Northamptonshire |
Proposal | Installation of a glass-reinforced plastic (GRP) kiosk to house electrical control equipment |
Decision | Approved by Delegation |
Decision Date | 21 March 2014 |
Relevant Documents |
2013
Application Numbers |
NCC - 13/00003/WASFUL |
---|---|
Location | Glebe Farm, Rothwell Road, Kettering, NN16 8XF |
Proposal | Change of use of land and related works to provide pallet storage and refurbishment and waste recycling facility. (in combination with retained agricultural use for part of site) |
Decision | Approved by Delegation |
Decision Date | 30 September 2013 |
Relevant Documents |
Application Numbers |
NCC - 13/00052/WASFUL |
---|---|
Location | Rothwell Lodge, Kettering Road, Rothwell, Kettering, NN16 8XF |
Proposal | Installation of additional de-sulphurization tank |
Decision | Approved by Delegation |
Decision Date | 19 July 2013 |
Relevant Documents |
2012
Application Numbers | NCC - 12/00068/WASVOC KBC - KET/2012/0604 |
---|---|
Location | Long Drowpits, The Boughton Estate, Weekley, Kettering |
Proposal | Variation of condition 21 of planning permission 08/00081/WAS to extend the time limit for restoration |
Decision | Approved by Delegation |
Decision Date | 19 December 2012 |
Relevant Documents |
Application Numbers | NCC - 12/00043/WASFUL KBC - KET/2012/0400 |
---|---|
Location | Land Off Eagle Avenue, Magnetic Park, Desborough, Northamptonshire |
Proposal | Erection and installation of an Energy Centre with the capacity to produce Combined Heat and Power through Energy from Waste technology and including associated buildings, plant and machinery, formation of access and associated works |
Decision | Approved by Committee |
Decision Date | 19 December 2012 |
Application Numbers | NCC - 12/00018/WAS KBC - KET/2012/0229 |
---|---|
Location | Woodside, Stoke Albany Road, Desborough |
Proposal | Erection of a waste materials storage and handling barn together with associated ancillary service buildings to facilitate the operation of a waste transfer site. |
Decision | Approved by Delegation |
Decision Date | 22 June 2012 |
Relevant Documents |
Application Numbers | NCC - 12/00003/WAS KBC - KET/2012/0105/NCC |
---|---|
Location | Shanks Waste Solutions, Telford Way, Telford Way Industrial Estate, Kettering, NN16 8UN |
Proposal | Variation of condition 23 (catchment area) of planning permission 11/00020/WAS |
Decision | Approved by Delegation |
Decision Date | 7 May 2012 |
Relevant Documents |
Application Numbers | NCC - 11/00070/WAS KBC - KET/2011/0688/NCC |
---|---|
Location | Bottom Farm, Desborough Airfield, Stoke Albany Road, Desborough, Kettering, NN14 2SP |
Proposal | Relocation of Vehicle Dismantling Yard |
Decision | Approved by Delegation |
Decision Date | 9 January 2012 |
Relevant Documents |
2011
Application Numbers | NCC - 11/00067/WAS KBC - KET/2011/0657 |
---|---|
Location | Fernbrook Bio Limited, Rothwell Lodge Farm, Rothwell, Kettering, NN16 8XF |
Proposal | Variation of condition 3 of planning permission 10/00076/WAS to increase total annual throughput to 49,000 tonnes per annum |
Decision | Approved by Committee |
Decision Date | 16 December 2011 |
Relevant Documents |
Application Numbers | NCC - 11/00066/WAS KBC - KET/2011/0656 |
---|---|
Location | Fernbrook Bio Limited, Rothwell Lodge Farm, Rothwell, Kettering, NN16 8XF |
Proposal | Erection of new digester tank and plastics recycling building |
Decision | Approved by Committee |
Decision Date | 16 December 2011 |
Relevant Documents |
Application Numbers | NCC - 11/00049/WAS KBC - KET/2011/0533/NCC |
---|---|
Location | Storefield Lodge Waste Management Park, Oakley Road, Rushton, Kettering, NN14 1RS |
Proposal | Variation of conditions 3 (hours) and 13 (end date) of planning permission 10/00004/WAS |
Decision | Approved by Committee |
Decision Date | 11 November 2011 |
Relevant Documents |
Application Numbers | NCC - 11/00048/WAS KBC - KET/2011/0532/NCC |
---|---|
Location | Storefield Lodge Waste Management Park, Oakley Road, Rushton, Kettering, NN14 1RS |
Proposal | Variation of conditions 12 (restoration contours) and 22 (end date) of planning permission 09/0018/WAS |
Decision | Approved by Committee |
Decision Date | 11 November 2011 |
Relevant Documents |
Application Numbers | NCC - 11/00047/WAS KBC - KET/2011/0531/NCC |
---|---|
Location | Storefield Lodge Waste Management Park, Oakley Road, Rushton, Kettering, NN14 1RS |
Proposal | Variation of conditions 11 (restoration contours), 21 (end date) and 22 (catchment area) of planning permission 08/00101/WAS |
Decision | Approved by Committee |
Decision Date | 11 November 2011 |
Relevant Documents |
Application Numbers | NCC - 11/00046/WAS KBC - KET/2011/0530 |
---|---|
Location | Storefield Lodge Waste Management Park, Oakley Road, Rushton, Kettering, NN14 1RS |
Proposal | Northern Extension to Storefield Lodge (Rushton Landfill), including the extraction of limestone and the diversion of Storefield Brook. |
Decision | Approved by Committee |
Decision Date | 11 November 2011 |
Relevant Documents |
Application Numbers | NCC - 11/00020/WAS KBC - KET/2011/0229 |
---|---|
Location | Furnace Park, Old Telford Way, Telford Way Industrial Estate, Kettering, NN16 8UN |
Proposal | Variation of condition 2 of planning permission 10/00059/WAS to amend the layout of the site |
Decision | Approved by Delegation |
Decision Date | 13 June 2011 |
Relevant Documents |
Application Numbers | NCC - 10/00076/WAS KBC - KET/2010/0751 |
---|---|
Location | Rothwell Lodge Farm, Rothwell, Kettering, NN16 8XF |
Proposal | Variation of planning permission 09/00033/WAS to remove condition 16 (Highway Safety and Access) |
Decision | Approved by DC Committee |
Decision Date | 26 January 2011 |
Relevant Documents |
Application Numbers | NCC - 10/00059/WAS KBC - KET/2010/0628 |
---|---|
Location | Furnace Park, Old Telford Way, Telford Way Industrial Estate, Kettering, NN16 8UN |
Proposal | The extension of an existing building, the construction of a canopy and ancillary works to facilitate an increase in annual throughput from 125,000 tonnes to 215,000 tonnes of mixed, non-hazardous and inert waste |
Decision | Approved by DC Committee |
Decision Date | 26 January 2011 |
Relevant Documents |
Application Numbers | NCC - 10/00061/WAS KBC - KET/2010/0615 |
---|---|
Location | Furnace Park, Old Telford Way, Telford Way Industrial Estate, Kettering, NN16 8UN |
Proposal | Variation of condition 11 of planning permission 08/00071/WAS to increase the waste catchment area to a 50 mile radius |
Decision | Withdrawn on 14 January 2011 |
Application Numbers | NCC - 10/00060/WAS KBC - KET/2010/0630 |
---|---|
Location | Furnace Park, Old Telford Way, Telford Way Industrial Estate, Kettering, NN16 8UN |
Proposal | Variation of condition 5 of planning permission 08/00071/WAS to amend the hours of operation and restrictions on outside operations |
Decision | Withdrawn on 14 January 2011 |
2010
Application Numbers | NCC - 10/00035/WAS KBC - KET/2010/0339 |
---|---|
Location | Blackbridge Farm, Cranford Road, Kettering, NN15 5JJ |
Proposal | Variation of condition 2 of planning permission 09/00014/WAS for the installation of additional plant to improve the efficiency of the waste operations and material processing |
Decision | Withdrawn on 21 September 2010 |
Application Numbers | NCC - 10/00020/WAS KBC - KET/2010/0185 |
---|---|
Location | Kettering Household Waste Recycling Centre, Garrard Way, Telford Way Industrial Estate, Kettering, NN16 8TD |
Proposal | Variation of condition 7 of planning permission 09/00034/WAS to extend the current permitted opening times |
Decision | Approved by Delegation |
Decision Date | 28 May 2010 |
Relevant Documents |
Application Numbers | NCC - 10/00004/WAS KBC - KET/2010/0039 |
---|---|
Location | Storefield Lodge, Oakley Road, Rushton, Kettering, NN14 1RS |
Proposal | Variation of condition 14 of planning permission 08/00069/WAS to vary the end date of waste recycling operations to 30 September 2017 |
Decision | Approved by Delegation |
Decision Date | 14 April 2010 |
Relevant Documents |
Application Numbers | NCC - 10/00011/NMA KBC - KET/2010/0144/NCC |
---|---|
Location | Kettering Household Waste Recycling Centre, Garrad Way, Telford Way Industrial Estate, Kettering, NN16 8TD |
Proposal | Non-material amendment to 09/00034/WAS for surface level changes to external roads and hard landscaped areas |
Decision | Approved |
Decision Date | 26 March 2010 |
Relevant Documents |
2009
Application Numbers | NCC - 09/00033/WAS KBC - KET/2009/0295 |
---|---|
Location | Rothwell Lodge Farm, Rothwell, Kettering, NN16 8XF |
Proposal | Anaerobic digestion plant (1 waste reception/handling building, 2 digester tanks, 2 pre-storage tanks, 1 feedstock buffer tanks, 2 big estate storage tanks) and associated hard surfacing and landscaping |
Decision | Approved by DC Committee |
Decision Date | 22 October 2009 |
Relevant Documents |
Application Numbers | NCC - 09/00034/WAS KBC - KET/2009/0311 |
---|---|
Location | Land of Robinson Way and Garrad Way, Kettering |
Proposal | Proposed relocation of the existing Household Waste Recycling Centre located within Telford Way Industrial Estate, to the land situated at the rear of the Kettering Depot on Robinson Way and the construction of a new access onto the application site from Garrard Way |
Decision | Approved by Delegated |
Decision Date | 29 July 2009 |
Relevant Documents |
Application Numbers | NCC - 09/00016/WAS KBC - KET/2009/0162 |
---|---|
Location | Cranford Landfill Site, Thrapston Road, Cranford St John, Kettering, NN14 4HY |
Proposal | Variation of conditions 12, 20, 21 and 22 of planning permission KE/02/547C for the extension of end date of landfill site to 31/10/2017, revision of restoration contours and the siting of a gas flare stack |
Decision | Approved by Delegation |
Decision Date | 18 June 2009 |
Relevant Documents |
Application Numbers | NCC - 09/00018/WAS KBC - KET/2009/0187 |
---|---|
Location | Storefield Lodge, Oakley Road, Rushton, Kettering, NN14 1QT |
Proposal | Green waste composting, bioremediation, recovery of limestone and additional non-hazardous waste landfill |
Decision | Approved by Delegation |
Decision Date | 15 June 2009 |
Relevant Documents |
Application Numbers | NCC - 09/00014/WAS KBC - KET/2009/0128 |
---|---|
Location | Blackbridge Farm, Cranford Road, Kettering, NN15 5JJ |
Proposal | Bio-drying and pyrolysis waste management facility |
Decision | Approved by Delegation |
Decision Date | 20 May 2009 |
Relevant Documents |
Application Numbers | NCC - 08/00101/WAS KBC - KET/2008/1038 |
---|---|
Location | Rushton Quarry, Oakley Road, Rushton, NN14 1RS |
Proposal | Variation of condition numbers 12 and 21 of planning permission KE/89/714C to facilitate revision to approved contours |
Decision | Approved by Delegation |
Decision Date | 4 March 2009 |
Relevant Documents |
Application Numbers | NCC - 08/00102/WAS KBC - KET/2008/1043 |
---|---|
Location | Rushton Quarry, Oakley Road, Rushton, NN14 1RS |
Proposal | Extension to Rushton Landfill Site and modification to working scheme including the recovery and processing of limestone |
Decision | Approved by Delegation |
Decision Date | 3 March 2009 |
Relevant Documents |
Application Numbers | NCC - 08/00093/WAS KBC - KET/2008/0963 |
---|---|
Location | The Piggeries, Cranford Road, Burton Latimer, Kettering |
Proposal | Restoration of previously quarried land to agriculture using imported soils |
Decision | Approved by DC Committee |
Decision Date | 29 January 2009 |
Relevant Documents |
Application Numbers | NCC - 08/00086/WAS KBC - KET/2008/0878 |
---|---|
Location | Rushton Quarry, Oakley Road, Rushton, Kettering, NN14 1RS |
Proposal | Variation of condition 12 of planning permission KE/89/0714 to facilitate to revision to the approved contours |
Decision | Approved by Delegation |
Decision Date | 6 January 2009 |
Relevant Documents |
Application Numbers | NCC - 08/00085/WAS KBC - KET/2008/0877 |
---|---|
Location | Rushton Quarry, Oakley Road, Rushton, Kettering, NN14 1RS |
Proposal | Re-contouring of the southern slope of the existing landfill site |
Decision | Approved by Delegation |
Decision Date | 6 January 2009 |
Relevant Documents |
2008
Application Numbers | NCC - 08/00082/WAS KBC - KET/2008/0863 |
---|---|
Location | Long Drowpits Gullet, The Boughton Estate, Weekley, Kettering |
Proposal | Extension of Long Drowpits landfill site with associated clay extraction and retention of the recycling area |
Decision | Approved by Delegation |
Decision Date | 22 December 2008 |
Relevant Documents |
Application Numbers | NCC - 08/00081/WAS KBC - KET/2008/0850 |
---|---|
Location | Long Drowpits Gullet, The Boughton Estate, Weekley, Kettering |
Proposal | Amended restoration contours and timescale for completion of the inert waste landfill in the area of Long Drowpits Phase 2 |
Decision | Approved by Delegation |
Decision Date | 22 December 2008 |
Relevant Documents |
Application Numbers | NCC - 08/00071/WAS KBC - KET/2008/0807 |
---|---|
Location | Furnace Park, Old Telford Way, Telford Way Industrial Estate, Kettering |
Proposal | Variation of condition 3, 5 and 11 of planning permissions KE/04/1336 and KE/07/0113 to amend hours of operation and restrictions on outside operations |
Decision | Approved by Delegation |
Decision Date | 21 November 2008 |
Relevant Documents |
Application Numbers | NCC - 08/00069/WAS KBC - KET/2008/0791 |
---|---|
Location | Rushton Landfill Site, Oakley Road, Rushton, Kettering, NN14 1RS |
Proposal | Erection of a covered waste recycling facility for the reception and recycling of non hazardous waste materials and skip storage |
Decision | Approved by Delegation |
Decision Date | 19 November 2008 |
Relevant Documents |
Application Numbers | NCC - 08/00044/WAS KBC - KET/2008/0521 |
---|---|
Location | Land to the East of The Piggeries, Cranford Road, Burton Latimer, Kettering |
Proposal | Restoration of previously quarried land to agriculture using imported soils |
Decision | Withdrawn on 15 August 2008 |
Application Numbers | NCC - 08/00012/WAS KBC - KET/2008/0198 |
---|---|
Location | Old Telford Way, Kettering |
Proposal | Variation of conditions of planning permissions KE/04/1336 and KE/07/0113 to amend hours of operation and restrictions on outside operations |
Decision | Approved by Delegation |
Decision Date | 23 May 2008 |
Relevant Documents |
2007
Application Numbers | NCC - 07/00061/WAS KBC - KET/2008/1053 |
---|---|
Location | Kettering Borough Council Depot, Robinson Way, Kettering |
Proposal | Household waste recycling and collection facility |
Decision | Withdrawn on 20 December 2007 |
Application Numbers | KBC - KET/2007/0319 |
---|---|
Location | Wharf Lodge, Harrington, Kettering, NN6 9NP |
Proposal | Change of use to operate a waste transfer station and recycling centre |
Decision | Withdrawn on 21 June 2007 |
Application Numbers | KBC - KET/2007/0113 |
---|---|
Location | Furnace Park, Telford Way, Kettering |
Proposal | Erection of a new shed to provide a tipping hall to facilitate the transfer and bulking of waste |
Decision | Approved by Delegation |
Decision Date | 29 March 2007 |
Relevant Documents |
2006
Application Numbers | KBC - KET/2006/0891 |
---|---|
Location | Storefield Plant, Storefield Road, Rushton, Kettering |
Proposal | Bio Diesel Research and Development Project |
Decision | Approved by Delegation |
Decision Date | 17 November 2006 |
Relevant Documents |
Application Numbers | KBC - KET/2006/0578 |
---|---|
Location | Bottom Farm, Stoke Albany Road, Desborough |
Proposal | Change of use from a storage facility for building materials to a processing site for salvaged building materials to be recycled for conservation purposes |
Decision | Withdrawn on 10 November 2006 |
Application Numbers | KBC - KET/2006/0560 |
---|---|
Location | Land at Duck End Farm, Cranford |
Proposal | Use of previously imported waste materials |
Decision | Approved by Delegation |
Decision Date | 8 August 2006 |
Relevant Documents |
Application Numbers | KBC - KET/2006/0301 |
---|---|
Location | Cranford Landfill Site, Thrapston Lane, Cranford St John |
Proposal | Installation of landfill gas fuelled power generation plant as part of a renewable energy scheme |
Decision | Approved by Delegation |
Decision Date | 15 May 2006 |
Relevant Documents |
Application Numbers | KBC - KET/2006/0245 |
---|---|
Location | Rushton Landfill Site, Oakley Road, Rushton |
Proposal | Development of land without complying with condition 7a of planning permission KE/01/0361 |
Decision | Approved by Delegation |
Decision Date | 5 May 2006 |
Relevant Documents |
2005
Application Numbers | KBC - KET/2005/0867 |
---|---|
Location | Wood Lodge Buildings, Duck End, Cranford |
Proposal | Change of use of agricultural building to a temporary storage of clean agricultural plastic waste |
Decision | Approved by Delegation |
Decision Date | 4 November 2005 |
Relevant Documents |
Application Numbers | KBC - KET/2005/0774 |
---|---|
Location | Wood Lodge Buildings, Duck End, Cranford |
Proposal | Change of use of agricultural building to a temporary storage of clean agricultural plastic waste |
Decision | Approved by Delegation |
Decision Date | 4 November 2005 |
Relevant Documents |
Application Numbers | KBC - KET/2004/1336 |
---|---|
Location | Old Telford Way, Telford Way Industrial Estate, Kettering |
Proposal | Change of use of industrial/storage building and land to waste materials recycling facility |
Decision | Approved by Delegation |
Decision Date | 11 March 2005 |
Relevant Documents |
2004
Application Numbers | KBC - KET/2004/0976 |
---|---|
Location | Land at Duck End Farm, Cranford |
Proposal | Use of previously imported waste materials to extend the farm access |
Decision | Refused by Delegation |
Decision Date | 13 December 2004 |
Relevant Documents |
Application Numbers | KBC - KET/2004/0975 |
---|---|
Location | Land at Duck End Farm, Cranford |
Proposal | Use of previously imported waste materials to raise the levels of other land for agricultural improvement |
Decision | Approved by Delegation |
Decision Date | 13 December 2004 |
Relevant Documents |
Application Numbers | KBC - KET/2004/0808 |
---|---|
Location | Windmill Farm, Burton Latimer, Kettering |
Proposal | Infilling of old mineral railway cutting with inert waste materials for restoration to agriculture |
Decision | Approved by Delegation |
Decision Date | 29 October 2004 |
Relevant Documents |
Application Numbers | KBC - KET/2002/0547 |
---|---|
Location | Cranford Landfill Site, Thrapston Lane, Cranford St John |
Proposal | Revised restoration profile, placement of gas flare stack and modification of various conditions relating to planning permission KE/90/0396 and KE/92/0496 |
Decision | Approved by Delegation |
Decision Date | 22 June 2004 |
Relevant Documents |
Application Numbers | KBC - KET/2004/0079 |
---|---|
Location | Rushton Landfill Site, Oakley Road, Rushton |
Proposal | Variation of condition 2 of planning permission KE/94/0326 and condition 3b and 12 of planning permission KE/89/0714 to reconfigure the operations at the site, alter the phasing and provide a different restoration profile |
Decision | Approved by Delegation |
Decision Date | 21 April 2004 |
Relevant Documents |
Application Numbers | KBC - KET/2004/0078 |
---|---|
Location | Rushton Landfill Site, Oakley Road, Rushton |
Proposal | Use of current storage mound as permanent engineering bund for completion of the site covered under planning permission KE/94/0326 and KE/89/0714 |
Decision | Approved by Delegation |
Decision Date | 21 April 2004 |
Relevant Documents |
2023
Application number |
NN/23/00014/MINVOC |
---|---|
Location |
Earls Barton Quarry, Grendon Road, Earls Barton, NN6 0PE |
Proposal | Proposed variation of conditions 4 & 57 of planning permission WP/2007/0039 & SN/2006/1670 dated 16 December 2009 to extend the time limits for extraction of sand and gravel with progressive restoration to wet woodland and agriculture utilising imported inert materials; and to extend the time limit for the operation of the plant site |
Decision | Approved by delegation |
Decision date |
29 August 2023 |
Approved documents |
The original decision notice is available on request by emailing us at [email protected]. Submitted documentsSupporting informationPlans |
2022
Application number |
20/00017/WASFUL |
---|---|
Location | Doddington Road (Also known as Hardwater Road), Wollaston |
Proposal | Proposed Industrial/Commercial Building (Use Class B1, B2, B8 including non-hazardous waste transfer, storage, and recycling) and storage yard |
Decision | Refused by Delegation |
Decision date | 15 November 2022 |
Relevant documents |
Supporting Information
Plans |
Application number |
NN/22/00001/MINVOC |
---|---|
Location | Earls Barton Spinney Quarry, Grendon Road, Earls Barton, NN6 0RB |
Proposal | Variation of condition 6 of planning permission 15/00091/MIN for an extension of time in order to complete extraction of permitted minerals |
Decision | Approved by Delegation |
Decision date | 13 June 2022 |
Relevant documents |
Supporting InformationPlans |
Application number |
NN/21/00048/WASVOC |
---|---|
Location | 1-4 Neilson Road, Wellingborough, NN8 4PE |
Proposal | Variation of condition 5 (hours of working) of planning permission 18/00029/WASCOU (Proposed change of use from B2 (General Industrial) to B2 and 'Sui Generis' uses to allow the recycling of double-glazed windows, including the construction of two ancillary buildings, increasing the height of part of an existing building, provision of a new storage silo (23m), provision of new hardstanding areas, and other site alterations) |
Decision | Approved by Delegation |
Decision date | 17 January 2022 |
Relevant documents |
Supporting Information |
2021
Application numbers |
NCC - 19/00012/WASFUL WBC - WP/19/00173/CRA |
---|---|
Location | Unit 3-7 Bevan Close, Finedon Industrial Estate, Wellingborough, NN8 4BL |
Proposal | Operate the recycling of inert material from local surrounding areas |
Decision | Approved by Delegation |
Decision date | 23 July 2021 |
Relevant documents |
Supporting InformationPlans
|
Application numbers |
NCC - 20/00035/WASVOC WBC - WP/20/00627/CRA |
---|---|
Location | Northampton Shooting Ground, Kettering Road, Sywell, Northamptonshire, NN6 9TE |
Proposal | Variation of Condition 13 (End Date) of planning permission 17/00013/WASVOC to extend the time limit for completion of operations for a further three years |
Decision | Approved by Delegation |
Decision date | 12 February 2021 |
Relevant documents |
Supporting Information
Plans |
2020
Application numbers |
NCC - 20/00039/WASFUL WBC - WP/20/00506/CRA |
---|---|
Location | 1-4 Neilson Road, Wellingborough, Northamptonshire, NN8 4PE |
Proposal | Erection of 8 new storage silos (30m) 4 new hopper silos (8m) and new material storage building |
Decision | Approved by Delegation |
Decision date | 03 November 2020 |
Relevant documents |
Supporting InformationPlans |
2019
Application numbers |
NCC - 19/00022/MINNMA WBC - WP/19/00220/CRA |
---|---|
Location | Earls Barton Quarry, Grendon Road, Earls Barton, Northampton, Northamptonshire |
Proposal | Non-Material Amendment to work the remaining permitted mineral in the following sequence - 1G then 1F with 1D being extracted contemporaneously during the summer months when weather conditions allow of planning consent: 15/00091/MINVOC |
Decision | Approved by Delegation |
Decision date | 15 June 2019 |
Relevant documents |
Supporting InformationPlans |
Application numbers |
NCC - 19/00018/WASLAE |
---|---|
Location | Sidegate Lane Landfill Site, Sidegate Lane, Finedon, Wellingborough, NN8 1RN |
Proposal | Certificate of existing lawful use for a waste transfer station |
Decision | Approved by Delegation |
Decision date | 14 May 2019 |
Relevant documents |
Supporting InformationPlans |
Application numbers |
NCC - 19/00013/WASLAE |
---|---|
Location | DCS House, Unit 12, Baron Avenue, Earls Barton, Northamptonshire, NN6 0JE |
Proposal | Proposed certificate of existing lawful development for B2 (general industrial) use for the processing of redundant refrigeration units |
Decision | Approved by Delegation |
Decision date | 03 May 2019 |
Relevant documents |
Supporting InformationPlans |
2018
Application numbers |
NCC - 18/00041/WASFUL |
---|---|
Location | Sidegate Lane Landfill Site, Sidegate Lane, Finedon, Wellingborough, Northamptonshire NN8 1RN |
Proposal | Erection of a single storey portacabin and removal of three trees |
Decision | Approved by Delegation |
Decision date | 17 December 2018 |
Relevant documents |
Supporting InformationPlans |
Application numbers |
NCC - 18/00005/MINFUL |
---|---|
Location | Neilson Rail Sidings, Meadow Close, Wellingborough, Northamptonshire NN8 4BH |
Proposal | Extension to existing site for provision of increased aggregate stocking capacity (retrospective), plus replacement car parking facilities. |
Decision | Approved by Delegation |
Decision date | 01 November 2018 |
Relevant documents |
Plans |
Application numbers |
NCC - 17/00053/MINFUL |
---|---|
Location | Land To The East Of Great Billing WRC, Northampton, Northamptonshire NN3 9BX |
Proposal | Extraction of sand and gravel, construction of concrete batching plant, processing plant, including ancillary weighbridge, office, workshop, recycling activities and access, plus importation of inert material and restoration to agriculture and nature conservation. |
Decision | Approved by Delegation |
Decision date | 13 July 2018 |
Relevant documents |
Supporting documents |
Application numbers |
NCC - 18/00021/MINNMA WBC - WP/18/00405/CRA |
---|---|
Location | Earls Barton Quarry, Grendon Road, Earls Barton, Northampton, Northamptonshire |
Proposal | Non-Material Amendment to planning consent ref.: SN/06/1670 for the retrospective alteration of approved site layout drawings |
Decision | Approved by Delegation |
Decision date | 27 June 2018 |
Relevant documents |
Supporting informationPlans |
Application numbers |
NCC - 18/00002/MINVOC WBC - WP/18/00175/CRA |
---|---|
Location | White Mills Marina, 344 Grendon Road, Earls Barton, Northampton, Northamptonshire |
Proposal | Variation of Conditions 2 (Scope of Permission), 18 (Landscape and Habitat Management), 20 (Habitat Management Plan), 23 (Materials) and 24 (Lighting) of planning consent ref. 16/00064/MINVOC to amend the approved plans to reflect the marina site layout as constructed |
Decision | Approved by Delegation |
Decision date | 07 May 2018 |
Relevant documents |
Supporting information
Plans |
Application numbers |
NCC - 18/00008/MINNMA WBC - WP/18/00091/CRA |
---|---|
Location | Earls Barton Spinney Quarry, Grendon Road, Earls Barton, Northampton, Northamptonshire |
Proposal | Non-Material Amendment to Conditions 2 (Commencement of Development) and 7 (Protection of Hedgerows) of planning consent ref. 15/00091/MINVOC to alter the approved scheme for tree and hedgerow protection |
Decision | Approved by delegation |
Decision date | 20 February 2018 |
Relevant documents |
Supporting information
Plans |
2017
Application Numbers |
NCC - 17/000045/WASLAP |
---|---|
Location | 1 Bradfield Road, Wellingborough, Northamptonshire, NN8 4HB |
Proposal | Certificate of proposed lawful use for the storage and transfer of asbestos waste |
Decision | Approved by delegation |
Decision Date | 10 November 2017 |
Relevant Documents |
Supporting Information
Plans |
Application Numbers |
NCC - 17/000036/MINNMA |
---|---|
Location | Earls Barton Quarry, Grendon Road, Earls Barton, Northampton, Northamptonshire |
Proposal | Non-material amendment to planning consent ref. SN/06/1670 and WP/07/0039 to retain the diverted Whiston Brook as a permanent feature |
Decision | Approved by delegation |
Decision Date | 14 August 2017 |
Relevant Documents |
PlansSupporting Information |
Application Numbers |
NCC - 17/000024/MINVOC |
---|---|
Location | Bozeat Quarry, London Road, Bozeat, Wellingborough, Northamptonshire |
Proposal | Variation of Condition 13.1 (Restoration and Aftercare Scheme) of planning permission ref. no. APP/K2800/97/287275 (NCC ref. no. WP/96/340C) for the amendment of the habitat layout, and the retention of the site access and access road |
Decision | Approved by Delegation |
Decision Date | 30 June 2017 |
Relevant Documents |
Plans:Supporting Information: |
Application Numbers |
NCC - 17/000014/WASVOC |
---|---|
Location | Northampton Shooting Ground, Sywell Range, Sywell, Northampton, NN6 9TE |
Proposal | Variation of Condition 18 (End Date) of planning permission 13/00103/WAS to extend the time limit for the completion of works for a further 3 years until 30th April 2020 |
Decision | Approved by Delegation |
Decision Date | 09 June 2017 |
Relevant Documents |
Plans:
Supporting Information: |
Application Numbers |
NCC - 17/000013/WASVOC |
---|---|
Location | Northampton Shooting Ground, Sywell Range, Sywell, Northampton, NN6 9TE |
Proposal | Variation of Condition 13 (End Date) of planning permission 13/00102/WAS to extend the time limit for completion of operations for a further 3 years until 30th April 2020 |
Decision | Approved by Delegation |
Decision Date | 09 June 2017 |
Relevant Documents |
Plans:
Supporting Information: |
Application Numbers |
NCC - 17/000015/MINNMA |
---|---|
Location | Earls Barton Spinney Quarry, Grendon Road, Earls Barton, Northampton, Northamptonshire |
Proposal | Non-Material Amendment to conditions 3 and 9 of planning permission ref. no. 15/00091/MINVOC to allow internal construction works to the site access, site compound and plant site area prior to completion of the external highway access |
Decision | Approved by Delegation |
Decision Date | 05 May 2017 |
Relevant Documents |
Application Numbers |
NCC - 17/000022/MINNMA |
---|---|
Location | Earls Barton Spinney Quarry, Grendon Road, Earls Barton, Northampton, Northamptonshire |
Proposal | Non-Material Amendment to planning permission 15/00091/MINVOC for the amendment of the wording of Condition 9 |
Decision | Approved by Delegation |
Decision Date | 02 May 2017 |
Relevant Documents |
Application Numbers |
NCC - 17/000018/MINNMA |
---|---|
Location | Earls Barton Quarry, Grendon Road, Earls Barton, Northampton, Northamptonshire |
Proposal | Non-material amendment to planning permissions SN/06/1670 and WP/07/0039 for the construction of two (2) temporary settlement lagoons within Phase 1a of the extraction area |
Decision | Approved by Delegation |
Decision Date | 02 May 2017 |
Relevant Documents |
Application Numbers |
NCC - 17/00008/WASVOC |
---|---|
Location | Sidegate Lane Landfill Site, Sidegate Lane, Finedon, Wellingborough, Northamptonshire |
Proposal | Variation of Conditions 13, 17, 20, 21 and 22 of planning permission WP/04/806C to update the restoration and landscaping scheme, the introduction of an aftercare scheme and to extend the end date to 31st July 2019 |
Decision | Approved by Delegation |
Decision Date | 24 April 2017 |
Relevant Documents |
Application Numbers |
NCC - 16/00064/MINVOC |
---|---|
Location | Whitemills Marina, 344 Grendon Road, Earls Barton, Northamptonshire, NN6 0RB |
Proposal | Variation of Condition 2 of planning permission 14/00001/MINFUL to alter the approved site layout to allow the relocation of the proposed facilities building, site access and car park, and retention of existing temporary buildings and security fencing |
Decision | Approved by Delegation |
Decision Date | 7 April 2017 |
Relevant Documents |
2016
Application Numbers |
NCC - 16/00056/WASNMA |
---|---|
Location | 3-4 Bevan Close, Wellingborough, Northamptonshire, NN8 4BL |
Proposal | Non-Material Amendment of planning permission 13/00014/WASVOC to increase existing chimney height |
Decision | Approved by Delegation |
Decision Date | 15 December 2016 |
Relevant Documents |
Application Numbers |
NCC - 16/00048/MINNMA |
---|---|
Location | Earls Barton Quarry, Grendon Road, Earls Barton, Northampton, Northamptonshire |
Proposal | Non-Material Amendment to planning permission APP/K2800/A/97/287275 for time extension of operations to 31/01/2017 |
Decision | Approved by Delegation |
Decision Date | 15 November 2016 |
Relevant Documents |
Application Numbers |
NCC - 16/00047/MINNMA |
---|---|
Location | Bozeat Quarry, London Road, Bozeat, Wellingborough, Northamptonshire |
Proposal | Non-Material Amendment to planning permission APP/K2800/A/97/287275 for time extension of extraction to 31/01/2017 |
Decision | Approved by Delegation |
Decision Date | 15 November 2016 |
Relevant Documents |
Application Numbers |
NCC - 16/00031/WASFUL |
---|---|
Location | 30 Sanders Park, Sanders Road, Wellingborough, Northamptonshire, NN8 4FR |
Proposal | Waste Transfer Station to bulk up dry recyclable waste, including a new building |
Decision | Approved by Delegation |
Decision Date | 14 October 2016 |
Relevant Documents |
Application Numbers |
NCC - 16/00021/MINNMA |
---|---|
Location | Bozeat Quarry, London Road, Bozeat, Wellingborough |
Proposal | Non-material amendment to planning permission APP/K2800/A/97/287275 for time extension of extraction to 30/11/2016 |
Decision | Approved by Delegation |
Decision Date | 27 May 2016 |
Relevant Documents |
Application Numbers |
NCC - 15/00091/MINVOC |
---|---|
Location | Earls Barton Spinney, Grendon Road, Earls Barton, Northampton |
Proposal | Variation of conditions 2, 16, 17 and 43 of planning permission 10/00066/MINEXT to amend working scheme |
Decision | Approved by Delegation |
Decision Date | 24 February 2016 |
Relevant Documents |
Application Numbers |
NCC - 15/00043/WASFUL |
---|---|
Location | 3-4 Bevan Close, Wellingborough, NN8 4BL |
Proposal | Erection of two industrial buildings, open storage bins and bays and an ancillary building and WCs, for processing of waste wood |
Decision | Approved by Delegation |
Decision Date | 18 January 2016 |
Relevant Documents |
Application Numbers |
NCC - 15/00088/MINVOC |
---|---|
Location | Earls Barton Quarry, Grendon Road, Earls Barton, Northamptonshire |
Proposal | Variation of condition 5 of planning permission WP/05/767C to continue the importation of aggregates until 27 August 2027 |
Decision | Approved by Delegation |
Decision Date | 18 January 2016 |
Relevant Documents |
Application Numbers |
NCC - 15/00084/MINNMA |
---|---|
Location | Land Opposite Sports Ground, Grendon Road, Earls Barton, Northamptonshire |
Proposal | Non-material amendment to planning permission 14/00001/MINFUL to reduce the footprint of the facilities building |
Decision | Approved |
Decision Date | 11 January 2016 |
Relevant Documents |
2015
Application Numbers |
NCC - 15/00045/MINFUL |
---|---|
Location | Neilson's Railway Sidings, Meadow Close, Ise Valley Industrial Estate, Wellingborough, NN8 4BH |
Proposal | Rail served concrete block making facility with associated infrastructure and ancillary uses |
Decision | Approved by Delegation |
Decision Date | 23 September 2015 |
Relevant Documents |
|
Application Numbers |
NCC - 15/00062/WASNMA |
---|---|
Location | Mick George Ltd., Waste Transfer Station, Lower Ecton Lane, Northampton, Northamptonshire, NN3 5HQ |
Proposal | Non Material Amendment to Planning Permission 14/00096/WASFUL for amended site layout |
Decision | Approved by Delegation |
Decision Date | 07 August 2015 |
Relevant Documents |
Application Numbers |
NCC - 15/00049/WASNMA |
---|---|
Location | Mick George Ltd., Waste Transfer Station, Lower Ecton Lane, Northampton, Northamptonshire, NN3 5HQ |
Proposal | Non Material Amendment to Planning Permission 13/00097/WASVOC to extend the end date to import and process municipal solid waste by a further nine months |
Decision | Approved by Delegation |
Decision Date | 07 August 2015 |
Relevant Documents |
Application Numbers |
NCC - 14/00096/WASFUL |
---|---|
Location | Land at Lower Ecton Lane, Northampton, Northamptonshire, NN3 5HQ |
Proposal | Waste Transfer Station, ready mix concrete plant and overnight parking of 15 HGVs |
Decision | Approved by Delegation |
Decision Date | 01 July 2015 |
Relevant Documents |
Application documents |
Application Numbers |
NCC - 15/00020/WASNMA |
---|---|
Location | 3-4 Bevan Close, Wellingborough, Northamptonshire, NN8 4BL |
Proposal | Non-Material Amendment to Planning Permission 13/00014/WASVOC for building adjustments, changes to internal arrangements and amended wording of Conditions 13 and 24 |
Decision | Approved by Delegation |
Decision Date | 28 April 2015 |
Relevant Documents |
Application Numbers |
NCC - 15/00009/MINNMA |
---|---|
Location | Earls Barton Quarry, Grendon Road, Earls Barton, Wellingborough, Northamptonshire |
Proposal | Non-Material Amendment to Planning Permission SN/2006/1670 for a new drainage channel |
Decision | Approved by Delegation |
Decision Date | 10 March 2015 |
Relevant Documents |
Application Numbers |
NCC - 15/00007/MINNMA |
---|---|
Location | Earls Barton Quarry, Grendon Road, Earls Barton, Wellingborough, Northamptonshire |
Proposal | Retention of car parking area |
Decision | Approved by Delegation |
Decision Date | 10 March 2015 |
Relevant Documents |
2014
Application Numbers |
NCC - 14/00001/MINFUL |
---|---|
Location | Land opposite Sports Ground, Grendon Road, Earls Barton, Wellingborough, Northamptonshire |
Proposal | Extraction of minerals together with new inland waterways marina, access road, parking, facilities building and improved landscaping scheme |
Decision | Approved by Delegation |
Decision Date | 11 September 2014 |
Relevant Documents |
|
Application Numbers |
NCC - 14/00032/WASFUL |
---|---|
Location | 30 Sanders Park, Sanders Road, Wellingborough, Northamptonshire, NN8 4FR |
Proposal | Waste Transfer Station to process dry recyclable waste including a new building |
Decision | Approved by Delegation |
Decision Date | 07 August 2014 |
Relevant Documents |
Application Numbers |
NCC - 13/00111/WASVOC |
---|---|
Location | Northampton Shooting Ground, Sywell, Northampton, NN6 9TE |
Proposal | Variation of condition 12 of planning permission 10/00043/WAS to extend the end date until 7 January 2015. |
Decision | Approved by Delegation |
Decision Date | 12 May 2014 |
Relevant Documents |
Application Numbers |
NCC - 14/00003/WASFUL |
---|---|
Location | Northampton Shooting Ground, Sywell, Northampton, NN6 9TE |
Proposal | Construction of a new safety mound using inert material to protect permitted go kart track from the adjacent shooting ground. |
Decision | Approved by Delegation |
Decision Date | 09 May 2014 |
Relevant Documents |
Application Numbers |
NCC - 13/00103/WASVOC |
---|---|
Location | Northampton Shooting Ground, Sywell, Northampton, NN6 9TE |
Proposal | Variation of condition 19 of planning permission 10/00005/WAS to extend the time limit for completion for a further 3 years until 30 April 2017 |
Decision | Approved by Delegation |
Decision Date | 28 February 2014 |
Relevant Documents |
Application Numbers |
NCC - 13/00102/WASVOC |
---|---|
Location | Northampton Shooting Ground, Kettering Road, Sywell, NN6 9TD |
Proposal |
Variation of condition 13 of planning permission 10/00074/WAS to extend the time limit for completion for a further 3 years until 30 April 2017 |
Decision | Approved by Delegation |
Decision Date | 18 February 2014 |
Relevant Documents |
Application Numbers |
NCC - 13/00110/MINNMA |
---|---|
Location | Earls Barton Quarry, Grendon Road, Earls Barton, Wellingborough |
Proposal |
Non Material Amendment to planning permission 10/00066/EXT to amend working programme |
Decision | Approved by Delegation |
Decision Date | 15 January 2014 |
Relevant Documents |
2013
Application Numbers |
NCC - 13/00107/WASNMA |
---|---|
Location | Sidegate lane Landfill Site, Sidegate Lane, Finedon, Wellingborough |
Proposal |
Non Material Amendment to planning permission 13/00070/WASFUL to amend the name of the applicant from ESG to Energy Development (UK) Ltd |
Decision | Approved by Delegation |
Decision Date | 29 November 2013 |
Relevant Documents |
Application Numbers |
NCC - 13/00081/WASNMA |
---|---|
Location | Sidegate lane Landfill Site, Sidegate Lane, Finedon, Wellingborough |
Proposal |
Non Material Amendment to planning permission 12/00056/WASFUL for phased implementation |
Decision | Approved by Delegation |
Decision Date | 23 October 2013 |
Relevant Documents |
Application Numbers |
NCC - 13/00070/WASFUL |
---|---|
Location | Sidegate lane Landfill Site, Sidegate Lane, Finedon, Wellingborough |
Proposal |
Installation of two additional engines to the existing power generation plant and installation of a portacabin at the southeastern end of the compound |
Decision | Approved by Delegation |
Decision Date | 11 October 2013 |
Relevant Documents |
Application Numbers |
NCC - 13/00058/WASFUL |
---|---|
Location | Sidegate lane Landfill Site, Sidegate Lane, Finedon, Wellingborough |
Proposal |
Retrospective planning permission for the installation of a temporary landfill gas flare and ancillary equipment |
Decision | Approved by Delegation |
Decision Date | 26 September 2013 |
Relevant Documents |
Application Numbers |
NCC - 13/00014/WASVOC |
---|---|
Location | Larner Pallets, Bevan Close, Wellingborough, NN8 4BL |
Proposal |
Variations to the approved plans (condition 2) and hours of working (condition 12) permitted under planning permission 11/00088/WAS for the erection of a new industrial building, plant and machinery and installation of a biomass fuelled power plant at Larner Pallets, Bevan Close, Finedon Road Industrial Estate, Wellingborough, NN8 4BL |
Decision | Approved by Delegation |
Decision Date | 23 May 2013 |
Relevant Documents |
2012
Application Numbers |
NCC - 12/00056/WASFUL |
---|---|
Location | Sidegate Lane, Finedon, Wellingborough |
Proposal | Resource Recovery Facility, to include Refuse Derived Fuel Facility, Road Sweeping Recycling and Soil Blending, for the treatment of 125,000 tonnes of municipal, commercial and industrial waste, road sweepings and soil making material |
Decision | Approved by Delegation |
Decision Date | 18 January 2013 |
Relevant Documents |
Application Numbers | NCC - 12/00040/MINNMA WBC - WP/2012/0270 |
---|---|
Location | Land West of Earls Barton Quarry, Grendon Road, Northamptonshire, NN6 0PE |
Proposal | Non-material amendment to planning permissions SN/2006/1670 ·& WP/2007/0039 to transport up to 1000 tonnes of sand and gravel by road using lorries over a period of 1-3 days |
Decision | Approved by Delegation |
Decision Date | 13 July 2012 |
Relevant Documents |
Application Numbers | NCC - 11/00088/WAS WBC - WP/2012/0008 |
---|---|
Location | Larner Pallets, Bevan Close, Finedon Road Industrial Estate, Wellingborough, NN8 4BL |
Proposal | Erection of a new industrial building, plant and machinery and installation of a biomass fuelled power plant |
Decision | Approved by Delegation |
Decision Date | 21 March 2012 |
Relevant Documents |
2011
Application Numbers | NCC - 11/00064/EXT WBC - WP/2011/0440 |
---|---|
Location | Larner Pallets, Bevan Close, Finedon Road Industrial Estate, Wellingborough, NN8 4BL |
Proposal | Replacement of extant planning permission 08/00049/WAS to extend the time limit for implementation |
Decision | Approved by Delegation |
Decision Date | 20 December 2011 |
Relevant Documents |
Application Numbers | NCC - 11/00019/WAS WBC - WP/2011/0143 |
---|---|
Location | Unit 1, Midland Works Business Centre, Mill Road, Wellingborough, NN8 1QW |
Proposal | Variation of planning permission 09/00032/WAS to include recycling of end of life vehicles |
Decision | Approved by Delegation |
Decision Date | 13 June 2011 |
Relevant Documents |
Application Numbers | NCC - 11/00018/WAS WBC - WP/2011/0121 |
---|---|
Location | The Recycling Centre, 301 Grendon Road, Earls Barton, Northampton, NN6 0RB |
Proposal | Variation of condition 2 of planning permission 10/00001/WAS to permit the erection of a staircase and viewing platform and the installation of a safety line on the roof of an existing materials recycling facility building |
Decision | Approved by Delegation |
Decision Date | 9 May 2011 |
Relevant Documents |
Application Numbers | NCC - 10/00066/EXT WBC - WP/2010/0443 |
---|---|
Location | Earls Barton Spinney Quarry, Off Grendon Road, Earls Barton, Northamptonshire |
Proposal | Replacement of extant planning permission 07/00050/MIN to extend the time limit for implementation |
Decision | Approved by DC Committee |
Decision Date | 28 January 2011 |
Relevant Documents |
Application Numbers | NCC - 10/00074/WAS WBC - WP/2010/0481 |
---|---|
Location | Northampton Shooting Ground, Sywell, Northampton, NN6 9TE |
Proposal | The operation of a recycled inert waste export facility for a temporary period expiring 30 April 2014 |
Decision | Approved by Delegation |
Decision Date | 26 January 2011 |
Relevant Documents |
2010
Application Numbers | NCC - 10/00075/NMA WBC - WP/2010/0482 |
---|---|
Location | 15-21 Links Road, Finedon Road Industrial Estate, Wellingborough, NN8 4EY |
Proposal | Non-material amendment to planning permission 10/00016/WAS to allow the storage and treatment of waste vegetable oil at an existing waste transfer station |
Decision | Approved |
Decision Date | 30 November 2010 |
Relevant Documents |
Application Numbers | NCC - 10/00043/WAS WBC - WP/2010/0252 |
---|---|
Location | Sywell Aerodrome, Belman Gate, Holcot Lane, Sywell, NN6 0BN |
Proposal | Variation of condition 13 of planning permission 07/00002/WAS to extend the end date by two years |
Decision | Approved by DC Committee |
Decision Date | 8 September 2010 |
Relevant Documents |
Application Numbers | NCC - 10/00016/WAS WBC - WP/2010/0104 |
---|---|
Location | 15-21 Links Road, Finedon Road Industrial Estate, Wellingborough, NN8 4EY |
Proposal | Change of use to Waste Transfer Station |
Decision | Approved by Delegation |
Decision Date | 25 May 2010 |
Relevant Documents |
Application Numbers | NCC - 10/00005/WAS WBC - WP/2010/0020 |
---|---|
Location | Sywell Shooting School, A43 Kettering Road, Sywell, NN6 9TE |
Proposal | Creation of undulating area on existing shooting ground through the importation of inert material |
Decision | Approved by Delegation |
Decision Date | 21 April 2010 |
Relevant Documents |
Application Numbers | NCC - 10/00001/WAS WBC - WP/2010/0010 |
---|---|
Location | The Recycling Centre, 301 Grendon Road, Earls Barton, Northampton, NN6 0RB |
Proposal | Variation of condition 3 of planning permission 07/00027/WAS to increase operating hours |
Decision | Approved by Delegation |
Decision Date | 31 March 2010 |
Relevant Documents |
Application Numbers | NCC - 09/00078/WAS WBC - WP/2009/0507 |
---|---|
Location | Sidegate Lane Landfill Site, Sidegate Lane, Wellingborough, NN8 1RN |
Proposal | Variation of condition 8 of planning permission WP/95/238C to extend the life of the power generation plant until 30/06/2031 |
Decision | Approved by Delegation |
Decision Date | 18 March 2010 |
Relevant Documents |
2009
Application Numbers | WBC - WP/2007/0039 SNC - S/2006/1670 |
---|---|
Location | Land west of Earls Barton Quarry, Grendon Road, Northamptonshire, NN6 0PE |
Proposal | Winning and working of sand and gravel with progressive restoration to wet woodland and agriculture utilising imported inert materials |
Decision | Approved by DC Committee |
Decision Date | 16 December 2009 |
Relevant Documents |
|
Application Numbers | NCC - 09/00068/WAS WBC - WP/2009/0397 |
---|---|
Location | The Recycling Centre, 301 Grendon Road, Earls Barton, Northampton, NN6 0RB |
Proposal | Variation of condition 2 of planning permission 09/00007/WAS for temporary permission to handle waste outside |
Decision | Approved by Delegation |
Decision Date | 16 December 2009 |
Relevant Documents |
Application Numbers | NCC - 09/00057/WAS WBC - WP/2009/0365 |
---|---|
Location | Larner Pallets, Bevan Close, Finedon Road Industrial Estate, Wellingborough, NN8 4BL |
Proposal | Erection of new industrial building and installation of 3MW biomass fuelled power plant |
Decision | Approved by DC Committee |
Decision Date | 14 December 2009 |
Relevant Documents |
Application Numbers | NCC - 09/00032/WAS WBC - WP/2009/0161 |
---|---|
Location | Shed 1, Mill Road Works, Wellingborough |
Proposal | Change to use to a facility to manage the storage and treatment and recycling of waste electrical products, cardboard, metals and plastics and storage of batteries, with no change to the building |
Decision | Approved by Delegation |
Decision Date | 3 August 2009 |
Relevant Documents |
Application Numbers | NCC - 09/00007/WAS WBC - WP/2009/0047 |
---|---|
Location | The Recycling Centre, Grendon Road, Earls Barton, Northampton, NN6 0RB |
Proposal | Extension to MRF building and increase in annual waste imports |
Decision | Approved by Delegation |
Decision Date | 20 April 2009 |
Relevant Documents |
Application Numbers | NCC - 09/00009/MIN WBC - WP/2009/0047 |
---|---|
Location | Neilson's Sidings, Ise Valley Industrial Estate, Wellingborough |
Proposal | Aggregates rail depot |
Decision | Approved by Delegation |
Decision Date | 7 April 2009 |
Relevant Documents |
Application Numbers | NCC - 08/00073/MIN WBC - WP/2008/0546 |
---|---|
Location | Neilson's Sidings, Ise Valley Industrial Estate, Wellingborough |
Proposal | Aggregates rail depot |
Decision | Refused by Delegation |
Decision Date | 30 January 2009 |
Relevant Documents |
2008
Application Numbers | NCC - 08/00083/WAS |
---|---|
Location | The Recycling Centre, Grendon Road, Earls Barton, Northampton, NN6 0RB |
Proposal | Extension to materials recycling facility building and increase in annual waste imports |
Decision | Withdrawn on 18 December 2008 |
Application Numbers | NCC - 08/00072/WAS WBC - WP/2008/0453 |
---|---|
Location | 11-13 Yeldon Court, Finedon Road Industrial Estate, Wellingborough, NN8 4SS |
Proposal | Change of use to a facility to manage the sorting, treatment and recycling of Waste Electrical Equipment |
Decision | Approved by Delegation |
Decision Date | 28 November 2008 |
Relevant Documents |
Application Numbers | NCC - 08/00061/WAS WBC - WP/2008/0405 |
---|---|
Location | Earls Barton Quarry, Station Road, Earls Barton, Northampton, NN6 0PE |
Proposal | Variation of condition 12 of planning permission WP/06/359C to extend the date by which the development should be completed by 12 months, to 15 August 2009 |
Decision | Approved by Delegation |
Decision Date | 22 September 2008 |
Relevant Documents |
Application Numbers | NCC - 08/00049/WAS WBC - WP/2008/0320 |
---|---|
Location | Larner Pallets, Bevan Close, Finedon Road Industrial Estate, Wellingborough, NN8 4BL |
Proposal | Erection of a new industrial building and installation of a 3MW gasification plant to generate electricity from reclaimed timber |
Decision | Approved by Delegation |
Decision Date | 15 September 2008 |
Relevant Documents |
Application Numbers | NCC - 08/00027/WAS WBC - WP/2008/0180 |
---|---|
Location | Grendon Road, Earls Barton, Northampton, NN6 0RB |
Proposal | Improvement to access track to Materials Recycling Facility and Waste Transfer Station |
Decision | Approved by Delegation |
Decision Date | 20 June 2008 |
Relevant Documents |
Application Numbers | NCC - 08/00025/WAS WBC - WP/2008/0276 |
---|---|
Location | Unit 1, 50 Bradfield Road, Wellingborough, NN8 4HB |
Proposal | Change of use to a recycling and reprocessing unit |
Decision | Approved by Delegation |
Decision Date | 10 June 2008 |
Relevant Documents |
Application Numbers | NCC - 07/00050/MIN WBC - WP/2007/0625 |
---|---|
Location | Earls Barton Spinney Quarry (West of Grendon Road, south of the A45) |
Proposal | Sand and gravel quarry with restoration of floodplain habitats and agriculture |
Decision | Approved by Delegation |
Decision Date | 20 March 2008 |
Relevant Documents |
Application Numbers | NCC - 07/00076/WAS WBC - WP/2007/0001 |
---|---|
Location | Sidegate Lane Landfill Site, Sidegate Lane, Wellingborough |
Proposal | Replacement of existing portakabins with new portakabin and relocation of lorry parking area |
Decision | Approved by Delegation |
Decision Date | 18 February 2008 |
Relevant Documents |
2007
Application Numbers | NCC - 07/00027/WAS WBC - WP/2007/0443 |
---|---|
Location | Recycling Centre, Grendon Road, Earls Barton, Northampton, NN6 0RB |
Proposal | Materials recycling facility and waste transfer station |
Decision | Approved by Delegation |
Decision Date | 4 October 2007 |
Relevant Documents |
Application Numbers | NCC - 07/00025/WAS WBC - WP/2007/0401 |
---|---|
Location | Unit 19B, The Leyland Trading Estate, Irthlingborough Road, Wellingborough, NN8 1RT |
Proposal | Change of use from warehouse (B8) to waste management and mechanical recycling |
Decision | Approved by Delegation |
Decision Date | 10 August 2007 |
Relevant Documents |
Application Numbers | NCC - 07/00002/WAS WBC - WP/2007/0252 |
---|---|
Location | Sywell Aerodrome, Belman Gate, Holcot Lane, Sywell |
Proposal | Land levelling by importation of waste soils |
Decision | Approved by Delegation |
Decision Date | 2 July 2007 |
Relevant Documents |
Application Numbers | WBC - WP/07/0008 |
---|---|
Location | Sidegate Lane Landfill Site, Sidegate Lane, Wellingborough |
Proposal | Variation of condition 8 of planning permission WP/01/481C to allow the extraction of clay and overlying minerals to subsequent reinstatement to cease no later than 31 July 2017 |
Decision | Approved by Delegation |
Decision Date | 22 February 2007 |
Relevant Documents |
2006
Application Numbers | WBC - WP/2006/0359 |
---|---|
Location | Land at Earls Barton Quarry, Grendon Road, Earls Barton |
Proposal | Importation and deposition of inert waste materials with restoration to improved wetland |
Decision | Approved by Delegation |
Decision Date | 5 September 2006 |
Relevant Documents |
Application Numbers | WBC - WP/2006/0218 |
---|---|
Location | Irchester Landfill Site, Wollaston Road, Irchester |
Proposal | Installation of a landfill gas collection system and monitoring boreholes |
Decision | Approved by Delegation |
Decision Date | 26 June 2006 |
Relevant Documents |
2005
Application Numbers | WBC - WP/2005/0767 |
---|---|
Location | Earls Barton Quarry, Grendon Road, Earls Barton |
Proposal | Proposed importation, stockpiling and distribution of aggregate |
Decision | Approved by Delegation |
Decision Date | 20 December 2005 |
Relevant Documents |
Application Numbers | WBC - WP/2005/0599 |
---|---|
Location | Land to the south-western end of Sywell Aerodrome |
Proposal | Land levelling to existing runway and safety areas |
Decision | Approved by Delegation |
Decision Date | 25 November 2005 |
Relevant Documents |
Application Numbers | WBC - WP/2005/0432 |
---|---|
Location | Appleby Lodge Farm, Sywell Road, Wellingborough |
Proposal | Change of use from agricultural building and yard to building for the sorting of waste and parking of skip lorries and skip bins |
Decision | Approved by Delegation |
Decision Date | 15 September 2005 |
Relevant Documents |
Application Numbers | WBC - WP/2005/0001 |
---|---|
Location | Land at Wellingborough/Irchester |
Proposal | Transportation and deposition of surplus soil from Victoria Business Park |
Decision | Approved by Delegation |
Decision Date | 23 May 2005 |
Relevant Documents |
Application Numbers | WBC - WP/2005/0179 |
---|---|
Location | Unit 21 & 23B, The Leyland Trading Estate, Irthlingborough Road, Wellingborough |
Proposal | Extension of existing processing operations from Unit 21 into Unit 23B |
Decision | Approved by Delegation |
Decision Date | 23 May 2005 |
Relevant Documents |
2004
Application Numbers | WBC - WP/1999/0272 |
---|---|
Location | Sidegate Lane Landfill Site, Sidegate Lane, Wellingborough |
Proposal | Chance in final levels for planning permissions BW/92/0246 & WP/94/0028, change in area of BW/92/0246 and change in end date to 31/12/2002 |
Decision | Approved by Delegation |
Decision Date | 22 September 2004 |
Relevant Documents |
Application Numbers | WBC - WP/2004/0165 |
---|---|
Location | Sywell Aerodrome, Wellingborough Road, Sywell, Northampton |
Proposal | Land levelling and reduced gradients |
Decision | Approved by Delegation |
Decision Date | 1 June 2004 |
Relevant Documents |
Last updated 16 October 2023