LEVI Project works start and go live dates
The build programme for the LEVI project with Connected Kerb is underway. This is installing public EV chargers both on-street and in the council’s car parks over the next three to five years. The expected start dates for civils works on site to install new EV chargepoints are shown below. The dates when the EV chargepoints are expected to be connected to the grid and ready for service are also shown. Dates may be subject to change.
View the full list of approved EV chargepoint sites.
An interactive map showing approved sites, as well as planned sites where the council is inviting feedback on proposals, can be viewed on Connected Kerb.
| Expected build works start date | Location | Street name | Expected EV chargepoint availability date |
|---|---|---|---|
| 31 August to 14 September | Aldwincle | Opposite 55 Main Street | October to December 2026 |
| 1 September to 16 September | Corby | Willow Brook Road (North) | October to December 2026 |
| 1 September to 16 September | Corby | Willow Brook Road (South) | October to December 2026 |
| 4 September to 17 September | Corby | Kingsthorpe Avenue | October to December 2026 |
| 8 September to 21 September | Corby | Glastonbury Road | October to December 2026 |
| 10 September to 23 September | Corby | Lyveden Way | October to December 2026 |
| 27 August to 14 September | Corby | Shakespeare Way | October to December 2026 |
| 9 September to 22 September | Corby | Newark Drive | October to December 2026 |
| 11 September to 24 September | Corby | Headway | October to December 2026 |
| 30 June to 2 July | Kettering | Whiteford Drive | July to September 2026 |
| 26 to 30 June | Kettering | Dahlia Road | July to September 2026 |
| 25 to 29 June | Kettering | Ivy Road | July to September 2026 |
| 24 to 26 June | Kettering | Broadway | July to September 2026 |
| 23 to 25 June | Kettering | Hallwood Road | July to September 2026 |
| 18 June 2026 | Kettering | Bath Road | July to September 2026 |
| 17 June 2026 | Kettering | Northumberland Road | July to September 2026 |
| 16 to 18 June | Irthlingborough | Musson Close | July to September 2026 |
| 16 June 2026 | Barton Seagrave | Castle Way | July to September 2026 |
| 12 to 16 June | Irthlingborough | Fernmoor Drive | July to September 2026 |
| 11 June 2026 | Irchester | Baker Crescent | July to September 2026 |
| 10 June 2026 | Higham Ferrers | Celtic Close | July to September 2026 |
| 9 June 2026 | Finedon | Thrapston Road | July to September 2026 |
| 8 June 2026 | Wellingborough | Owen Close | July to September 2026 |
| 4 June 2026 | Wellingborough | Hatton Park Road | July to September 2026 |
| 3 June 2026 | Wellingborough | Longfellow Road | July to September 2026 |
| 3 June 2026 | Wellingborough | Goldsmith Road | July to September 2026 |
| 2 June 2026 | Wellingborough | Birchfield Road | July to September 2026 |
| 1 June 2026 | Wellingborough | Chester Road | July to September 2026 |
| 29 May 2026 | Earls Barton | Clarke Court | July to September 2026 |
| 29 May 2026 | Irchester | Wollaston Road | July to September 2026 |
| 28 May 2026 | Wollaston | Park Street | July to September 2026 |
| 28 May 2026 | Rushden | Tennyson Road | July to September 2026 |
| 27 May 2026 | Earls Barton | Wellingborough Road | July to September 2026 |
| 26 May 2026 | Rushden | Gloucester Crescent | July to September 2026 |
| 21 May 2026 | Rushden | Irchester Road | July to September 2026 |
| 21 May 2026 | Wollaston | Irchester Road | July to September 2026 |
| 20 May 2026 | Wollaston | Hinwick Road | July to September 2026 |
Last updated 01 September 2026