Key work and factsheets
Location | Activity | Planned dates |
---|---|---|
Station Road, Irthlingborough | Traffic management, long-term, road closed | For the foreseeable future |
Kettering Road, Geddington | Anti-skid work | To be confirmed |
You can keep up-to-date via our NNCHighways Facebook and NNCHighways Twitter channels.
Other work and factsheets
Key information about major works.
When
Monday 31 March to Sunday 4 May 2025
Traffic management
Road closures will be in place along with an approved diversion route for each phase of works.
The diversion is shown in blue and the closure is shown in red on the maps below.
Emergency vehicles
We aim to maintain access for emergency vehicles when safe to do so.
Buses
Bus stops along Warkton Lane will be suspended during the works as no through route being available. Please contact your local bus provider for further information.
Residents and businesses
Footways will always be open for pedestrian access during the works.
The works are planned to be undertaken between the side road junctions (Constable Drive, Hogarth Drive, Poplars Farm Road and Stubbs Lane) to allow access to residents. Access will be controlled by our site team.
To help us complete the work as quickly and efficiently as possible, we kindly ask that if you need to use your car, driveways and parked cars on Warkton Lane must be vacated from the works area by 07:45am each morning.
Where properties fall inside the works area, there will be no vehicle access available until the phase of works are completed and we have created safe passage. We understand the importance of access to your driveway and will do our best to ensure it's available during the evening during the resurfacing phase.
When safe to do so, we will aim to reduce overnight and weekend road closures. We will complete these works as efficiently as possible to keep disruption to a minimum.
Phase 1 (Resurfacing)
Monday 31 March 2025 to Friday 4 April 2025 - these works have been completed
Phase 2 (Full depth road excavation)
Monday 7 April to Monday 28 April 2025 - these works have been completed
All driveways and access points will be accessible from Thursday 17 April at around 5pm until Monday 28 April at 09:30am when Phase 3 will start,
Phase 3 (Resurfacing)
Monday 28 April 2025 to Sunday 4 May 2025. With night works taking place on 2 and 3 May outside Ise Garden Centre.
Between Poplars Farm Road and Ise Garden Centre, access will remain to the side road junctions and will be controlled by our site team.
We understand the importance of access to your driveway and will do our best to ensure it's available during the evening during the resurfacing phase.
To help us complete the work as quickly and efficiently as possible, we kindly ask that if you need to use your car, driveways and parked cars on Warkton Lane must be vacated from the works area by 7:45am each morning.
- Blue shows the diversion
- Red shows the closure
- Yellow highlights the section from Poplars Farm Road to Stubbs Lane
- Green highlights the section from Stubbs Lane to Ise Garden Centre
- Purple highlights the night works on 2 and 3 May

Last updated 15 April 2025