LEVI Project works start and go live dates

The build programme for the LEVI project with Connected Kerb is underway. This is installing public EV chargers both on-street and in the council’s car parks over the next three to five years. The expected start dates for civils works on site to install new EV chargepoints are shown below. The dates when the EV chargepoints are expected to be connected to the grid and ready for service are also shown. Dates may be subject to change.

View the full list of approved EV chargepoint sites.

An interactive map showing approved sites, as well as planned sites where the council is inviting feedback on proposals, can be viewed on Connected Kerb.

Expected build works start dateLocationStreet nameExpected EV chargepoint availability date
31 August to 14 SeptemberAldwincle Opposite 55 Main Street October to December 2026
1 September to 16 SeptemberCorby Willow Brook Road (North) October to December 2026
1 September to 16 SeptemberCorby Willow Brook Road (South) October to December 2026
4 September to 17 SeptemberCorby Kingsthorpe Avenue October to December 2026
8 September to 21 SeptemberCorby Glastonbury Road October to December 2026
10 September to 23 SeptemberCorby Lyveden Way October to December 2026
27 August to 14 SeptemberCorby Shakespeare Way October to December 2026
9 September to 22 SeptemberCorby Newark Drive October to December 2026
11 September to 24 SeptemberCorby Headway October to December 2026
30 June to 2 JulyKetteringWhiteford DriveJuly to September 2026
26 to 30 JuneKetteringDahlia RoadJuly to September 2026
25 to 29 JuneKetteringIvy RoadJuly to September 2026
24 to 26 JuneKetteringBroadwayJuly to September 2026
23 to 25 JuneKetteringHallwood RoadJuly to September 2026
18 June 2026KetteringBath RoadJuly to September 2026
17 June 2026KetteringNorthumberland RoadJuly to September 2026
16 to 18 JuneIrthlingborough Musson CloseJuly to September 2026
16 June 2026Barton SeagraveCastle WayJuly to September 2026
12 to 16 JuneIrthlingborough Fernmoor DriveJuly to September 2026
11 June 2026IrchesterBaker CrescentJuly to September 2026
10 June 2026Higham FerrersCeltic CloseJuly to September 2026
9 June 2026FinedonThrapston RoadJuly to September 2026
8 June 2026WellingboroughOwen CloseJuly to September 2026
4 June 2026WellingboroughHatton Park RoadJuly to September 2026
3 June 2026WellingboroughLongfellow RoadJuly to September 2026
3 June 2026WellingboroughGoldsmith RoadJuly to September 2026
2 June 2026WellingboroughBirchfield RoadJuly to September 2026
1 June 2026WellingboroughChester RoadJuly to September 2026
29 May 2026Earls BartonClarke CourtJuly to September 2026
29 May 2026IrchesterWollaston RoadJuly to September 2026
28 May 2026WollastonPark Street July to September 2026
28 May 2026RushdenTennyson RoadJuly to September 2026
27 May 2026Earls BartonWellingborough RoadJuly to September 2026
26 May 2026RushdenGloucester CrescentJuly to September 2026
21 May 2026RushdenIrchester RoadJuly to September 2026
21 May 2026WollastonIrchester RoadJuly to September 2026
20 May 2026WollastonHinwick RoadJuly to September 2026

Last updated 01 September 2026